Delaware (State or Other Jurisdiction of Incorporation) |
001-13783 (Commission File Number) |
76-0542208 (I.R.S. Employer Identification Number) |
Exhibit Number | Description | |
Exhibit 10.1* | Subcontract, dated June 17, 2009, by and between IES
Commercial, Inc. and Manhattan Torcon A Joint Venture. |
|
Exhibit 10.2 | Letter Agreement, dated November 4, 2009, by and between
Integrated Electrical Services, Inc., IES Commercial, Inc.
and Manhattan Torcon A Joint Venture. |
|
Exhibit 99.1 | Press Release dated November 24, 2009. |
* | Portions of this exhibit have been omitted pursuant to a request for confidential treatment. |
INTEGRATED ELECTRICAL SERVICES, INC. |
||||
Date: November 24, 2009 | /s/ William L. Fiedler | |||
William L. Fiedler | ||||
General Counsel |
Exhibit Number | Description | |
Exhibit 10.1* | Subcontract, dated June 17, 2009, by and between IES
Commercial, Inc. and Manhattan Torcon A Joint Venture. |
|
Exhibit 10.2 | Letter Agreement, dated November 4, 2009, by and between
Integrated Electrical Services, Inc., IES Commercial, Inc.
and Manhattan Torcon A Joint Venture. |
|
Exhibit 99.1 | Press Release dated November 24, 2009. |
* | Portions of this exhibit have been omitted pursuant to a request for confidential treatment. |
Date: June 17,2009
|
Subcontractor: IES Commercial, Inc. | |
Project Name: USAMRIID Replacement
|
Address: 500 Woodlake Drive,
Suite 150 Chesapeake, Virginia 23320 |
|
Address: Ft. Detrick, Maryland
|
Attention: Mike Valentine | |
Project No.: 3239
|
Telephone No.: 757-424-5164 | |
Cost Code: 160.160010
|
Fax No.: 757-424-7145 |
MANHATTAN TORCON A JOINT VENTURE GENERAL
PROVISION
|
Page(s) 1 13, Dated: June 17, 2009 | |
MODIFICATIONS TO GENERAL PROVISIONS
|
Page(s) 1, Dated: June 29, 2009 | |
EXHIBIT A Scope of Subcontractors Work
|
Page(s) 1 7 | |
EXHIBIT Al Contract Documents
|
Page(s) 1 52 | |
EXHIBIT B Payment and Performance Bonds
|
Page(s) 1 2 | |
EXHIBIT C Insurance Requirements
|
Page(s) 1 14 | |
EXHIBIT D Miscellaneous Provisions
|
Page(s) 1 29 |
Subcontractor
|
MTJV | |
SUBCONTRACTOR NAME
|
MANHATTAN TORCON A JOINT VENTURE | |
/s/ MICHAEL J. CALIEL
|
/s/ TED M. BAKER | |
Signature
|
Signature | |
Michael J. Caliel
|
Ted M. Baker | |
Printed Name
|
Printed Name | |
President
|
Executive Vice President | |
Title
|
Title | |
June 30, 2009
|
July 9, 2009 | |
Date:
|
Date: |
Page 1 of 13
Page 2 of 13
Page 3 of 13
Page 4 of 13
Page 5 of 13
Page 6 of 13
(a) | Subcontractor has failed to perform its obligations under the Subcontract or otherwise is in default under the Subcontract or the Contract Documents; | ||
(b) | If any part of such payment is attributable to Work which is not performed in accordance with the Contract Documents; provided, however, payment will be made for the portions of the Work which have been performed in accordance with the Contract Documents; |
Page 7 of 13
(c) | Subcontractor or any subcontractor has failed to make payments promptly to any lower-tier subcontractor, as applicable, or to pay for material or labor used in the Work for which Subcontractor has received payment; | ||
(d) | Subcontractor has failed to provide the revised Schedule of Values with the Application for Payment; | ||
(e) | Subcontractor has suspended the Work other than as authorized by Owner or the Contract; or | ||
(f) | Subcontractor has filed a voluntary petition for protection for relief under or a petition has been filed placing Subcontractor under the protection of the bankruptcy laws of the United States and Subcontractor has not (1) notified MTJV that Subcontractor has the necessary capacity and resources to finish the Work and honor the Subcontract and will dismiss such petition and remove itself from bankruptcy protection within 90 days of the filing or (2) affirmed and had the bankruptcy court approve its obligations under this Subcontract to MTJV and evidence Subcontractors ability to perform this Subcontract to MTJVs reasonable satisfaction; or | ||
(g) | Subcontractor has failed to provide or maintain required insurance and bonds; or | ||
(h) | MTJV determines, in good faith, that Subcontractor has breached any other agreement it might have with MTJV on any other project. |
(a) | all Employees at the Project site or engaged in the Work and all other persons who may be affected by the Work or are in proximity to the Work; | ||
(b) | the Work and all materials and equipment to be incorporated into the Work, whether in storage on or off the Project site, under the care, custody or control of the Subcontractor or any lower-tier subcontractors; | ||
(c) | other property at the Project site or adjacent thereto, including all existing improvements not part of the Work, trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction; | ||
(d) | the Work of MTJV, the Owner or other separate contractors; and | ||
(e) | all tenants and visitors to the Project. |
(a) | Workers Compensation and Employers Liability; |
Page 8 of 13
(b) | Commercial General Liability (including Blanket Contractual Liability, Products and Completed Operations, Bodily Injury (including sickness, disease or death of any person other than Subcontractors employees) and Personal Injury and Broad Form Property Damage); | ||
(c) | Commercial Auto Liability; | ||
(d) | Umbrella Liability. |
Page 9 of 13
Page 10 of 13
Page 11 of 13
Page 12 of 13
Subcontractor
|
MTJV | |
IES COMMERCIAL, INC.
|
MANHATTAN TORCON A JOINT VENTURE | |
/s/ MICHAEL J. CALIEL
|
/s/ TED M. BAKER | |
Signature
|
Signature | |
Michael J. Caliel
|
Ted M. Baker | |
Printed Name
|
Printed Name | |
President
|
Executive Vice President | |
Title
|
Title | |
Date: June 30, 2009
|
Date: July 9, 2009 | |
Page 13 of 13
1. | Article 2.3.4; end of first sentence, after including, insert; up to $1,500,000, per claim, of. | ||
2. | Article 2.5.1 (iv); last sentence, after liability, insert; for consequential damages or. |
IES Commercial, Inc.
|
Manhattan Torcon A Joint Venture | |
/s/ MICHAEL J. CALIEL
|
/s/ TED M. BAKER | |
Michael J. Caliel, President
|
Ted M. Baker, Executive Vice President | |
June 30, 2009
|
July 9, 2009 | |
Date
|
Date |
Division One
|
GENERAL REQUIREMENTS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract, including Commissioning; | |
Section 02 41 00
|
DEMOLITION and DECONSTRUCTION, Pertinent portions thereof applicable to the work to be performed under this Subcontract; | |
Section 03 31 00.00 10
|
CAST-IN-PLACE STRUCTURAL CONCRETE, Pertinent portions thereof applicable to the work to be performed under this Subcontract; | |
Section 03 31 05
|
CONTAINMENT CONCRETE, Pertinent portions thereof applicable to the work to be performed under this Subcontract; | |
Section 05 50 10.00
|
SPECIAL METAL FABRICATIONS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 06 10 00
|
ROUGH CARPENTRY, Pertinent portions thereof applicable to the work to be performed under this Subcontract; | |
Section 07 14 00
|
FLUID-APPLIED WATERPROOFING, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 07 60 00
|
FLASHING AND SHEET METAL, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 07 81 00
|
SPRAY-APPLIED FIREPROOFING, Pertinent portions thereof applicable to the work to be performed under this Subcontract; | |
Section 07 84 00
|
FIRESTOPPING, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 07 92 00
|
JOINT SEALANTS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 08 39 15
|
PNEUMATIC AIR PRESSURE RESISTANT DOORS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 08 31 13
|
ACCESS DOORS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 08 71 00
|
DOOR HARDWARE, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 08 71 01
|
SECURITY DOOR HARDWARE (FOUO), Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 09 69 13
|
RIGID GRID ACCESS FLOORING, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 09 90 00
|
PAINTING AND COATINGS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Division 10
|
SPECIALTIES, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 1 of 7 |
Division 11
|
EQUIPMENT, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Division 12
|
FURNISHINGS, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Division 13
|
SPECIAL CONSTRUCTION, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Division 14
|
CONVEYING EQUIPMENT, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Division 21
|
FIRE SUPPRESSION, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Division 22
|
PLUMBING, Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Division 23
|
HEATING, VENTILATING AND AIR CONDITIONING, Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Division 25
|
INTEGRATED AUTOMATION, Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Division 26
|
ELECTRICAL, Complete; | |
Division 27
|
COMMUNICATIONS, Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Volume 9 & Div. 28
|
ELECTRONIC SAFETY and SECURITY SYSTEM (FOUO), Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Section 31 00 00
|
EARTHWORK, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; | |
Section 33 70 02.00 10
|
ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND, Complete; | |
Section 33 82 00
|
TELECOMMUNICATIONS OUTSIDE PLANT (OSP), Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Division 41
|
MATERIAL PROCESSING AND HANDLING EQUIPMENT, Pertinent portions thereof applicable to the Work being performed under this Subcontract; | |
Volume 7 & 8
|
APPENDIX A, B, & C, Pertinent portions thereof applicable to the Work to be performed under this Subcontract; |
1. | General contract options included in this subcontract: 1 thru 3, 5 thru 8, 10 thru 14, 16 thru 20, 22, 23, 25, 26, 27, 30 thru 50. | |
2. | Compliance with and implementation of the Quality Control, Safety, Environmental Protection, and Waste Management programs applicable to the Work. | |
3. | Submittals including, but not limited to, product literature and catalog cuts, site-specific work plans, design calculations, mock-ups, guarantees, shop drawings, certificates, welding certificates, qualification statements, |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 2 of 7 |
samples, warrantee, clerical work, administrative and reproduction requirements for the Work. This subcontract agreement is based on the Equipment and Materials specified. Provide submittals for the Containment area mock up within 30 days of award. Provide submittals with certification by a registered architect or professional engineer where required. | ||
4. | Coordinate, document, and comply with LEED requirements including, but not limited to, low emitting material content, recycled material content, construction waste management and Local manufacturing requirements. | |
5. | All trash, debris, and spoils generated by the Work will be cleaned up daily, broom swept and removed to onsite dumpsters. This Subcontractor shall sort and place all materials in dumpsters as identified and required by the Waste Management Program. Violation of not pre-sorting materials shall result in the work being performed on behalf of the Subcontractor, at the Subcontractors expense, on premium time. | |
6. | Coordinate the Work with other features of the work. Provide complete, integrated, and operable systems in accordance with contract requirements. | |
7. | Protection of the Work and adjacent surfaces while performing the Work. | |
8. | Material and equipment handling for the Work including, but not limited to, transporting, unloading, distribution, storage, hoisting, rigging, and relocations as work progresses. | |
9. | Ladders, scaffolds, and work platforms for the Work. | |
10. | Task lighting for this subcontractors work as required. | |
11. | Compliance with work restrictions and site security requirements including, but not limited to off-site parking, badging of employees, and sponsoring of visitors and unbadged personnel. | |
12. | All trade-specific permit and inspection fees. | |
13. | Coordinate with regulatory agencies for connections, shut-downs, disruptions, repairs, and inspections to ensure timely performance of the Work. | |
14. | Cutting and patching where the need for such is caused by Subcontractors untimely, uncoordinated or inaccurate performance of the Work. Cutting, patching and core drilling for the Work shall include protection, concrete slurry and water containment, and clean up of all core drilling, cutting, and patching operations, in addition to restoration of the patched area. | |
15. | Compliance with safety requirements of both MOSHA & USACOE. All work requiring welding or burning will not commence unless a Hot Work Permit has been issued. | |
16. | Provide MTJV with a subcontracting small business plan in accordance with 00100 Section 1.5.3.f and related FAR clauses including a plan to meet subcategories. Perform required reporting on eSRS with proper MTJV contact copied on the submission. This subcontractor is aware of the goals for participation by Small Businesses and Small Disadvantaged Businesses in accordance with the Contract Documents, and has diligently provided outreach to such businesses, and will award 20% of the value of this subcontract to recognized firms in accordance with this provision. Provide evidence of outreach in obtaining this goal. | |
17. | Provide all labor, material and equipment to accomplish the related requirements of Volume 9: Security specifications and the security drawings associated with the Work. | |
18. | Provide temporary power, lighting, re-lamping, re-ballasting and replacement of defective Work required to support the construction of the project, including, but not limited to, power, lighting, equipment hook-up, tower crane connection, welder connections, hoisting connections and other hook-ups related to supporting the Work. Temporary power and lighting shall be removed once the permanent systems are available for use. Provide tie-in to permanent power site system on premium time. Coordinate with MTJV, the Owner, and Fort Detrick for requirements for tie in. | |
19. | Provide electrical and communication service and distribution for MTJVs and Owners on site trailer complexes. Provide power, lighting, receptacles, phone, and data requirements for these complexes, including maintenance, re-lamping, re-ballasting, etc. as required through the life of the project. NOTE: Communications for the field offices is part of the base contract electrical work, and not part of the Communications alternate pricing. Provide connections from the Utilidor Power Project to transfer the temporary power initially serving the project to the Utilidor Power once the Utilidor work can support the temporary or permanent service. | |
20. | A full scale mock up of a High Containment area shall be constructed on site, and shall be ready for review by the Owner no later than December 7, 2009. This subcontractor has included all costs to complete the mock up, |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 3 of 7 |
for the related scope of work and components included herein. Provide other mock-ups and samples that interface the work with other features of work. | ||
21. | Provide 3 dimensional electronic drawings for utility coordination in the Containment areas. Provide hard copies and electronic files to the Containment Coordinator, for electronic coordination of the Containment area. The software for the electronic drawings shall be as determined by the Containment Coordinator. | |
22. | Complete all required documentation for commissioning and shall provide required labor to operate all equipment and systems related to start up, testing, training, demonstration, and commissioning. | |
23. | Arrange for all inspections, tests, fees, permits and licenses and file all plans or other data required in connection with this work in accordance with all codes, regulations, and ordinances required. | |
24. | The following records, as a minimum, must be kept by the Subcontractor on site: |
a. | Record documents of the Work. | ||
b. | Complete operation and maintenance manuals. | ||
c. | Other documents required by the contract and specifically section 01 72 00. |
These records are subject to regular audit by MTJV and the Owner. At the completion of the project and prior to final payment the above documents as well as CAD record documents are to be indexed and provided to MTJV and the Owner. | ||
25. | Provide all seismic supports, bracing, connections, vibration isolation, including submittals. Provide inspection documentation and certifications that systems have been installed in accordance with the special inspection seismic requirements | |
26. | Participate in the development of the CPM schedule for the project with cost-loaded activities for the Work. The schedule shall be updated monthly, for the work included herein, as a pre-requisite for approval of progress payments. | |
27. | Full-time on-site Project Manager and Superintendent for the full duration of the project. Both the Project Manager and Superintendent shall have the authority to commit resources and make commitments on behalf of the subcontractor. The Superintendent shall have authority and responsibility for all work performed under this subcontract including supervision of all craft and foreman and subcontractors. This subcontractor shall also provide a full-time Quality Control (QC) individual that will perform the duties as required by the specifications. The QC individual can have other duties. Provide additional exclusive project management and supervision for communications and security systems installations if alternates are accepted. | |
28. | Coordination drawings and participation in coordination meetings for coordination and interfacing of MEP work, Laboratory Work and all other features of work. Provide complete, integrated, and operable systems in accordance with contract requirements. | |
29. | Layout, coordinate, furnish and install sleeves and other penetrations for the Work, including the development and submittal of the sleeve layout in compliance with the special details for Containment area. Provide escutcheons, caulking, and sealants, associated with the Work. | |
30. | All rough-ins and connections to equipment furnished by others, including advance coordination to assure service is provided in accordance with manufacturers requirements and a complete installation. | |
31. | Provide equipment data information per section 01 00 00 paragraph 1.7 and Tagging and submittal requirements per 01 20 00 for all furnished equipment installed by this Subcontractor, at the time of installation and commissioning with appropriate tagging. | |
32. | Provide all layout from vertical and horizontal control lines. | |
33. | Electrical site work complete; including but not limited to, site lighting, site concrete for light foundations and pole bases, camera pole bases, electrical, communications, security and cable TV duct banks. This includes, but is not limited to, test pits, layout, saw cutting, trenching, excavation, backfill, concrete, rebar, manholes, hand holes, gratings, accessories, pull boxes, frames and covers, direct buried cables, and anchor bolts. Protect excavated soil for re-use as backfill. Provide suitable backfill if none available on-site. Spoils shall be loaded and placed at an on-site stockpile for disposal by others. All exposed concrete shall have a rubbed finish acceptable to the owner. | |
34. | Provide shop drawings with coordinated size and locations for housekeeping pads. Provide layout for all housekeeping pads. | |
35. | Firestopping, smoke sealing, and fire sealants for all penetrations associated with the work. |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 4 of 7 |
36. | Perform grouting of all work and equipment. | |
37. | Connection of all heat tracing, heat trace control and alarm panels, including site piping tracing and temporary utility piping heat tracing. | |
38. | Provide cathodic protection for engineered piping systems, coordinated with the Mechanical Subcontractor and/or Utility door Contractor. | |
39. | All miscellaneous brackets, clips, framing, blocking, inserts, racks, and accessories required for supporting electrical work. Where supports are to be mounted on fireproofed members, the Subcontractor shall assure that the mounting hardware is in place prior to fireproofing and provide the protection of the Work from the fireproofing Work. When hangers and supports are installed after the application of the spray fireproofing, this Subcontractor shall scrape and remove the spray fireproofing as required for the attachment of the hanger or support. This subcontractor shall be responsible for the repair and the applicable costs associated with the patching. | |
40. | Coordinate the Work with the sequencing and progression of the building installation to ensure that the Work is able to fit through the permanent openings and doors without any leave outs. If a leave-out cannot be avoided, provide a written listing of the locations, equipment type, equipment size, location and proposed pathway by September 30, 2009. | |
41. | Provide special supports required for all fixtures and equipment not indicated on the structural drawings, including but not limited to support for custom light fixtures (see E3.05). | |
42. | Provide raceways and cable tray for communications and security system throughout the facility outside of communication rooms. In addition, specifically provide raceways, cabletray, backboxes and coordination, for BMS, communication systems, and security systems in the High Containment BSL-4 Area as indicated. | |
43. | Provide maintenance, operation and extended warranty requirements to use the permanent systems to support the completion of the project, including re-lamping and ballast replacement where required. | |
44. | Provide the emergency power system, equipment, and generator set complete, including exhaust piping, muffler, fuel lines, and testing, test fuel, and refilling of the fuel prior to turn over to the Owner. Provide maintenance and extended warranties to comply with the Contract Documents. Allow for periodic exercising of the generator during commissioning. | |
45. | Receive, store, mount and connect VFDs including support structure design and support installation. | |
46. | Install loose motor starters, disconnects and fuses provided with other features of work. Provide loose motor starters, disconnects and fuses not provided by other features of work as indicated on the electrical drawings. | |
47. | Provide grounding system including testing, excavation, backfill, connections to structure, foundations, equipment, access flooring, and site equipment. | |
48. | Provide conduits, pathways and raceways for the security feature of work. Include exterior excavations, conduits, backfill, and concrete foundations for exterior cameras, light poles and card readers to support the security requirements. | |
49. | Provide fire pump service ductbanks, electrical service, panel installation power, lighting, fire alarm, communication and security rough-ins and connections. | |
50. | Provide fire alarm system complete, including under floor system in rooms Room Nos. 5SA210 and 3SA401 per specification section 09 69 13. | |
51. | Provide lightning protection system complete, including protection of exhaust stacks and roof equipment. Coordinate mounting details with the Roofing Subcontractor, and provide all required sealants, special mounting hardware, or other components as required, with the exception of roof flashing or boots. | |
52. | Provide potting of all conduit and raceways, for all complete systems included in this scope of work. | |
53. | Provide conduit for BMS, Security, and Communications systems within the BSL-4 Containment areas in addition to conduit required for Division 26. | |
54. | Provide empty conduit for control tubing for APR Door System per details A3 & A5/P5.06. Coordinate conduit locations and configuration with all associated Subcontractors. Provide electrical back boxes, conduit, raceways for all electronic door hardware. | |
55. | Furnish, coordinate and lay out access doors for all components being provided and requiring access. | |
56. | Provide raceways and wiring for elevator, fire pump, sump pumps, and similar status panels as required by the contract documents. |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 5 of 7 |
57. | Provide adequate and supplemental lighting as required to facilitate owner review and approval of architectural mock ups. | |
58. | All identification including, but not limited to, painting, labeling, identification markers and nameplates, including color coding requirements for fire alarm and high voltage conduit systems. | |
59. | Provide touch up paint and galvanizing touch up where required. | |
60. | Factory and field testing, including independent acceptance testing, start up, demonstration and training. | |
61. | Conduit, back boxes, wiring, and terminations, including but not limited to pathways, sequencing and coordination of the Work with the systems furniture, lab casework, fume hoods, millwork and specialty equipment. | |
62. | Power, control wiring, transformers, connection and mounting of control panels for electrically operated equipment including, but not limited to, overhead doors, projection screens, door operators, sensor operated flush valves, roller shades, loading dock levelers, Monorails, and similar equipment. | |
63. | Provide power to BAS control panels. | |
64. | Provide UPS components and system complete. | |
65. | Conduit, back boxes, wiring, and terminations, including low voltage connections for door hardware. | |
66. | Provide fire treated plywood backboards where required for all equipment. | |
67. | Cut and make safe any existing power utilities required to facilitate the demolition or relocation of existing structures. Include the removal of site poles, lighting and the transformer noted on the civil demolition drawings. | |
68. | Provide conduit and rough-ins for animal watering systems, mount and connect panels. Coordinate the installation requirements with the Division 22 Subcontractor. | |
69. | The penal sum of the bonds will be required in incremental values, totaling the Subcontract amount (as the same may be adjusted from time to time pursuant to the Subcontract), as follows: (1) fifty percent (50%) of the Subcontract amount at the time of execution of the Subcontract, (2) twenty-five percent (25%) of the Subcontract amount in July 2010 and (3) twenty-five percent (25%) of the Subcontract amount in July 2011. In addition, upon execution of the Subcontract, Subcontractor shall provide a written commitment from the surety that it will provide a Consent of Surety in the additional amounts required at the times stated above. |
1. | Interior concrete house keeping pads | |
2. | Concrete foundation for generator | |
3. | Animal Watering System |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 6 of 7 |
1. | Delete Payment and Performance Bond |
DEDUCT | $ | * | **** | |||||||
2. | Provide for a credit (subject to final audit) for the Contractor
Controlled Insurance Program (CCIP) being administered by Rooney
Insurance Agency for the Project. The insurance coverage to be
provided by MTJV under the CCIP is as described in Exhibit C.
Change proposal pricing will include Subcontractors applicable
insurance values with a breakout for the value in the change
proposal. |
DEDUCT | $ | * | **** | |||||||
3. | Delete excavation and backfill |
DEDUCT | $ | * | **** | |||||||
4. | Delete ductbank (conduit, concrete) |
DEDUCT | $ | * | **** | |||||||
5. | Delete architectural exposed caulking and sealing |
DEDUCT | $ | * | **** | |||||||
6. | Delete firestopping and fire sealants |
DEDUCT | $ | * | **** | |||||||
7. | Delete the requirement to provide cathodic protection |
DEDUCT | $ | * | **** | |||||||
8. | Delete communications for office trailer complexes |
DEDUCT | $ | * | **** | |||||||
9. | Delete conduit for BMS in the BSL-4 High Containment Area |
DEDUCT | $ | * | **** | |||||||
10. | Delete presorting requirement for construction waste |
DEDUCT | $ | * | **** | |||||||
11. | Add Division 27 Communications (complete) |
ADD | $ | * | **** | |||||||
12. | Add Section 28 20 01.00 10 Electronic Safety and Security (Complete) |
ADD | $ | * | **** |
1. | The Subcontract (including all attached and referenced Exhibits). | |
2. | The Agreement between the MTJV and the Owner Agreement) in its entirety including all referenced and included terms and conditions. | |
3. | Exhibits enumerated and attached to the Agreement. | |
4. | All Amendments issued prior to and all modifications issued after execution of the Agreement. | |
5. | Alternates as selected and incorporated herein. | |
6. | Unit Prices. | |
7. | Plans and Specifications as follows: |
Exhibit A, IES Commercial Inc., Scope of Work, USAMRIID Replacement | 7 of 7 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
CIVIL | ||||
C0.011 |
Cover Sheet-Civil/Landscaping-Phase 1 | 1/19/09 | ||
C0.021 |
Index of Drawings-Civil/Landscaping-Phase 1 | 1/19/09 | ||
C0.031 |
Overall Site Access Plan | 10/31/08 | ||
V1.100 |
Survey Plan-Overall -Phase 1 | 9/19/08 | ||
V1.101 |
Survey Area 1-Phase 1 | 9/19/08 | ||
V1.102 |
Survey Area 2-Phase 1 | 9/19/08 | ||
V1.103 |
Survey Area 3-Phase 1 | 9/19/08 | ||
V1.104 |
Survey Area 4-Phase 1 | 9/19/08 | ||
V1.105 |
Survey Area 5-Phase 1 | 9/19/08 | ||
VI. 106 |
Survey Area 6-Phase 1 | 9/19/08 | ||
V1.107 |
Survey Area 7-Phase 1 | 9/19/08 | ||
V1.108 |
Survey Area 8-Phase 1 | 9/19/08 | ||
V1.109 |
Survey Area 9-Phase 1 | 9/19/08 | ||
V1.109A |
Survey Area 9A-Phase l | 9/19/08 | ||
C1 .000 |
Overall Demolition Plan-Phase 1 | 9/19/08 | ||
C1 .001 |
Demolition Plan Area 1-Phase 1 | 9/19/08 | ||
C1 .002 |
Demolition Plan Area 2-Phase 1 | 9/19/08 | ||
C1.003 |
Demolition Plan Area 3-Phase 1 | 9/19/08 | ||
C1.004 |
Demolition Plan Area 4-Phase 1 | 9/19/08 | ||
C1.005 |
Demolition Plan Area 5-Phase 1 | 9/19/08 | ||
C1.006 |
Demolition Plan Area 6-Phase 1 | 9/19/08 | ||
C1.007 |
Demolition Plan Area 7-Phase 1 | 9/19/08 | ||
C1.008 |
Demolition Plan Area 8-Phase 1 | 9/19/08 | ||
C1.009 |
Demolition Plan Area 9-Phase 1 | 9/19/08 | ||
C1.020 |
Overall Utility Demolition/ Relocation Plan-Phase 1 | 10/31/08 | ||
C1 .021 |
Utility Demolition/Relocation Plan Area 1-Phase 1 | 9/19/08 | ||
C1.022 |
Utility Demolition/Relocation Plan Area 2-Phase 1 | 9/19/08 | ||
C1 .023 |
Utility Demolition/Relocation Plan Area 3-Phase 1 | 9/19/08 | ||
C1.024 |
Utility Demolition/Relocation Plan Area 4-Phase 1 | 9/19/08 | ||
C1.025 |
Utility Demolition/Relocation Plan Area 5-Phase 1 | 9/19/08 | ||
C1.026 |
Utility Demolition/Relocation Plan Area 6-Phase 1 | 9/19/08 | ||
C1.027 |
Utility Demolition/Relocation Plan Area 7-Phase 1 | 9/19/08 | ||
C1 .028 |
Utility Demolition/Relocation Plan Area 8-Phase 1 | 10/31/08 | ||
C1.029 |
Utility Demolition/Relocation Plan Area 9-Phase 1 | 9/19/08 | ||
C1.029A |
Utility Demolition/Relocation Plan Area 9A-Phase 1 | 10/31/08 | ||
C1.037 |
Overall Utility Demolition and Relocation Plan | 9/19/08 | ||
C1.100 |
Overall Site Plan-Phase 1 | 10/31/08 | ||
C1.101 |
Site Plan Area l-Phase 1 | 9/19/08 | ||
C1.102 |
Site Plan Area 2-Phase 1 | 9/19/08 | ||
C1.103 |
Site Plan Area 3-Phase 1 | 9/19/08 | ||
C1.104 |
Site Plan Area 4-Phase 1 | 9/19/08 | ||
C1.105 |
Site Plan Area 5-Phase 1 | 9/19/08 | ||
C1.106 |
Site Plan Area 6-Phase 1 | 9/19/08 | ||
C1.107 |
Site Plan Area 7-Phase 1 | 9/19/08 | ||
C1.108 |
Site Plan Area 8-Phase 1 | 9/19/08 | ||
C1.109 |
Site Plan Area 9-Phase 1 | 9/19/08 | ||
C1.200 |
Overall Grading Plan-Phase 1 | 9/19/08 | ||
C1.201 |
Grading Plan Area 1-Phase 1 | 9/19/08 | ||
C1.202 |
Grading Plan Area 2-Phase 1 | 9/19/08 | ||
C1.203 |
Grading Plan Area 3-Phase 1 | 9/19/08 | ||
C1.204 |
Grading Plan Area 4-Phase 1 | 9/19/08 | ||
C1.205 |
Grading Plan Area 5-Phase 1 | 9/19/08 | ||
C1.206 |
Grading Plan Area 6-Phase 1 | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 1 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
C1.207 |
Grading Plan Area 7-Phase 1 | 9/19/08 | ||
C1.208 |
Grading Plan Area 8-Phase 1 | 9/19/08 | ||
C1.209 |
Grading Plan Area 9-Phase 1 | 9/19/08 | ||
C1.209A |
Grading Plan Area 9A-Phase 1 | 10/31/08 | ||
C2.100 |
Site Enlargement Plan | 9/19/08 | ||
C2.101 |
Site Enlargement Plan | 9/19/08 | ||
C2.102 |
Site Enlargement Plan | 9/19/08 | ||
C2.103 |
Site Enlargement Plan | 9/19/08 | ||
C2.104 |
Site Enlargement Plan | 9/19/08 | ||
C2.105 |
Site Enlargement Plan | 9/19/08 | ||
C2.106 |
Site Enlargement Plan | 10/31/08 | ||
C3.000 |
Details-Phase 1 | 9/19/08 | ||
C3.001 |
Details-Phase 1 | 10/31/08 | ||
C3.002 |
Details-Phase 1 | 10/31/08 | ||
C3.003 |
Details-Phase 1 | 10/31/08 | ||
C3.020 |
Site Details | 9/19/08 | ||
C3.021 |
Site Details | 9/19/08 | ||
C3.022 |
Site Details | 10/31/08 | ||
C3.023 |
Site Details-Logistics Dock Ramp-Section Elevations | 9/19/08 | ||
C3.024 |
Site Details-Logistics Dumpster Dock-Section Elevations | 9/19/08 | ||
C3.025 |
Site Details-Logistics Dumpster Dock-Section Elevations | 9/19/08 | ||
C3.026 |
Site Details | 9/19/08 | ||
C3.028 |
Site Details-Logistics Dock Section Elevations | 9/19/08 | ||
C3.029 |
Site Details-Logistics Dock Section Elevations | 9/19/08 | ||
C5.100 |
Overall Site Utility Plan-Phase 1 | 10/31/08 | ||
C5.101 |
Site Utility Plan Area 1-Phase 1 | 10/31/08 | ||
C5.102 |
Site Utility Plan Area 2-Phase 1 | 10/31/08 | ||
C5.103 |
Site Utility Plan Area 3-Phase 1 | 10/31/08 | ||
C5.104 |
Site Utility Plan Area 4-Phase 1 | 10/31/08 | ||
C5.105 |
Site Utility Plan Area 5-Phase 1 | 10/31/08 | ||
C5.106 |
Site Utility Plan Area 6-Phase 1 | 10/31/08 | ||
C5.107 |
Site Utility Plan Area 7-Phase 1 | 10/31/08 | ||
C5.108 |
Site Utility Plan Area 8-Phase 1 | 10/31/08 | ||
C5.109 |
Site Utility Plan Area 9-Phase 1 | 10/31/08 | ||
C5.109A |
Site Utility Plan Area 9A-Phase 1 | 9/19/08 | ||
C5.200 |
Site Sanitary Profiles-Phase 1 | 10/31/08 | ||
C5.201 |
Site Sanitary Profiles-Phase 2 | 10/31/08 | ||
C5.400 |
Site Fire and Domestic Water Profiles-Phase 1 | 10/31/08 | ||
C5.500 |
Storm Water Profiles-Phase 1 | 10/31/08 | ||
C5.501 |
Storm Water Profiles-Phase 2 | 10/31/08 | ||
C7.100 |
Overall Soil Erosion and Sediment Control Plan-Phase 1 | 1/12/09 | ||
C7.100DA |
Overall Soil Erosion and Sediment Control Plan-Drainage Area Map-Phase 1 | 1/12/09 | ||
C7.101 |
Soil Erosion and Sediment Control Plan Area 1-Phase 1 | 1/12/09 | ||
C7.102 |
Soil Erosion and Sediment Control Plan Area 2-Phase 1 | 1/12/09 | ||
C7.103 |
Soil Erosion and Sediment Control Plan Area 3-Phase 1 | 1/12/09 | ||
C7.104 |
Soil Erosion and Sediment Control Plan Area 4-Phase 1 | 1/12/09 | ||
C7.105 |
Soil Erosion and Sediment Control Plan Area 5-Phase 1 | 1/12/09 | ||
C7.106 |
Soil Erosion and Sediment Control Plan Area 6-Phase 1 | 1/12/09 | ||
C7.107 |
Soil Erosion and Sediment Control Plan Area 7-Phase 1 | 1/12/09 | ||
C7.108 |
Soil Erosion and Sediment Control Plan Area 8-Phase 1 | 1/12/09 | ||
C7.108A |
Soil Erosion & Sediment Control Plan-Area 8A Phase | 1/19/09 | ||
C7.109 |
Soil Erosion and Sediment Control Plan Area 9-Phase 1 | 1/12/09 | ||
C7.109A |
Soil Erosion and Sediment Control Plan Area 9A-Phase 1 | 1/12/09 | ||
C7.120 |
Soil E&S Notes and Details-Phase 1 | 1/12/09 | ||
C7.121 |
Soil E&S Notes and Details-Phase 2 | 1/12/09 | ||
C7.122 |
Storm Water Management-Phase 1 | 1/12/09 | ||
L1.100 |
Overall Landscape Plan-Phase 1 | 9/19/08 | ||
L1.101 |
Landscape Plan Area 1-Phase 1 | 9/19/08 | ||
L1.102 |
Landscape Plan Area 2-Phase 1 | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 2 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
L1.103 |
Landscape Plan Area 3-Phase 1 | 9/19/08 | ||
L1.104 |
Landscape Plan Area 4-Phase 1 | 9/19/08 | ||
L1.105 |
Landscape Plan Area 5-Phase 1 | 9/19/08 | ||
L1.106 |
Landscape Plan Area 6-Phase 1 | 9/19/08 | ||
L1.107 |
Landscape Plan Area 7-Phase 1 | 9/19/08 | ||
L1.108 |
Landscape Plan Area 8-Phase 1 | 9/19/08 | ||
L1.109 |
Landscape Plan Area 9-Phase 1 | 9/19/08 | ||
L1.109A |
Landscape Plan Area 9A-Phase 1 | 9/19/08 | ||
L3.001 |
Landscape Details | 9/19/08 | ||
L3.002 |
Landscape Details | 9/19/08 | ||
L3.003 |
Landscape Details-Planting Schedule | 9/19/08 | ||
L3.004 |
Landscape Details-Planting Schedule | 9/19/08 | ||
B1.001 |
Subsurface Exploration Logs and Notes | 9/19/08 | ||
B1.002 |
Subsurface Exploration Logs | 9/19/08 | ||
B1.003 |
Subsurface Exploration Logs | 10/31/08 | ||
C0.011 |
Cover Sheet-Civil/Landscaping-Phase 2 | 10/31/08 | ||
C0.021 |
Index of Drawings-Civil/Landscaping-Phase 2 | 10/31/08 | ||
C0.031 |
Overall Site Access Plan | 10/31/08 | ||
V1.100 |
Survey Plan-Overall-Phase 2 | 9/19/08 | ||
V1.110 |
Survey Area 10-Phase 2 | 9/19/08 | ||
V1.111 |
Survey Area 1l-Phase 2 | 9/19/08 | ||
V1.112 |
Survey Area 12-Phase 2 | 9/19/08 | ||
V1.113 |
Survey Area l3-Phase 2 | 9/19/08 | ||
V1.114 |
Survey Area l4-Phase 2 | 9/19/08 | ||
V1.115 |
Survey Area 15-Phase 2 | 9/19/08 | ||
V1.116 |
Survey Area 16-Phase 2 | 9/19/08 | ||
C1.000 |
Overall Demolition Plan-Phase 2 | 9/19/08 | ||
C1.010 |
Demolition Plan Area 10-Phase 2 | 9/19/08 | ||
C1.011 |
Demolition Plan Area 11-Phase 2 | 9/19/08 | ||
C1.012 |
Demolition Plan Area 12-Phase 2 | 9/19/08 | ||
C1.013 |
Demolition Plan Area 13-Phase 2 | 9/19/08 | ||
C1.014 |
Demolition Plan Area 14-Phase 2 | 9/19/08 | ||
C1.015 |
Demolition Plan Area 15-Phase 2 | 9/19/08 | ||
Cl.016 |
Demolition Plan Area 16-Phase 2 | 9/19/08 | ||
C1.020 |
Overall Utility Demolition and Relocation Plan-Phase 2 | 10/31/08 | ||
C1.030 |
Utility Demolition/Relocation Plan Area 10-Phase 2 | 9/19/08 | ||
C1.031 |
Utility Demolition/Relocation Plan Area 11-Phase 2 | 9/19/08 | ||
C1.032 |
Utility Demolition/ Relocation Plan Area 12-Phase 2 | 10/31/08 | ||
C1.033 |
Utility Demolition/ Relocation Plan Area 13-Phase 2 | 10/31/08 | ||
C1 .034 |
Utility Demolition/ Relocation Plan Area 14-Phase 2 | 10/31/08 | ||
C1 .035 |
Utility Demolition/ Relocation Plan Area 15-Phase 2 | 10/31/08 | ||
C1 .036 |
Utility Demolition/ Relocation Plan Area 16-Phase 2 | 10/31/08 | ||
C1.100 |
Overall Site Plan-Phase 2 | 9/19/08 | ||
C1.110 |
Site Plan Area 10-Phase 2 | 9/19/08 | ||
C1.111 |
Site Plan Area 11-Phase 2 | 9/19/08 | ||
C1.112 |
Site Plan Area 12-Phase 2 | 9/19/08 | ||
C1.113 |
Site Plan Area 13-Phase 2 | 9/19/08 | ||
C1.114 |
Site Plan Area 14-Phase 2 | 9/19/08 | ||
C1.115 |
Site Plan Area 15-Phase 2 | 9/19/08 | ||
C1 116 |
Site Plan Area 16-Phase 2 | 9/19/08 | ||
C1.200 |
Overall Grading Plan-Phase 2 | 9/19/08 | ||
C1.210 |
Grading Plan Area 10-Phase 2 | 9/19/08 | ||
C1.211 |
Grading Plan Area 11-Phase 2 | 9/19/08 | ||
C1.212 |
Grading Plan Area 12-Phase 2 | 9/19/08 | ||
C1 .213 |
Grading Plan Area 13-Phase 2 | 9/19/08 | ||
C1.214 |
Grading Plan Area 14-Phase 2 | 9/19/08 | ||
C1 .215 |
Grading Plan Area 15-Phase 2 | 9/19/08 | ||
C1 .216 |
Grading Plan Area 16-Phase 2 | 9/19/08 | ||
C2.105 |
Site Enlargement Plan | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 3 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
C2.106 |
Site Enlargement Plan | 9/19/08 | ||
C3.000 |
Details-Phase 2 | 9/19/08 | ||
C3.001 |
Details-Phase 2 | 10/31/08 | ||
C3.002 |
Details-Phase 2 | 10/31/08 | ||
C3.003 |
Details-Phase 2 | 10/31/08 | ||
C3.020 |
Site Details | 9/19/08 | ||
C3.021 |
Site Details | 9/19/08 | ||
C3.022 |
Site Details | 10/31/08 | ||
C3.027 |
Site Details | 9/19/08 | ||
C5.100 |
Overall Site Utility Plan-Phase 2 | 10/31/08 | ||
C5.110 |
Site Utility Plan Area 10-Phase 2 | 10/31/08 | ||
C5.111 |
Site Utility Plan Area 11-Phase 2 | 10/31/08 | ||
C5.112 |
Site Utility Plan Area 12-Phase 2 | 10/31/08 | ||
C5.113 |
Site Utility Plan Area 13-Phase 2 | 10/31/08 | ||
C5.114 |
Site Utility Plan Area 14-Phase 2 | 10/31/08 | ||
C5.115 |
Site Utility Plan Area 15-Phase 2 | 10/31/08 | ||
C5.116 |
Site Utility Plan Area 16-Phase 2 | 10/31/08 | ||
C5.510 |
Stormwater Profiles-Phase 2 | 9/19/08 | ||
C5.511 |
Stormwater Profiles-Phase 2 | 9/19/08 | ||
C7.100 |
Overall Soil Erosion and Sediment Control Plan-Phase 2 | 10/31/08 | ||
C7.110 |
Soil Erosion and Sediment Control Plan Area 10-Phase 2 | 10/31/08 | ||
C7.111 |
Soil Erosion and Sediment Control Plan Area 11-Phase 2 | 10/31/08 | ||
C7.112 |
Soil Erosion and Sediment Control Plan Area 12-Phase 2 | 10/31/08 | ||
C7.113 |
Soil Erosion and Sediment Control Plan Area 13-Phase 2 | 10/31/08 | ||
C7.114 |
Soil Erosion and Sediment Control Plan Area 14-Phase 2 | 10/31/08 | ||
C7.115 |
Soil Erosion and Sediment Control Plan Area 15-Phase 2 | 10/31/08 | ||
C7.116 |
Soil Erosion and Sediment Control Plan Area 16-Phase 2 | 10/31/08 | ||
C7.130 |
Soil E&S Notes and Details-Phase 2 | 10/31/08 | ||
C7.131 |
Soil E&S Notes and Details-Phase 2 | 10/31/08 | ||
C7.132 |
Stormwater Management Phase 2 | 10/31/08 | ||
L1.100 |
Overall Landscape Plan Phase 2 Landscape Plan Area 10-Phase 2 | 9/19/08 | ||
L1.110 |
Landscape Plan Area 10 Phase 2 | 9/19/08 | ||
L1.111 |
Landscape Plan Area l1 Phase 2 | 9/19/08 | ||
L1.112 |
Landscape Plan Area 12-Phase 2 | 9/19/08 | ||
L1.113 |
Landscape Plan Area 13-Phase 2 | 9/19/08 | ||
L1.114 |
Landscape Plan Area 14-Phase 2 | 9/19/08 | ||
L1.115 |
Landscape Plan Area 15-Phase 2 | 9/19/08 | ||
L1.116 |
Landscape Plan Area 16-Phase 2 | 9/19/08 | ||
L3.001 |
Landscape Details | 9/19/08 | ||
L3.002 |
Landscape Details | 9/19/08 | ||
L3.003 |
Landscape Details-Planting Schedule | 9/19/08 | ||
L3.004 |
Landscape Details-Planting Schedule | 9/19/08 | ||
B1.001 |
Subsurface Exploration Logs and Notes | 9/19/08 | ||
B1.002 |
Subsurface Exploration Logs | 9/19/08 | ||
B1.003 |
Subsurface Exploration Logs | 9/19/08 | ||
CSO.011 |
Cover Sheet-Civil Security-Phase 1 | 10/31/08 | ||
CSO.021 |
Index of Drawings-Civil Security-Phase 1 | 9/19/08 | ||
CS0.011 |
Cover Sheet-Civil Security-Phase 2 | 9/19/08 | ||
CSO.021 |
Index of Drawings-Civil Security-Phase 2 | 9/19/08 | ||
ARCHITECTURAL | ||||
A0.011 |
Cover Sheet-Architectural-Part 1 | 1/19/09 | ||
A0.021 |
Index of Drawings-Architectural-Part 1 | 1/19/09 | ||
A0.031 |
General Information | 10/31/08 | ||
A0.20 |
Basement and Tunnel Part 5E-Key Plans | 1/19/09 | ||
A0.21 |
Floors 1 and 2-Key Plans | 1/19/09 | ||
A0.21-X |
Floors 1 and 2 Key Plans-(Bid Option #03) | 1/19/09 | ||
A0.23 |
Floors 3 and 4 Key Plans | 1/19/09 | ||
A0.24 |
Floor 4 and Floor 5 Radiation Shielding Key Plan | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 4 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A0.25 |
Floor 5 and 6 Key Plans | 10/31/08 | ||
A0.26P |
Floor 6P Key Plan | 10/31/08 | ||
A0.27 |
Roof Key Plan | 10/31/08 | ||
A0.31 |
Life Safety Review | 1/19/09 | ||
A0.32 |
Life Safety Review | 9/19/09 | ||
A0.404 |
Basement Life Safety Plan Parts 4, 5 and SE Tunnel | 1/19/09 | ||
A0.409 |
Basement Life Safety Plan Part 9 | 1/19/09 | ||
A0.411 |
Floor 1 Life Safety Plan Parts 1 to 5 | 1/19/09 | ||
A0.411-X |
Floor Life Safety Plan Parts 1 to 5-(Bid Option #03) | 1/19/09 | ||
A0.416 |
Floor 1 Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.421 |
Floor 2 Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.421-X |
Floor 2 Life Safety Plan Part 1 to 5-(Bid Option #03) | 10/31/08 | ||
A0.426 |
Floor 2 Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.42TZ1 |
Floor 2 Transition Zone Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.42TZ1-X |
Floor 2 Transition Zone Life Safety Plan Parts 1 to 5 (Bid Option #03) | 10/31/08 | ||
A0.431 |
Floor 3 Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.436 |
Floor 5 Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.441 |
Floor 4 Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.446 |
Floor 4 Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.44TZ1 |
Floor 4 Transition Zone Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.451 |
Floor 5 Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.456 |
Floor 5 Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.461 |
Floor 6 Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.466 |
Floor 6 Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.46P1 |
Floor of Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.46P6 |
Floor of Life Safety Plan Parts 6 to 9 | 10/31/08 | ||
A0.471 |
Roof Life Safety Plan Parts 1 to 5 | 10/31/08 | ||
A0.476 |
Roof Life Safety Plan Parts 6 to 9 | 9/19/08 | ||
A1.04 |
Basement Plan Part 4 | 9/19/08 | ||
A1.05 |
Basement Plan Part 5 | 10/31/08 | ||
A1.05E |
Basement Plan Part SE Tunnel | 10/31/08 | ||
A1.09 |
Basement Plant Part 9 | 1/19/09 | ||
A1.11 |
Floor 1 Plan Part 1 | 10/31/08 | ||
A1.11-X |
Floor 1 Plan Part 1-(Bid Option #03) | 12/1/08 | ||
A1.12 |
Floor 1 Plan Part 2 | 9/19/09 | ||
A1.13 |
Floor 1 Plan Part 3 | 9/19/09 | ||
A1.14 |
Floor 1 Plan Part 4 | 1/19/09 | ||
A1.15 |
Floor 1 Plan Part 5 | 10/31/08 | ||
A1.16 |
Floor 1 Plan Part 6 | 10/31/08 | ||
A1.17 |
Floor 1 Plan Part 7 | 10/31/08 | ||
A1.18 |
Floor 1 Plan Part 8 | 10/31/08 | ||
A1.19 |
Floor 1 Plan Part 9 | 1/19/09 | ||
A1.21 |
Floor 2 Plan Part 1 | 12/1/08 | ||
A1.21-X |
Floor 2 Plan Part 1-(Bid Option #03) | 12/1/08 | ||
A1.22 |
Floor 2 Plan Part 2 | 12/1/08 | ||
A1.23 |
Floor 2 Plan Part 3 | 12/1/08 | ||
A1.24 |
Floor 2 Plan Part 4 | 10/31/08 | ||
A1.25 |
Floor 2 Plan Part 5 | 10/31/08 | ||
A1.26 |
Floor 2 Plan Part 6 | 10/31/08 | ||
A1.27 |
Floor 2 Plan Part 7 | 10/31/08 | ||
A1.28 |
Floor 2 Plan Part 8 | 10/31/08 | ||
A1.29 |
Floor 2 Plan Part 9 | 10/31/08 | ||
A1.2TZ2 |
Floor 2 Transition Zone Plan Part 2 | 9/19/08 | ||
A1.2TZ3 |
Floor 2 Transition Zone Plan Part 3 | 9/19/08 | ||
A1.2TZ4 |
Floor 2 Transition Zone Plan Part 4 | 9/19/08 | ||
A1.31 |
Floor 3 Plan Part 1 | 12/1/08 | ||
A1.32 |
Floor 3 Plan Part 2 | 1/12/09 | ||
A1.33 |
Floor 3 Plan Part 3 | 1/12/09 | ||
A1.34 |
Floor 3 Plan Part 4 | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 5 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A1.35 |
Floor 3 Plan Part 5 | 10/31/08 | ||
A1.36 |
Floor 3 Plan Part 6 | 10/31/08 | ||
A1.37 |
Floor 3 Plan Part 7 | 10/31/08 | ||
A1.38 |
Floor 3 Plan Part 8 | 10/31/08 | ||
A1.39 |
Floor 3 Plan Part 9 | 10/31/08 | ||
A1.41 |
Floor 4 Plan Part 1 | 10/31/08 | ||
A1.42 |
Floor 4 Plan Part 2 | 10/31/08 | ||
A1.43 |
Floor 4 Plan Part 3 | 10/31/08 | ||
A1.44 |
Floor 4 Plan Part 4 | 10/31/08 | ||
A1.45 |
Floor 4 Plan Part 5 | 1/19/09 | ||
A1.46 |
Floor 4 Plan Part 6 | 10/31/08 | ||
A1.47 |
Floor 4 Plan Part 7 | 10/31/08 | ||
A1.48 |
Floor 4 Plan Part 8 | 10/31/08 | ||
A1.49 |
Floor 4 Plan Part 9 | 10/31/08 | ||
A1.4TZ2 |
Floor 4 Transition Zone Plan Part 2 | 9/19/08 | ||
A1.4TZ3 |
Floor 4 Transition Zone Plan Part 3 | 9/19/08 | ||
A1.4TZ4 |
Floor 4 Transition Zone Plan Part 4 | 9/19/08 | ||
A1.51 |
Floor 5 Plan Part l | 10/31/08 | ||
A1.52 |
Floor 5 Plan Part 2 | 12/1/08 | ||
A1.53 |
Floor 5 Plan Part 3 | 10/31/08 | ||
A1.54 |
Floor 5 Plan Part 4 | 10/31/08 | ||
A1.55 |
Floor 5 Plan Part 5 | 10/31/08 | ||
A1.56 |
Floor 5 Plan Part 6 | 10/31/08 | ||
A1.57 |
Floor 5 Plan Part 7 | 1/12/08 | ||
A1.58 |
Floor 5 Plan Part 8 | 10/31/08 | ||
A1.59 |
Floor 5 Plan Part 9 | 10/31/08 | ||
A1.61 |
Floor 6 Plan Part l | 10/31/08 | ||
A1.62 |
Floor 6 Plan Part 2 | 10/31/08 | ||
A1.63 |
Floor 6 Plan Part 3 | 10/31/08 | ||
A1 .64 |
Floor 6 Plan Part 4 | 10/31/08 | ||
A1.65 |
Floor 6 Plan Part 5 | 10/31/08 | ||
A1.66 |
Floor 6 Plan Part 6 | 10/31/08 | ||
A1 .67 |
Floor 6 Plan Part 7 | 10/31/08 | ||
A1 .68 |
Floor 6 Plan Part 8 | 10/31/08 | ||
A1.69 |
Floor 6 Plan Part 9 | 10/31/08 | ||
A1.6P4 |
Floor 6 Plan Part 4 | 10/31/08 | ||
A1.6P6 |
Floor 6 Plan Part 6 | 10/31/08 | ||
A1.6P7 |
Floor 5 Plan Part 7 | 10/31/08 | ||
A1.6P8 |
Floor 6 Plan Part 8 | 10/31/08 | ||
A1.6P9 |
Floor 6 Plan Part 9 | 10/31/08 | ||
A2.01 |
Stair No. 1 Plans | 10/31/08 | ||
A2.02 |
Stair No. 2 Plans | 10/31/08 | ||
A2.03 |
Stair No. 3 Plans | 1/19/08 | ||
A2.04 |
Stair No. 4 Plans | 1/19/08 | ||
A2.05 |
Stair No. 5 Plans | 1/19/08 | ||
A2.06 |
Stair No. 6 Plans | 10/31/08 | ||
A2.07 |
Stair No. 7 Plans | 10/31/08 | ||
A2.08 |
Stair No. 8 Plans | 10/31/08 | ||
A2.09 |
Stair No. 9 Plans | 10/31/08 | ||
A2.11 |
Utility Tunnel Stair Plans | 10/31/08 | ||
A2.12 |
Communicating Stair No. 1 | 1/19/09 | ||
A2.13 |
Communicating Stair No. 2 | 1/19/09 | ||
A2.21 |
Stair Details | 10/31/08 | ||
A2.22 |
Stair Details | 10/31/08 | ||
A2.23 |
Stair Details | 1/19/09 | ||
A2.24 |
Stair Details | 1/12/09 | ||
A2.31 |
Elevator Plans | 10/31/08 | ||
A2.32 |
Elevator Plans | 1/19/09 | ||
A2.33 |
Elevator Plans | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 6 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A2.41 |
Toilet Locker Plans | 1/12/09 | ||
A2.42 |
Toilet Locker Plans | 1/12/09 | ||
A2.43 |
Toilet Locker Plans | 10/31/08 | ||
A2.51 |
Millwork Plans | 10/31/08 | ||
A2.52 |
Millwork Plans | 10/31/08 | ||
A2.53 |
Millwork Plans | 10/31/08 | ||
A2.54 |
Millwork Plans | 10/31/08 | ||
A2.55 |
Millwork Plans | 10/31/08 | ||
A3.004 |
Basement Exterior Key Plan Parts 4, 5 and SE Tunnel | 1/19/09 | ||
A3.009 |
Basement Exterior Key Plan Part 9 | 1/19/09 | ||
A3.011 |
Floor 1 Exterior Key Plan Parts 1 to | 1/19/09 | ||
A3.016 |
Floor 1 Exterior Key Plan Parts 6 to 9 | 1/19/09 | ||
A3.021 |
Floor 2 Exterior Key Plan Parts 1 to 5 | 12/1/08 | ||
A3.026 |
Floor 2 Exterior Key Plan Parts 6 to 9 | 9/19/08 | ||
A3.031 |
Floor 3 Exterior Key Plan Parts 1 to 5 | 9/19/08 | ||
A3.036 |
Floor 3 Exterior Key Plan Parts 6 to 9 | 9/19/08 | ||
A3.041 |
Floor 4 Exterior Key Plan Parts 1 to 5 | 9/19/08 | ||
A3.046 |
Floor 4 Exterior Key Plan Parts 6 to 9 | 9/19/08 | ||
A3.051 |
Floor 5 Exterior Key Plan Parts 1 to 5 | 9/19/08 | ||
A3.056 |
Floor 5 Exterior Key Plan Parts 6 to 9 | 9/19/08 | ||
A3.061 |
Floor 5 Exterior Key Plan Parts 1 to 5 | 9/19/08 | ||
A3.066 |
Floor 6 Exterior Key Plan Parts 6 to 9 | 9/19/08 | ||
A3.06P1 |
Floor 6 Exterior Key Plan Parts 1 to 5 | 10/31/08 | ||
A3.06P6 |
Floor 6 Exterior Key Plan Parts 6 to 9 | 9/19/08 | ||
A3.07R1 |
Roof Exterior Key Plan Parts 1 to 5 | 12/1/08 | ||
A3.07R6 |
Roof Exterior Key Plan Parts 6 to 9 | 12/1/08 | ||
A3.11 |
East, West, South and North Elevations | 10/31/08 | ||
A3.12 |
Partial Exterior Elevations | 10/31/08 | ||
A3.13 |
Partial Exterior Elevations | 10/31/08 | ||
A3.13A |
Partial Exterior Elevations | 9/19/08 | ||
A3.14 |
Partial Exterior Elevations | 1/19/09 | ||
A3.15 |
Partial Exterior Elevations | 10/31/08 | ||
A3.16 |
Partial Exterior Elevations | 10/31/08 | ||
A3.17 |
Enlarged Exterior Plan and Elevations-Main Entry | 9/19/08 | ||
A3.18 |
Enlarged Exterior Elevations | 9/19/08 | ||
A3.19 |
Enlarged Exterior Plans and Section Details | 10/31/08 | ||
A3.21 |
Building Sections | 1/19/09 | ||
A3.22 |
Building Sections | 1/19/09 | ||
A3.31 |
Exterior On-Site Mock-Up | 9/19/08 | ||
A4.01 |
Wall Sections | 12/1/08 | ||
A4.02 |
Wall Sections | 12/1/08 | ||
A4.03 |
Wall Sections | 12/1/08 | ||
A4.04 |
Wall Sections | 1/19/09 | ||
A4.05 |
Wall Sections | 9/19/08 | ||
A4.06 |
Wall Sections | 10/31/08 | ||
A4.07 |
Wall Sections | 9/19/09 | ||
A4.08 |
Wall Sections | 1/19/09 | ||
A4.09 |
Wall Sections | 12/1/08 | ||
A4.11 |
Wall Section Details | 12/1/08 | ||
A4.12 |
Wall Section Details | 10/31/08 | ||
A4.13 |
Wall Section Details | 1/19/09 | ||
A4.14 |
Wall Section Details | 12/1/08 | ||
A4.15 |
Wall Section Details | 1/19/09 | ||
A4.16 |
Wall Section Details | 1/19/09 | ||
A4.17 |
Wall Section Details | 9/19/08 | ||
A4.18 |
Wall Section Details | 10/31/08 | ||
A4.19 |
Wall Section Details | 9/19/08 | ||
A4.20A |
Wall Section Details | 10/31/08 | ||
A4.20B |
Wall Section Details | 1/19/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 7 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A4.21 |
Exterior Plan Details | 10/31/08 | ||
A4.22 |
Exterior Plan Details | 10/31/08 | ||
A4.23 |
Exterior Plan Details: FLRS 1-2 | 12/1/08 | ||
A4.24 |
Exterior Plan Details: FLRS 1-2 | 12/1/08 | ||
A4.25 |
Exterior Plan Details | 12/1/08 | ||
A4.26 |
Skylight Details | 12/1/08 | ||
A4.27 |
Exterior Plan Details | 1/19/09 | ||
A4.28 |
Exterior Plan Details | 12/1/08 | ||
A4.29 |
Typical Precast Concrete and Misc. Exterior Details | 9/19/08 | ||
A4.30 |
Exterior Plan Details | 9/19/08 | ||
A4.31 |
Exterior Stair Details | 1/19/09 | ||
A4.32 |
Waterproofing Details | 10/31/08 | ||
A4.33 |
Sun Screen Details | 9/19/08 | ||
A4.34 |
Expansion Joint Details | 12/1/08 | ||
A4.41 |
Roof Details | 9/19/08 | ||
A4.42 |
Roof Details | 10/31/08 | ||
A0.012 |
Cover Sheet-Architectural-Part 2 | 1/19/09 | ||
A0.022 |
Index of Drawings-Architectural-Part 2 | 10/31/08 | ||
A0.032 |
General information | 10/31/08 | ||
A5.01 |
Partition Types | 10/31/08 | ||
A5.02 |
Partition Details | 10/31/08 | ||
A5.03 |
Partition Details | 10/31/08 | ||
A5.11 |
Interior Elevations | 1/12/09 | ||
A5.12 |
Interior Elevations | 9/19/08 | ||
A5.13 |
Interior Elevations | 10/31/08 | ||
A5.14 |
Interior Elevations | 10/31/08 | ||
A5.15 |
Interior Elevations | 10/31/08 | ||
A5.16-X |
Interior Elevations | 10/31/08 | ||
A5.17 |
Imaging Interior Elevations | 9/19/09 | ||
A5.21 |
Interior Sections | 10/31/08 | ||
A5.22 |
Interior Sections | 10/31/08 | ||
A5.23 |
Interior Sections | 10/31/08 | ||
A5.24 |
Interior Section Details | 10/31/08 | ||
A5.25 |
Interior Section Details | 10/31/08 | ||
A5.26 |
Interior Section Details | 10/31/08 | ||
A5.27 |
Interior Section Details | 10/31/08 | ||
A5.28 |
Interior Section Details | 1/19/09 | ||
A5.29 |
Interior Section Details | 10/31/08 | ||
A5.29-X |
Interior Section Details | 10/31/08 | ||
A5.311 |
Interior Plan Details | 1/19/09 | ||
A5.312 |
Interior Plan Details | 10/31/08 | ||
A5.313 |
Interior Plan Details | 10/31/08 | ||
A5.321 |
Interior Plan Details | 10/31/08 | ||
A5.322 |
Interior Plan Details | 12/1/08 | ||
A5.323 |
Interior Plan Details | 10/31/08 | ||
A5.324 |
Interior Plan Details | 9/19/08 | ||
A5.331 |
Interior Plan Details | 10/31/08 | ||
A5.332 |
Interior Plan Details | 12/1/08 | ||
A5.333 |
Interior Plan Details | 10/31/08 | ||
A5.334 |
Interior Plan Details | 10/31/08 | ||
A5.335 |
Interior Plan Details | 10/31/08 | ||
A5.341 |
Interior Plan Details | 9/19/08 | ||
A5.342 |
Interior Plan Details | 9/19/08 | ||
A5.343 |
Interior Plan Details | 10/31/08 | ||
A5.351 |
Interior Plan Details | 9/19/08 | ||
A5.352 |
Interior Plan Details | 9/19/08 | ||
A5.353 |
Interior Plan Details | 10/31/08 | ||
A5.354 |
Interior Plan Details | 10/31/08 | ||
A5.355 |
Interior Plan Details | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 8 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A5.356 |
Interior Plan Details | 9/19/08 | ||
A5.361 |
Interior Plan Details | 1/12/09 | ||
A5.362 |
Interior Plan Details | 1/12/09 | ||
A5.363 |
Interior Plan Details | 1/12/09 | ||
A5.364 |
Interior Plan Details | 9/19/08 | ||
A5.365 |
Interior Plan Details | 9/19/08 | ||
A5.371 |
Interior Plan Details | 9/19/08 | ||
A5.372 |
Interior Plan Details | 9/19/08 | ||
A5.381 |
Interior Plan Details | 9/19/08 | ||
A5.41 |
Interior Door/Window Elevations | 9/19/08 | ||
A5.42 |
Interior Door/Window Elevations | 9/19/08 | ||
A5.43 |
Interior Door/Window Elevations | 9/19/08 | ||
A5.44 |
Interior Door/Window Elevations | 9/19/08 | ||
A5.46 |
Interior Door/Window Details | 10/31/08 | ||
A5.47 |
Interior Door/Window Details | 10/31/08 | ||
A5.48 |
Interior Door/Window Details | 10/31/08 | ||
A5.491 |
Interior Door/Window Details | 1/12/09 | ||
A5.492 |
Interior Door/Window Details | 10/31/08 | ||
A5.51 |
Millwork Elevations | 10/31/08 | ||
A6.52 |
Millwork Elevations | 10/31/08 | ||
A5.53 |
Millwork Elevations | 10/31/08 | ||
A5.541 |
Atrium Acoustical Wall Details | 9/19/08 | ||
A5.542 |
Atrium Acoustical Wall Details | 9/19/08 | ||
A5.543 |
Atrium Acoustical Wall Details | 9/19/08 | ||
A5.544 |
Atrium Acoustical Wall Details | 1/12/09 | ||
A5.545 |
Acoustical Wall Panels | 1/12/09 | ||
A5.55 |
Millwork Elevations | 9/19/08 | ||
A5.56 |
Millwork Details | 10/31/08 | ||
A5.57 |
Work Details | 10/31/08 | ||
A5.58 |
Work Details | 12/1/08 | ||
A5.59 |
Work Details | 10/31/08 | ||
A5.59-X |
Work Details | 9/19/08 | ||
A5.61 |
Specialty Details | 10/31/08 | ||
A5.62 |
Specialty Details | 1/19/09 | ||
A5.63 |
Specialty Details | 10/31/08 | ||
A5.64 |
Specialty Details | 9/19/08 | ||
A5.65 |
Floor Finish Transition Details | 10/31/08 | ||
A5.71 |
Room Elevations High Containment | 12/1/08 | ||
A5.72 |
Room Elevations High Containment | 12/1/08 | ||
A5.73 |
Room Elevations High Containment | 10/31/08 | ||
A5.74 |
Room Elevations High Containment | 12/1/08 | ||
A5.75 |
Room Elevations High Containment | 10/31/08 | ||
A5.76 |
Room Elevations High Containment | 1/12/09 | ||
A5.77 |
Room Elevations High Containment | 10/31/08 | ||
A5.81 |
Specialty Details Aero & Tissue Digester | 9/19/08 | ||
A5.82 |
Specialty Details Imaging | 10/31/08 | ||
A5.83 |
Specialty Details Imaging | 9/19/09 | ||
A5.91 |
HC APR Details | 1/12/09 | ||
A5.92 |
Specialty Details HC | 1/12/09 | ||
A5.93 |
Specialty Details HC | 9/19/08 | ||
A5.94 |
Specialty Details HC | 10/31/08 | ||
A5.95 |
Specialty Details HC | 10/31/08 | ||
A5.96 |
Specialty Details HC | 1/12109 | ||
A5.97 |
Specialty Details HC | 10/31/08 | ||
A5.98 |
Specialty Details HC | 12/1/08 | ||
A5.991 |
Specialty Details HC | 9/19/08 | ||
A5.992 |
Specialty Details HC | 10/31/08 | ||
A5.993 |
Specialty Details HC | 10/31/08 | ||
A6.01 |
Casework Symbols | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 9 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A6.02 |
Casework Profile Types | 9/19/08 | ||
A6.03 |
Casework Profile Types | 1/12/09 | ||
A6.11A-X |
Floor 1 Casework Plan Part 1A | 9/19/08 | ||
A6.11B-X |
Floor 1 Casework Plan Part lB | 10/31/08 | ||
A6.14D |
Floor 1 Casework Plan Part 4D | 9/19/08 | ||
A6.14E |
Floor 1 Casework Plan Part 4E | 9/19/08 | ||
A8.14F |
Floor 1 Casework Plan Part 4F | 9/19/08 | ||
A6.15A |
Floor 1 Casework Plan Part 5A | 9/19/08 | ||
A6.I5B |
Floor 1 Casework Plan Part 5B | 9/19/08 | ||
A6.15C |
Floor 1 Casework Plan Part 5C | 9/19/08 | ||
A8.15D |
Floor 1 Casework Plan Part 5D | 9/19/08 | ||
A6.17B |
Floor 1 Casework Plan Part 7B | 9/19/08 | ||
A6.17C |
Floor 1 Casework Plan Part 7C | 9/19/08 | ||
A6.17D |
Floor 1 Casework Plan Part 7D | 9/19/08 | ||
A6.18A |
Floor 1 Casework Plan Part 8B | 9/19/08 | ||
A6.18C |
Floor 1 Casework Plan Part 8C | 9/19/08 | ||
A6.18D |
Floor 1 Casework Plan Part 8D | 1/12/09 | ||
A6.19C |
Floor 1 Casework Plan Part 9C | 9/19/08 | ||
A6.19D |
Floor 1 Casework Plan Part 9D | 9/19/08 | ||
A6.22A |
Floor 2 Casework Plan Part 2A | 1/19/09 | ||
A6.22B |
Floor 2 Casework Plan Part 2B | 10/31/08 | ||
A6.22C |
Floor 2 Casework Plan Part 2C | 1/12/09 | ||
AS.23A |
Floor 2 Casework Plan Part 3A | 1/19/09 | ||
A6.23B |
Floor 2 Casework Plan Part 3B | 10/31/08 | ||
A6.23C |
Floor 2 Casework Plan Part 3C | 1/12/09 | ||
A6.24A |
Floor 2 Casework Plan Part 4A | 1/19/09 | ||
A6.24B |
Floor 2 Casework Plan Part 4B | 9/19/08 | ||
A6.24C |
Floor 2 Casework Plan Part 4C | 1/19/09 | ||
A6.24D |
Floor 2 Casework Plan Part 4D | 9/19/08 | ||
A6.24E |
Floor 2 Casework Plan Part 4E | 9/19/08 | ||
A6.24F |
Floor 2 Casework Plan Part 4F | 9/19/08 | ||
A6.25A |
Floor 2 Casework Plan Part 5A | 10/31/08 | ||
A6.25B |
Floor 2 Casework Plan Part 5B | 9/19/08 | ||
A6.25C |
Floor 2 Casework Plan Part 5C | 9/19/08 | ||
A6.25D |
Floor 2 Casework Plan Part 5D | 9/19/08 | ||
A6.26C |
Floor 2 Casework Plan Part 6C | 10/31/08 | ||
A6.27C |
Floor 2 Casework Plan Part 7C | 9/19/08 | ||
A6.27D |
Floor 2 Casework Plan Part 7D | 9/19/08 | ||
A6.28C |
Floor 2 Casework Plan Part 8C | 9/19/08 | ||
A6.28D |
Floor 2 Casework Plan Part 8D | 9/19/08 | ||
A6.29C |
Floor 2 Casework Plan Part 9C | 9/19/08 | ||
A6.29D |
Floor 2 Casework Plan Part 9D | 9/19/08 | ||
A6.37C |
Floor 3 Casework Plan Part 7C | 9/19/08 | ||
A6.37D |
Floor 3 Casework Plan Part 7D | 9/19/08 | ||
A6.38C |
Floor 3 Casework Plan Part 8C | 9/19/08 | ||
A6.38D |
Floor 3 Casework Plan Part 8D | 9/19/08 | ||
A6.39C |
Floor 3 Casework Plan Part 9C | 9/19/08 | ||
A6.39D |
Floor 3 Casework Plan Part 9D | 9/19/08 | ||
A6.42A |
Floor 4 Casework Plan Part 2A | 9/19/08 | ||
A6.42B |
Floor 4 Casework Plan Part 2B | 1/19/09 | ||
A6.42C |
Floor 4 Casework Plan Part 2C | 1/19/09 | ||
A6.43A |
Floor 4 Casework Plan Part 3A | 9/19/08 | ||
A6.43B |
Floor 4 Casework Plan Part 3B | 9/19/08 | ||
A6.43C |
Floor 4 Casework Plan Part 3C | 1/19/09 | ||
A6.44A |
Floor 4 Casework Plan Part 4A | 9/19/08 | ||
A6.44B |
Floor 4 Casework Plan Part 4B | 1/19/09 | ||
A6.44C |
Floor 4 Casework Plan Part 4C | 1/19/09 | ||
A6.44D |
Floor 4 Casework Plan Part 4D | 9/19/08 | ||
A6.44E |
Floor 4 Casework Plan Part 4E | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 10 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A6.44F |
Floor 4 Casework Plan Part 4F | 9/19/08 | ||
A6.45A |
Floor 4 Casework Plan Part 5A | 10/31/08 | ||
A6.45B |
Floor 4 Casework Plan Part 5B | 9/19/08 | ||
A6.45C |
Floor 4 Casework Plan Part 5C | 1/19/09 | ||
A6.45D |
Floor 4 Casework Plan Part 5D | 9/19/08 | ||
A6.47C |
Floor 4 Casework Plan Part 7C | 9/19/08 | ||
A6.47D |
Floor 4 Casework Plan Part 7D | 9/19/08 | ||
A6.48C |
Floor 4 Casework Plan Part 8C | 9/19/08 | ||
A6.48D |
Floor 4 Casework Plan Part 8D | 9/19/08 | ||
A6.49C |
Floor 4 Casework Plan Part 9C | 9/19/08 | ||
A6.49D |
Floor 4 Casework Plan Part 9D | 1/12/098 | ||
A6.57C |
Floor 5 Casework Plan Part 7C | 9/19/08 | ||
A6.57D |
Floor 5 Casework Plan Part 7D | 9/19/08 | ||
A6.58C |
Floor 5 Casework Plan Part 8C | 9/19/08 | ||
A6.58D |
Floor 5 Casework Plan Part 8D | 9/19/08 | ||
A6.59C |
Floor 5 Casework Plan Part 9C | 9/19/08 | ||
A6.59D |
Floor 5 Casework Plan Part 9D | 9/19/08 | ||
A6.81 |
Casework Details | 9/19/08 | ||
A6.82 |
Miscellaneous Casework Details | 9/19/08 | ||
A6.83 |
Fumehood Elevations and Details | 9/19/08 | ||
A6.91 |
Casework Profile Types | 1/12/098 | ||
A0.013 |
Cover Sheet-Architectural-Part 3 | 10/31/08 | ||
A0.023 |
Index of Drawings-Architectural-Part 3 | 10/31/08 | ||
A0.033 |
General Information | 10/31/08 | ||
A7.00 |
Interior Finish Legend | 9/19/08 | ||
A7.01-X |
Interior Floor Pattern Detail | 9/19/08 | ||
A7.04 |
Basement Interior Finish Plan Part 4 | 1/19/09 | ||
A7.05 |
Basement Interior Finish Plan Part 5 | 1/19/09 | ||
A7.05E |
Basement Interior Finish Plan Part 5E Tunnel | 1/19/09 | ||
A7.09 |
Basement Interior Finish Plan Part 9 | 1/19/09 | ||
A7.11 |
Floor 1 Interior Finish Plan Part I | 9/19/08 | ||
A7.12 |
Floor 1 Interior Finish Plan Part 2 | 9/19/08 | ||
A7.13 |
Floor 1 Interior Finish Plan Part 3 | 1/19/09 | ||
A7.14 |
Floor 1 Interior Finish Plan Part 4 | 10/31/08 | ||
A7.15 |
Floor 1 Interior Finish Plan Part 5 | 10/31/08 | ||
A7.16 |
Floor 1 Interior Finish Plan Part 6 | 12/1/08 | ||
A7.17 |
Floor 1 Interior Finish Plan Part 7 | 9/19/08 | ||
A7.18 |
Floor 1 Interior Finish Plan Part 8 | 10/31/08 | ||
A7.19 |
Floor 1 Interior Finish Plan Part 9 | 10/31/08 | ||
A7.21 |
Floor 2 Interior Finish Plan Part 1 | 1/12/09 | ||
A7.22 |
Floor 2 Interior Finish Plan Part 2 | 1/12/09 | ||
A7.23 |
Floor 2 Interior Finish Plan Part 3 | 1/12/09 | ||
A7.24 |
Floor 2 Interior Finish Plan Part 4 | 1/12/09 | ||
A7.25 |
Floor 2 Interior Finish Plan Part 5 | 1/12/09 | ||
A7.26 |
Floor 2 Interior Finish Plan Part 6 | 10/31/08 | ||
A7.27 |
Floor 2 Interior Finish Plan Part 7 | 10/31/08 | ||
A7.28 |
Floor 2 Interior Finish Plan Part 8 | 10/31/08 | ||
A7.29 |
Floor 2 Interior Finish Plan Part 9 | 9/19/08 | ||
A7.31 |
Floor 2 Interior Finish Plan Part 1 | 10/31/08 | ||
A7.32 |
Floor 2 Interior Finish Plan Part 2 | 10/31/08 | ||
A7.33 |
Floor 3 Interior Finish Plan Part 3 | 10/31/08 | ||
A7.34 |
Floor 3 Interior Finish Plan Part 4 | 10/31/08 | ||
A7.35 |
Floor 3 Interior Finish Plan Part 5 | 9/19/08 | ||
A7.36 |
Floor 3 Interior Finish Plan Part 6 | 9/19/08 | ||
A7.37 |
Floor S Interior Finish Plan Part 7 | 9/19/08 | ||
A7.38 |
Floor 3 Interior Finish Plan Part 8 | 10/31/08 | ||
A7.39 |
Floor 3 Interior Finish Plan Part 9 | 9/19/08 | ||
A7.41 |
Floor 4 Interior Finish Plan Part 1 | 9/19/08 | ||
A7.42 |
Floor 4 Interior Finish Plan Part 2 | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 11 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A7.43 |
Floor 4 Interior Finish Plan Part 3 | 10/31/08 | ||
A7.44 |
Floor 4 interior Finish Plan Part 4 | 10/31/08 | ||
A7.45 |
Floor 4 Interior Finish Plan Part 5 | 9/19/08 | ||
A7.46 |
Floor 4 Interior Finish Plan Part 6 | 10/31/08 | ||
A7.47 |
Floor 4 Interior Finish Plan Part 7 | 9/19/08 | ||
A7.48 |
Floor 4 Interior Finish Plan Part 8 | 10/31/08 | ||
A7.49 |
Floor 4 Interior Finish Plan Part 9 | 9/19/08 | ||
A7.51 |
Floor 5 Interior Finish Plan Part 1 | 10/31/08 | ||
A7.52 |
Floor 5 Interior Finish Plan Part 2 | 10/31/08 | ||
A7.53 |
Floor 5 Interior Finish Plan Part 3 | 10/31/08 | ||
A7.54 |
Floor 5 Interior Finish Plan Part 4 | 10/31/08 | ||
A7.55 |
Floor 5 Interior Finish Plan Part 5 | 10/31/08 | ||
A7.56 |
Floor 5 Interior Finish Plan Part 6 | 10/31/08 | ||
A7.57 |
Floor 5 Interior Finish Plan Part 7 | 1/12/09 | ||
A7.58 |
Floor 5 Interior Finish Plan Part 8 | 9/19/08 | ||
A7.59 |
Floor 5 Interior Finish Plan Part 9 | 9/19/08 | ||
A7.61 |
Floor 6 Interior Finish Plan Part 1 | 10/31/08 | ||
A7.62 |
Floor 6 Interior Finish Plan Part 2 | 10/31/08 | ||
A7.63 |
Floor 6 Interior Finish Plan Part 3 | 10/31/08 | ||
A7.64 |
Floor 6 Interior Finish Plan Part 4 | 10/31/08 | ||
A7.65 |
Floor 6 Interior Finish Plan Part 5 | 9/19/08 | ||
A7.66 |
Floor 6 Interior Finish Plan Part 6 | 10/31/08 | ||
A7.67 |
Floor 6 Interior Finish Plan Part 7 | 10/31/08 | ||
A7.68 |
Floor 6 Interior Finish Plan Part 8 | 10/31/08 | ||
A7.69 |
Floor 8 Interior Finish Plan Part 9 | 10/31/08 | ||
A7.6P4 |
Floor 6P Interior Finish Plan Part 4 | 9/19/08 | ||
A7.6P6 |
Floor SP Interior Finish Plan Part 6 | 9/19/08 | ||
A7.6P7 |
Floor SP Interior Finish Plan Part 7 | 9/19/08 | ||
A7.6P8 |
Floor 8P Interior Finish Plan Part 8 | 9/19/08 | ||
A7.6P9 |
Floor SP Interior Finish Plan Part 9 | 9/19/08 | ||
A8.04 |
Basement Reflected Ceiling Plan Part 4 | 1/19/09 | ||
A8.05 |
Basement Reflected Ceiling Plan Part 5 | 9/19/08 | ||
A8.05E |
Basement Reflected Ceiling Plan Part 5E | 9/19/08 | ||
A8.09 |
Basement Reflected Ceiling Plan Part 9 | 1/19/09 | ||
A8.11 |
Floor 1 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.11-X |
Floor 1 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.12 |
Floor 1 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.13 |
Floor 1 Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.14 |
Floor 1 Reflected Ceiling Plan Part 4 | 1/19/09 | ||
A8.15 |
Floor 1 Reflected Ceiling Plan Part 5 | 12/1/08 | ||
A8.16 |
Floor 1 Reflected Ceiling Plan Part 6 | 1/12/09 | ||
A8.17 |
Floor l Reflected Ceiling Plan Part 7 | 1/12/09 | ||
A8.18 |
Floor 1 Reflected Ceiling Plan Part 8 | 1/12/09 | ||
A8.19 |
Floor 1 Reflected Ceiling Plan Part 9 | 1/12/09 | ||
A8.21 |
Floor 2 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.21-X |
Floor 2 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.22 |
Floor 2 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.22B |
Floor 2 Reflected Ceiling Plan Part 2 | 10/31/08 | ||
A8.22B ALT |
Floor 2 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.22C |
Floor 2 Reflected Ceiling Plan Part 2 | 10/31/08 | ||
A8.22C ALT |
Floor 2 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.23 |
Floor 2 Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.23B |
Floor 2 Reflected Ceiling Plan Part 3 | 10/31/08 | ||
A8.23B ALT |
Floor 2 Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.23C |
Floor 2 Reflected Ceiling Plan Part 3 | 10/31/08 | ||
A8.23C ALT |
Floor 2 Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.24 |
Floor 2 Reflected Ceiling Plan Part 4 | 10/31/08 | ||
A8.25 |
Floor 2 Reflected Ceiling Plan Part 5 | 10/31/08 | ||
A8.26 |
Floor 2 Reflected Ceiling Plan Part 6 | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 12 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A8.27 |
Floor 2 Reflected Ceiling Plan Part 7 | 1/12/09 | ||
A8.28 |
Floor 2 Reflected Ceiling Plan Part 8 | 1/12/09 | ||
A8.29 |
Floor 2 Reflected Ceiling Plan Part 9 | 1/12/09 | ||
A8.2TZ2 |
Floor 2 Transition Zone Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.2TZ3 |
Floor 2 Transition Zone Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.2TZ4 |
Floor 2 Transition Zone Reflected Ceiling Plan Part 4 | 9/19/08 | ||
A8.31 |
Floor 3 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.32 |
Floor 3 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.33 |
Floor 3 Reflected Ceiling Plan Part 3 | 12/1/08 | ||
A8.34 |
Floor 3 Reflected Ceiling Plan Part 4 | 10/31/08 | ||
A8.35 |
Floor 3 Reflected Ceiling Plan Part 5 | 10/31/08 | ||
A8.36 |
Floor 3 Reflected Ceiling Plan Part 6 | 1/12/09 | ||
A8.37 |
Floor 3 Reflected Ceiling Plan Part 7 | 1/12/09 | ||
A8.38 |
Floor 3 Reflected Ceiling Plan Part 8 | 1/12/09 | ||
A8.39 |
Floor 3 Reflected Ceiling Plan Part 9 | 1/12/09 | ||
A8.41 |
Floor 4 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.42 |
Floor 4 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.43 |
Floor 4 Reflected Ceiling Plan Part 3 | 12/1/08 | ||
A8.44 |
Floor 4 Reflected Ceiling Plan Part 4 | 10/31/08 | ||
A8.45 |
Floor 4 Reflected Ceiling Plan Part 5 | 1/19/09 | ||
A8.46 |
Floor 4 Reflected Ceiling Plan Part 6 | 1/12/09 | ||
A8.47 |
Floor 4 Reflected Ceiling Plan Part 7 | 1/12/09 | ||
A8.48 |
Floor 4 Reflected Ceiling Plan Part 8 | 1/12/09 | ||
A8.49 |
Floor 4 Reflected Ceiling Plan Part 9 | 1/12/09 | ||
A8.4TZ2 |
Floor 4 Transition Zone Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.4TZ3 |
Floor 4 Transition Zone Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.4TZ4 |
Floor 4 Transition Zone Reflected Ceiling Plan Part 4 | 9/19/08 | ||
A8.51 |
Floor 5 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.52 |
Floor 5 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.53 |
Floor 5 Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.54 |
Floor 5 Reflected Ceiling Plan Part 4 | 10/31/08 | ||
A8.55 |
Floor 5 Reflected Ceiling Plan Part 5 | 10/31/08 | ||
A8.56 |
Floor 5 Reflected Ceiling Plan Part 6 | 1/12/09 | ||
A8.57 |
Floor 5 Reflected Ceiling Plan Part 7 | 1/12/09 | ||
A8.58 |
Floor 5 Reflected Ceiling Plan Part 8 | 1/12/09 | ||
A8.59 |
Floor 5 Reflected Ceiling Plan Part 9 | 1/12/09 | ||
A8.61 |
Floor 6 Reflected Ceiling Plan Part 1 | 10/31/08 | ||
A8.62 |
Floor 6 Reflected Ceiling Plan Part 2 | 9/19/08 | ||
A8.63 |
Floor 6 Reflected Ceiling Plan Part 3 | 9/19/08 | ||
A8.64 |
Floor 6 Reflected Ceiling Plan Part 4 | 10/31/08 | ||
A8.65 |
Floor 6 Reflected Ceiling Plan Part 5 | 10/31/08 | ||
A8.66 |
Floor 6 Reflected Ceiling Plan Part 6 | 10/31/08 | ||
A8.67 |
Floor 8 Reflected Ceiling Plan Part 7 | 1/12/09 | ||
A8.68 |
Floor 5 Reflected Ceiling Plan Part 8 | 1/12/09 | ||
A8.69 |
Floor 6 Reflected Ceiling Plan Part 9 | 1/12/09 | ||
A8.6P4 |
Floor 6 Reflected Ceiling Plan Part 4 | 9/19/08 | ||
A8.6P6 |
Floor 6 Reflected Ceiling Plan Part 6 | 9/19/08 | ||
A8.6P7 |
Floor 6 Reflected Ceiling Plan Part 7 | 9/19/08 | ||
A8.6P8 |
Floor 6 Reflected Ceiling Plan Part 8 | 9/19/08 | ||
A8.6P9 |
Floor 6 Reflected Ceiling Plan Part 9 | 9/19/08 | ||
A8.81 |
Vivarium Ceiling Details | 9/19/08 | ||
A8.82 |
Ceiling Details | 1/12/09 | ||
A8.83 |
Ceiling Details | 9/19/08 | ||
A8.84 |
Ceiling Details | 9/19/08 | ||
A8.85 |
Ceiling Details | 10/31/08 | ||
A8.86 |
Ceiling Details | 9/19/08 | ||
A8.87 |
Ceiling Details | 9/19/08 | ||
A8.88 |
Ceiling Details | 9/19/08 | ||
A9.00 |
Furniture Plan Details | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 13 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
A9.11 |
Floor 1 Furniture Plan Part 1 | 1/12/09 | ||
A9.14 |
Floor 1 Furniture Plan Part 4 | 9/19/08 | ||
A9.15 |
Floor 1 Furniture Plan Part 5 | 9/19/08 | ||
A9.16 |
Floor 1 Furniture Plan Part 5 | 10/31/08 | ||
A9.17 |
Floor 1 Furniture Plan Part 7 | 1/12/09 | ||
A9.18 |
Floor 1 Furniture Plan Part 8 | 10/31/08 | ||
A9.19 |
Floor 1 Furniture Plan Part 9 | 10/31/08 | ||
A9-21-X |
Floor 2 Furniture Plan Part 1 | 10/31/08 | ||
A9-24 |
Floor 2 Furniture Plan Part 4 | 10/31/08 | ||
A9-25 |
Floor 2 Furniture Plan Part 5 | 10/31/08 | ||
A9-26 |
Floor 2 Furniture Plan Part 6 | 10/31/08 | ||
A9-27 |
Floor 2 Furniture Plan Part 7 | 10/31/08 | ||
A9-28 |
Floor 2 Furniture Plan Part 8 | 10/31/08 | ||
A9-29 |
Floor 2 Furniture Plan Part 9 | 10/31/08 | ||
A9-31 |
Floor 3 Furniture Plan Part 1 | 10/31/08 | ||
A9-34 |
Floor 3 Furniture Plan Part 4 | 10/31/08 | ||
A9-35 |
Floor 3 Furniture Plan Part 5 | 10/31/08 | ||
A9-36 |
Floor 3 Furniture Plan Part 6 | 10/31/08 | ||
A9-37 |
Floor 3 Furniture Plan Part 7 | 10/31/08 | ||
A9-38 |
Floor 3 Furniture Plan Part 8 | 10/31/08 | ||
A9-39 |
Floor 3 Furniture Plan Part 9 | 10/31/08 | ||
A9-44 |
Floor 4 Furniture Plan Part 4 | 10/31/08 | ||
A9-45 |
Floor 4 Furniture Plan Part 5 | 1/19/09 | ||
A9-46 |
Floor 4 Furniture Plan Part 6 | 10/31/08 | ||
A9-47 |
Floor 4 Furniture Plan Part 7 | 10/31/08 | ||
A9-48 |
Floor 4 Furniture Plan Part 5 | 10/31/08 | ||
A9-49 |
Floor 4 Furniture Plan Part 9 | 10/31/08 | ||
A9-56 |
Floor 5 Furniture Plan Part 6 | 10/31/08 | ||
A9-57 |
Floor 5 Furniture Plan Part | 10/31/08 | ||
A9-58 |
Floor 5 Furniture Plan Part 5 . | 10/31/08 | ||
A9-59 |
Floor 5 Furniture Plan Part 9 | 10131/0 | ||
A9-81 |
Display System Elevations | 10/31/08 | ||
STRUCTURAL | ||||
S0.011 |
Cover Sheet Structural Part 1 | 1/19/09 | ||
S0.021 |
Index of Drawings Structural Part 1 | 1/19/09 | ||
S0.11 |
General Information | 1/19/09 | ||
S0.12 |
General Information Component and Cladding Zones | 9/19/08 | ||
S1.01DP |
Drilled Pier Plan Part 1 | 11/18/08 | ||
S1.02DP |
Drilled Pier Plan Part 2 | 1/19/09 | ||
S1.03DP |
Drilled Pier Plan Part 3 | 1/19/09 | ||
S1.04DP |
Drilled Pier Plan Part 4 | 1/19/09 | ||
S1.05DP |
Drilled Pier Plan Part 5 | 11/18/08 | ||
S1.06DP |
Drilled Pier Plan Part 6 | 1/19/09 | ||
S1.07DP |
Drilled Pier Plan Part 7 | 1/19/09 | ||
S1.08DP |
Drilled Pier Plan Part 8 | 1/19/09 | ||
S1.09DP |
Drilled Pier Plan Part 9 | 1/19/09 | ||
S1.01 |
Foundation Plan Part 1 | 1/19/09 | ||
S1.02 |
Foundation Plan Part 2 | 1/19/09 | ||
S1.03 |
Foundation Plan Part 3 | 1/19/09 | ||
S1.04 |
Foundation and Basement Plan Part 4 | 1/19/09 | ||
S1.05 |
Foundation and Basement Plan Part 5 | 1/19/09 | ||
S1.05E |
Foundation, Basement and Roof Framing Plan Part 5E Tunnel | 1/19/09 | ||
S1.06 |
Foundation Plan Part 6 | 1/19/09 | ||
S1.07 |
Foundation Plan Part 7 | 1/19/09 | ||
S1.08 |
Foundation Plan Part 8 | 1/19/09 | ||
S1.09 |
Foundation and Basement Plan Part 9 | 1/19/09 | ||
S1.11 |
Floor 1 Slab on Grade Plan Part 1 | 1/19/09 | ||
S1.12 |
Floor 1 Slab on Grade Plan Part 2 | 1/19/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 14 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
S1.12H |
Floor 1 Slab on Grade Plan Part 2 | 10/31/08 | ||
S1.13 |
Floor 1 Slab on Grade Plan Part 3 | 1/19/09 | ||
S1.13H |
Floor 1 Slab on Grade Plan Part 5 | 10/31/08 | ||
S1.14 |
Floor 1 Slab on Grade/ Framing Plan Part 4 | 1/19/09 | ||
S1.15 |
Floor 1 Slab on Grade/ Framing Plan Part 5 | 1/19/09 | ||
S1.16 |
Floor 1 Slab on Grade/ Framing Plan Part 6 | 1/19/09 | ||
S1.17 |
Floor 1 Slab on Grade/Framing Plan Part 7 | 10/31/08 | ||
S1.18 |
Floor 1 Stab on Grade/ Framing Plan Part 8 | 1/19/09 | ||
S1.19 |
Floor 1 Slab on Grade/Framing Plan Part 9 | 1/19/09 | ||
S1.21 |
Floor 2 Framing Plan Part 1 | 1/19/09 | ||
S1.22 |
Floor 2 Framing Plan Part 2 | 10/31/08 | ||
S1.22H |
Floor 2 Framing Plan Part 2-High Containment | 1/19/09* | ||
S1.22H-SE |
Floor 2 Slab Edge Part 2-High Containment | 1/19/09* | ||
S1.23 |
Floor 2 Framing Plan Part 3 | 10/31/08 | ||
S1.23H |
Floor 2 Framing Plan Part 3-High Containment | 1/19/09* | ||
S1.23H-SE |
Floor 2 Slab Edge Part 3-High Containment | 1/19/09* | ||
S1.24 |
Floor 2 Framing Plan Part 4 | 1/19/09 | ||
S1.24TD |
Floor 2 Trench Drain Plan Part 4 | 9/19/08 | ||
S1.25 |
Floor 2 Framing Plan Part 5 | 1/19/09 | ||
S1.25TD |
Floor 2 Trench Drain Plan Part 5 | 9/19/08 | ||
S1.26 |
Floor 2 Framing Plan Part 5 | 1/19/09 | ||
S1.27 |
Floor 2 Framing Plan Part 7 | 1/19/09 | ||
S1.28 |
Floor 2 Framing Plan Part 8 | 1/19/09 | ||
S1.29 |
Floor 2 Framing Plan Part 9 | 1/19/09 | ||
S1.31 |
Floor 3 Framing Plan Part 1 | 1/19/09 | ||
S1.32 |
Floor 3 Framing Plan Part 2 | 11/18/08 | ||
S1.32H |
Floor 3 Framing Plan Part 2-High Containment | 1/19/09* | ||
S1.33 |
Floor 3 Framing Plan Part 3 | 11/18/08 | ||
S1.33H |
Floor 3 Framing Plan Part 3-High Containment | 1/19/09* | ||
S1.34 |
Floor 3 Framing Plan Part 4 | 1/19/09 | ||
S1.35 |
Floor 3 Framing Plan Part 5 | 1/19/09 | ||
S1.36 |
Floor 3 Framing Plan Part 6 | 1/19/09 | ||
S1.37 |
Floor 3 Framing Plan Part 7 | 1/19/09 | ||
S1.38 |
Floor 3 Framing Plan Part 6 | 1/19/09 | ||
S1.39 |
Floor 3 Framing Plan Part 9 | 1/19/09 | ||
S1.41 |
Floor 4 Framing Plan Part 1 | 1/19/09 | ||
S1.42 |
Floor 4 Framing Plan Part 2 | 1/19/09 | ||
S1.42TD |
Floor 4 Trench Drain Plan Part 2 | 9/19/08 | ||
S1.43 |
Floor 4 Framing Plan Part 3 | 1/19/09 | ||
S1.43TD |
Floor 4 Trench Drain Plan Part 3 | 9/19/08 | ||
S1.44 |
Floor 4 Framing Plan Part 4 | 1/19/09 | ||
S1.44TD |
Floor 4 Trench Drain Plan Part 4 | 9/19/08 | ||
S1.45 |
Floor 4 Framing Plan Part 5 | 1/19/09 | ||
S1.45TD |
Floor 4 Trench Drain Plan Part 5 | 9/19/08 | ||
S1.46 |
Floor 4 Framing Plan Part 6 | 1/19/09 | ||
S1.47 |
Floor 4 Framing Plan Part 7 | 1/19/09 | ||
S1.48 |
Floor 4 Framing Plan Part 8 | 1/19/09 | ||
S1.49 |
Floor 4 Framing Plan Part 9 | 1/19/09 | ||
S1.51 |
Floor 5 Framing Plan Part 1 | 1/19/09 | ||
S1.52 |
Floor 5 Framing Plan Part 2 | 1/19/09 | ||
S1.53 |
Floor 5 Framing Plan Part 3 | 1/19/09 | ||
S1.54 |
Floor 5 Framing Plan Part 4 | 1/19/09 | ||
S1.55 |
Floor 5 Framing Plan Part 5 | 1/19/09 | ||
S1.56 |
Floor 5 Framing Plan Part 6 | 1/19/09 | ||
S1.57 |
Floor 5 Framing Plan Part 7 | 1/19/09 | ||
S1.58 |
Floor 5 Framing Plan Part 5 | 1/19/09 | ||
S1.59 |
Floor 5 Framing Plan Part 9 | 1/19/09 | ||
S1.61 |
Floor 6 Framing Plan Part 1 | 1/19/09 | ||
S1.62 |
Floor 6 Framing Plan Part 2 | 1/19/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 15 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
S1.63 |
Floor 6 Framing Plan Part 3 | 1/19/09 | ||
S1.64 |
Floor 6 Framing Plan Part 4 | 1/19/09 | ||
S1.65 |
Floor 6 Framing Plan Part 5 | 1/19/09 | ||
S1.66 |
Floor 6 Framing Plan Part 6 | 1/19/09 | ||
S1.67 |
Floor 6 Framing Plan Part 7 | 1/19/09 | ||
S1.68 |
Floor 6 Framing Plan Part 8 | 1/19/09 | ||
S1.69 |
Floor 6 Framing Plan Part 9 | 1/19/09 | ||
S1.6P1 |
Roof (Floor 6P) Framing Plan Part 1 | 1/19/09 | ||
S1.6P2 |
Roof (Floor 6P) Framing Plan Part 2 | 1/19/09 | ||
S1.6P3 |
Roof (Floor 6P) Framing Plan Part 3 | 11/18/0 | ||
S1.6P4 |
Roof (Floor 6P) Framing Plan Part 4 | 1/19/09 | ||
S1.6P5 |
Roof (Floor 6P) Framing Plan Part 5 | 11/18/08 | ||
S1.6P6 |
Roof (Floor 6P) Framing Plan Part 6 | 1/19/09 | ||
S1.6P7 |
Roof (Floor 6P) Framing Plan Part 7 | 1/19/09 | ||
S1.6P8 |
Roof (Floor 6P) Framing Plan Part 8 | 10/31/08 | ||
S1.6P9 |
Roof (Floor 6P) Framing Plan Part 9 | 11/18/08 | ||
S1.74 |
Penthouse Roof, Dunnage and Solar Thermal Support Framing Plan Part 4 | 1/19/09 | ||
S1.75 |
Solar Thermal Support Framing Plan Part 5 | 10/31/08 | ||
S1.76 |
Roof Framing Plan Part 6 | 11/18/08 | ||
S1.77 |
Roof Framing Plan Part 7 | 11/18/08 | ||
S1.78 |
Roof Framing Plan Part 8 | 11/18/08 | ||
S1.79 |
Roof Framing Plan Part 9 | 11/18/08 | ||
S2.01 |
Foundation Schedules and Details | 1/19/09 | ||
S2.02 |
Foundation Schedules and Details | 1/19/09 | ||
S2.03 |
Foundation Schedules and Details | 9/19/08 | ||
S2.04 |
Foundation Schedules and Details | 1/19/09 | ||
S2.05 |
Foundation Schedules and Details | 1/19/09 | ||
S2.11 |
Steel Column Schedule | 1/19/09 | ||
S2.12 |
Steel Column Schedule | 1/19/09 | ||
S2.13 |
Steel Column Schedule . | 1/19/09 | ||
S2.15 |
Steel Column Schedule | 1/19/09 | ||
S2.16 |
Steel Column Details | 1/19/09 | ||
S2.30 |
Concrete Column Details-High Containment | 10/31/08 | ||
S2.31 |
Concrete Column Schedule-High Containment. | 10/31/08 | ||
S2.35 |
Concrete Bearing Wall Details-High Containment | 10/31/08 | ||
S2.36 |
Concrete Bearing Wall Details-High Containment | 10/31/08 | ||
S2.37 |
Concrete Bearing Wall Details-High Containment | 10/31/08 | ||
S2.50 |
Concrete Slab Details-High Containment | 10/31/08 | ||
S2.51 |
Concrete Beam Details-High Containment | 10/31/08 | ||
S2.52 |
Concrete Beam Schedule-High Containment | 10/31/08 | ||
S2.53 |
Concrete Beam Schedule-High Containment | 10/31/08 | ||
S0.012 |
Cover Sheet-Structural-Part 2 | 1/19/09 | ||
S0.022 |
Index of Drawings-Structural-Part 2 | 1/19/09 | ||
S3.01 |
Braced Frame Details | 11/18/08 | ||
S3.02 |
Braced Frame Elevations | 1/19/09 | ||
S3.03 |
Braced Frame Elevations | 11/18/08 | ||
S3.04 |
Braced Frame Elevations | 11/18/08 | ||
S3.05 |
Braced Frame Elevations | 1/19/09 | ||
S3.06 |
Diagonal Brace Elevation Along Grid Line EA | 10/31/08 | ||
S3.07 |
Diagonal Brace Elevation Along Grid Line EB | 11/18/08 | ||
S3.08 |
Braced Frame Connection Schedule | 1/19/09 | ||
S3.09 |
Braced Frame Connection Schedule | 1/19/09 | ||
S3.11 |
Foundations Sections and Details | 1/19/09 | ||
S3.12 |
Foundations Sections and Details | 1/19/09 | ||
S3.13 |
Foundations Sections and Details | 1/19/09 | ||
S3.13-X |
Foundations Sections and Details | 1/19/09 | ||
S3.14 |
Foundations Sections and Details | 1/19/09 | ||
S3.23 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.21 |
Superstructure Steel Sections and Details | 1/19/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 16 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
S3.22 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.23 |
Superstructure Steel Sections and Details | 9/19/08 | ||
S3.24 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.25 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.26 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.27 |
Superstructure Steel Sections and Details | 11/18/08 | ||
S3.28 |
Superstructure Steel Sections and Details | 10/31/08 | ||
S3.29 |
Superstructure Steel Sections and Details | 10/31/08 | ||
S3.31 |
Superstructure Sections and Details | 10/31/08 | ||
S3.32 |
Superstructure Sections and Details | 10/31/08 | ||
S3.41 |
Superstructure Framing Details-High Containment | 1/19/09* | ||
S3.51 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.52 |
Superstructure Steel Sections and Details | 11/18/08 | ||
S3.53 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.54 |
Superstructure Steel Sections and Details | 1/19/09 | ||
S3.55 |
Axial Connection Schedule and Details | 1/19/09 | ||
S4.01 |
Foundation Typical Details | 11/18/08 | ||
S4.02 |
Slab on Grade Typical Details | 9/19/08 | ||
S4.11 |
Superstructure Steel Typical Details | 1/18/08 | ||
S4.12 |
Superstructure Steel Typical Details | 11/18/08 | ||
S4.13 |
Superstructure Steel Typical Details | 11/18/08 | ||
SS0.011 |
Cover Sheet-Structural Security | 1/19/09 | ||
SS0.021 |
Index of Drawings-Structural Security | 1/19/09 | ||
SS1.21 |
Floor 2 PCP Connections Plan Part 1 and General Information | 11/18/08 | ||
SS1.22 |
Floor 2 PCP Connections Plan Part 2 | 11/18/08 | ||
SS1.23 |
Floor 2 PCP Connections Plan Part 3 | 11/18/08 | ||
SS1.24 |
Floor 2 PCP Connections Plan Pert 4 | 1/19/09 | ||
SS1.25 |
Floor 2 PCP Connections Plan Part 5 | 11/18/08 | ||
SS1.26 |
Floor 2 PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.27 |
Floor 2 PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.28 |
Floor 2 PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.29 |
Floor 2 PCP Connections Plan Part 9 | 11/18/08 | ||
SS1.31 |
Floor 3 PCP Connections Plan Part 1 | 11/18/08 | ||
SS1.32 |
Floor 3 PCP Connections Plan Part 2 | 11/18/08 | ||
SS1.33 |
Floor 3 PCP Connections Plan Part 3 | 1/19/09 | ||
SS1.34 |
Floor 3 PCP Connections Plan Part 4 | 1/19/09 | ||
SS1.35 |
Floor 3 PCP Connections Plan Part 5 | 1/18/08 | ||
SS1.36 |
Floor 3 PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.37 |
Floor 3 PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.38 |
Floor 3 PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.39 |
Floor 3 PCP Connections Plan Part 9 | 11/18/08 | ||
SS1.41 |
Floor 4 PCP Connections Plan Part 1 | 11/18/08 | ||
SS1.42 |
Floor 4 PCP Connections Plan Part 2 | 1/19/09 | ||
SS1.43 |
Floor 4 PCP Connections Plan Part 3 | 1/19/09 | ||
SS1.44 |
Floor 4 PCP Connections Plan Part 4 | 1/19/09 | ||
SS1.45 |
Floor 4 PCP Connections Plan Part 5 | 11/18/08 | ||
SS1.46 |
Floor 4 PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.47 |
Floor 4 PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.48 |
Floor 4 PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.49 |
Floor 4 PCP Connections Plan Part 9 | 11/18/08 | ||
SS1.51 |
Floor 5 PCP Connections Plan Part 1 | 11/18/08 | ||
SS1.52 |
Floor 5 PCP Connections Plan Part 2 | 1/19/09 | ||
SS1.53 |
Floor 5 PCP Connections Plan Part 3 | 1/19/09 | ||
SS1.54 |
Floor 5 PCP Connections Plan Part 4 | 1/19/09 | ||
SS1.55 |
Floor 5 PCP Connections Plan Part 5 | 1/19/09 | ||
SS1.56 |
Floor 5 PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.57 |
Floor 5 PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.58 |
Floor 5 PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.59 |
Floor 5 PCP Connections Plan Part 9 | 11/18/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 17 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
SS1.61 |
Floor 6 PCP Connections Plan Part 1 | 11/18/08 | ||
SS1.62 |
Floor 6 PCP Connections Plan Part 2 | 11/18/08 | ||
SS1.63 |
Floor 6 PCP Connections Plan Part 3 | 11/18/08 | ||
SS1.64 |
Floor 6 PCP Connections Plan Part 4 | 11/18/08 | ||
SS1.65 |
Floor 6 PCP Connections Plan Part 5 | 11/18/08 | ||
SS1.66 |
Floor 5 PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.67 |
Floor 6 PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.68 |
Floor 6 PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.69 |
Floor 6 PCP Connections Plan Part 9 | 11/18/08 | ||
SS1.6P1 |
Roof (Floor 6P) POP Connections Plan Part 1 | 11/18/08 | ||
SS1.6P2 |
Roof (Floor 6P) PCP Connections Plan Part 2 | 11/18/08 | ||
SS1.6P3 |
Roof (Floor 6P) PCP Connections Plan Part 3 | 11/18/08 | ||
SS1.6P4 |
Roof (Floor 6P) PCP Connections Plan Part 4 | 11/18/08 | ||
SS1.6P5 |
Roof (Floor 6P) PCP Connections Plan Part 5 | 11/18/08 | ||
SS1.6P6 |
Roof (Floor 6P) PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.6P7 |
Roof (Floor 6P) PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.6P8 |
Roof (Floor 6P) PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.6P9 |
Roof (Floor 6P) PCP Connections Plan Part 9 | 11/18/08 | ||
SS1.76 |
Roof PCP Connections Plan Part 6 | 11/18/08 | ||
SS1.77 |
Roof PCP Connections Plan Part 7 | 11/18/08 | ||
SS1.78 |
Roof PCP Connections Plan Part 8 | 11/18/08 | ||
SS1.79 |
Roof PCP Connections Plan Part 9 | 11/18/08 | ||
SS2.21 |
Tie Connections Schedule and Details | 1/19/09 | ||
SS2.22 |
Continuity Connection Schedule and Details | 11/18/08 | ||
SS3.21 |
Superstructure POP Steel Sections and Details | 11/18/08 | ||
MECHANICAL | ||||
ICO.011 |
Cover Sheet-BMS | 1/19/09 | ||
ICO.021 |
Index of Drawings-BMS | 10/31/08 | ||
ICO.11 |
Building Management System (EMS) Symbols and Abbreviations | 10/31/08 | ||
IC1.01 |
BMS Architecture Diagram | 10/31/08 | ||
IC1.02 |
Environmental Monitoring System (EMS) Architecture Diagram | 10/31/08 | ||
IC2.01 |
BMS Control Diagram AHU-ABSL2-1, AHU-ABSL2-2, AHU-ABSL2-3, AHU-ABSL2-4 | 10/31/08 | ||
IC2.02 |
BMS Control Diagram AHU-ABSL-3E-2-1 & 4-15 | 10/31/08 | ||
IC2.03 |
BMS Control Diagram AHU-ABSL-3E-2-2 | 10/31/08 | ||
IC2.04 |
BMS Control Diagram AHIJ-ABSL-3E-4-1 | 10/31/08 | ||
IC2.05 |
BMS Control Diagram AHU-ABSL-3E-4-2 | 10/31/08 | ||
IC2.06 |
BMS Control Diagram AHU-ABSL-3E-4-3 & 4-3S | 10/31/08 | ||
IC2.07 |
BMS Control Diagram AHU-ABSL-3E-4-4 | 10/31/08 | ||
IC2.08 |
BMS Control Diagram AHU-ABSL-3E-4-5 | 10/31/08 | ||
IC2.09 |
BMS Control Diagram AHU-ABSL-3E-4-6 | 10/31/08 | ||
IC2.10 |
BMS Control Diagram AHU-ABSL-3E-2-5 & 2-5S | 10/31/08 | ||
IC2.11 |
BMS Control Diagram AHU-ABSL-3E-2-6 | 10/31/08 | ||
IC2.12 |
BMS Control Diagram AHU-ABSL-3E-2-7 | 10/31/08 | ||
IC2.13 |
BMS Control Diagram AHU-ABSL-3E-2-8 | 10/31/08 | ||
IC2.14 |
BMS Control Diagram ABSL2 BarrierAHU Barrier-1 & -2 | 10/31/08 | ||
IC2.15 |
BMS Control Diagram HRU/EF BSL-3E Aero | 10/31/08 | ||
IC2.16 |
BMS Controls AHU BSL4 | 10/31/08 | ||
IC2.17 |
BMS Controls Aerobiology | 10/31/08 | ||
IC2.18 |
BMS Control Diagram AHU-ADM WKM | 9/19/08 | ||
IC2.19 |
BMS Control Diagram AHU BSL-2-1, 2-2 and 2-3 | 10/31/08 | ||
IC2.20 |
BMS Control Diagram AHU-BSL-2-4 | 10/31/08 | ||
IC2.21 |
BMS Control Diagram (Atrium and Amenities)AHU-ATM-1 & 2 | 10/31/08 | ||
IC2.22 |
BMS Control Diagram Offices) AHU-Lab Off-1, -2 & -3 | 10/31/08 | ||
IC2.23 |
BMS Control Diagram (Logistics NET Offices) AHU-Log Off1 & 2 | 10/31/08 | ||
IC2.24 |
BMS Control Diagram AHU-ADM CL-1 & 2 | 9/19/08 | ||
IC2.25 |
BMS Control Diagram (Non Containment Corridor) AHU-NCTM Corr 2-3, 2-4 & 4-7 | 10/31/08 | ||
IC2.26 |
BMS Control Diagram Chilled and Process Water Systems | 9/19/08 | ||
IC2.27 |
BMS Control Diagram Preheat and Reheat Systems | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 18 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
IC2.28 |
BMS Control Diagram-1st Floor Device Location Drawing | 1/12/09 | ||
IC2.29 |
BMS Control Diagram-2nd Floor Device Location Drawing | 10/31/08 | ||
IC2.30 |
BMS Control Diagram-2nd Floor Device Location Drawing | 9/19/08 | ||
IC2.31 |
BMS Control Diagram-2nd Floor Device Location Drawing | 10/31/08 | ||
IC2.32 |
BMS Control Diagram-2nd Floor Device Location Drawing | 10/31/08 | ||
IC2.33 |
MC Control Diagram-3rd Floor Device Location Drawing | 9/19/08 | ||
IC2.34 |
BMS Control Diagram-4th Floor Device Location Drawing | 10/31/08 | ||
IC2.35 |
BMS Control Diagram-4th Floor Device Location Drawing | 1/12/09* | ||
IC2.36 |
BMS Control Diagram-4th Floor Device Location Drawing | 9/19/08 | ||
IC2.37 |
BMS Control Diagram-4th Floor Device Location Drawing | 9/19/08 | ||
IC2.38 |
BMS Control Diagram-5th Floor Device Location Drawing | 9/19/08 | ||
IC2.39 |
BMS Control Diagram-BSL-4 Floor Device Location Drawings | 10/31/08 | ||
IC2.40 |
BMS Control Diagram-Device Locations for O2/LN2 Piping | 1/12/09 | ||
IC3.01 |
BMS Control Diagram-Room Details, Non-GLP | 9/19/08 | ||
IC3.02 |
BMS Control Diagram-Room Details, GLP | 9/19/08 | ||
IC3.03 |
BMS Control Diagram-Room Details, Miscellaneous | 1/12/09 | ||
IC3.04 |
BMS Control Diagram-Room Details, Miscellaneous | 10/31/08 | ||
IC3.05 |
BMS Control Diagram-BSL4 Lab | 9/19/08 | ||
IC3.05A |
BMS Control Diagram-BSL4 Lab Suite Control -Part 1 | 10/31/08 | ||
IC3.05B |
BMS Control Diagram-BSL4 Lab Suite Control -Part 2 | 10/31/08 | ||
IC3.06 |
BMS Control Diagram-BSL4 Animal Rooms | 9/19/08 | ||
IC3.06A |
BMS Control Diagram-ABSL-4 Vivarium Suite Control-Part 1 | 10/31/08 | ||
IC3.06B |
BMS Control Diagram-ABSL-4 Vivarium Suite Control-Part 2 | 10/31/08 | ||
IC3.07 |
BMS Control Diagram-Aerobiology | 9/19/08 | ||
IC3.07A |
BMS Control Diagram-Aerobiology/Suit Room Control-Part 1 | 10/31/08 | ||
IC3.07B |
BMS Control Diagram-Aerobiology/Suit Room Control-Part 2 | 10/31/08 | ||
IC3.08 |
BMS Control Diagram Imaging | 1/12/09 | ||
IC3.09 |
BMS Control Diagram-2nd Floor BSL-3E Aerobiology | 9/19/08 | ||
IC3.10 |
BMS Control Diagram-4th Floor South BSL-3E Aerobiology | 9/19/08 | ||
IC3.11 |
BMS Control Diagram-4th Floor North 1BSL-3E Aerobiology | 9/19/08 | ||
IC3.12 |
BMS Control Diagram-Miscellaneous Details, Part 1 | 1/12/09 | ||
IC3.13 |
BMS Control Diagram-Miscellaneous Details Part 2 | 10/31/08 | ||
IC3.14 |
BMS Control Diagram-Miscellaneous Details, Part 3 | 10/31/08 | ||
IC3.15 |
BMS Control Diagram-Miscellaneous Details, Part 4 | 1/12/09 | ||
IC3.16 |
BMS Control Diagram-(A)BSL-3E Standby Equipment Control | 9/19/08 | ||
IC3.17 |
BMS Control Diagram-Chemical Shower System | 1/12/09 | ||
IC3.18 |
BMS Control Diagram-Miscellaneous Details-Part 5 | 10/31/08 | ||
IC4.01 |
BMS Instrument Air System-Part 1, Non-Containment & Containment Level 2 | 10/31/08 | ||
IC4.02 |
BMS Instrument Air System-Part 2, Containment Level 3 | 10/31/08 | ||
IC4.03 |
BMS Instrument Air System-Part 3, High Containment Level 4 | 10/31/08 | ||
M0.011 |
Cover Sheet-Mechanical-Part 1 | 1/12/09* | ||
M0.021 |
Index of Drawings-Mechanical-Part 1 | 1/19/09 | ||
M0.11 |
General Information-Part 1 | 9/19/08 | ||
M0.12 |
General information-Part 2 | 9/19/08 | ||
M0.20 |
Basement and Tunnel Key Plan | 9/19/08 | ||
M0.21 |
Floor 1 and 2 Key Plans | 9/19/08 | ||
M0.23 |
Floor 3 and 4 Key Plans | 9/19/08 | ||
M0.25 |
Floor 5 and 6 Key Plans | 9/19/08 | ||
M0.26P |
Floor 6P Key Plan | 9/19/08 | ||
M0.27 |
Roof Key Plan | 10/31/08 | ||
M0.30 |
Basement HVAC Zoning Plan | 9/19/08 | ||
M0.31 |
Floor 1 HVAC Zoning Plan | 9/19/08 | ||
M0.32 |
Floor 2 HVAC Zoning Plan | 9/19/08 | ||
M0.33 |
Floor 3 HVAC Zoning Plan | 9/19/08 | ||
M0.34 |
Floor 4 HVAC Zoning Plan | 9/19/08 | ||
M0.35 |
Floor 5 HVAC Zoning Plan | 9/19/08 | ||
M0.36 |
Floor 6 HVAC Zoning Plan | 9/19/08 | ||
M0.404 |
Basement Duct Distribution Key Plan Part 5 4 & 5 | 1/19/09 | ||
M0.409 |
Basement Duct Distribution Key Plan Part 9 | 1/19/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 19 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M0.411 |
Floor 1 Duct Distribution Key Plan Part 5 1 to 5 | 1/19/09 | ||
M0.416 |
Floor 1 Duct Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
M0.421 |
Floor 2 Duct Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M0.426 |
Floor 2 Duct Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
M0.431 |
Floor 3 Duct Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M0.436 |
Floor 3 Duct Distribution Key Plan Parts 6 to 9 | 9/19/09 | ||
M0.441 |
Floor 4 Duct Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M0.446 |
Floor 4 Duct Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
M0.451 |
Floor 5 Duct Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M0.456 |
Floor 5 Duct Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
M0.461 |
Floor 6 Duct Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M0.466 |
Floor 6 Duct Distribution Key Plan Parts 6 to 9 | 1/12/09 | ||
M0.46P6 |
Floor 6 Duct Distribution Key Plan Parts 6 to 10 | 1/12/09 | ||
M0.4R1 |
Roof Duct Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M0.4R6 |
Roof Duct Distribution Key Plan Parts 6 to 9 | 10/31/08 | ||
MP0.404 |
Basement Piping Distribution Key Plan Parts 4 & 5 | 1/19/09 | ||
MP0.409 |
Basement Piping Distribution Key Plan Part 9 | 1/19/09 | ||
MP0.411 |
Floor 1 Piping Distribution Key Plan Parts 1 to 5 | 1/19/09 | ||
MP0.416 |
Floor 1 Piping Distribution Key Plan Parts 6 to 9 | 1/19/09 | ||
MP0.421 |
Floor 2 Piping Distribution Key Plan Parts 1 to 5 | 9/19/08 | ||
MP0.426 |
Floor 2 Piping Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
MP0.431 |
Floor 5 Piping Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
MP0.436 |
Floor 5 Piping Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
MP0.441 |
Floor 4 Piping Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
MP0.446 |
Floor 4 Piping Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
MP0.451 |
Floor 5 Piping Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
MP0.456 |
Floor 5 Piping Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
MP0.461 |
Floor 6 Piping Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
MP0.466 |
Floor 6 Piping Distribution Key Plan Parts 6 to 9 | 10/31/08 | ||
MP0.46P6 |
Floor 6P Piping Distribution Key Plan Parts 6 to 9 | 9/19/08 | ||
MP0.4R1 |
Roof Piping Distribution Key Plan Parts 1 to 5 | 10/31/08 | ||
M2.04F |
Basement Floor Plan Part 4F | 1/19/09 | ||
M2.04F-X |
Basement Floor Plan Part 4F-Bid Option #29 | 12/1/08 | ||
M2.09A |
Basement Floor Plan Part 9A & B | 1/19/09 | ||
M2.09A-X |
Basement Floor Plan Part 9A & B-Bid Option #29 | 12/1/08 | ||
M2.09D |
Basement Floor Plan Part 9D | 1/19/09 | ||
M2.09D-X |
Basement Floor Plan Part 9D-Bid Option #29 | 12/1/08 | ||
M2.11A |
Floor 1 Plan Part 1A | 1/12/09 | ||
M2.11A-X |
Floor 1 Plan Part 1A-Bid Option #03 | 1/19/09 | ||
M2.11B |
Floor 1 Plan Part 1B | 1/12/09 | ||
M2.11B-X |
Floor 1 Plan Part 18-Bid Option #03 | 1/19/09 | ||
M2.12A |
Floor 1 Plan Part 2A | 9/19/08 | ||
M2.12B |
Floor 1 Plan Part 2B | 9/19/08 | ||
M2.12C |
Floor 1 Plan Part 2C | 9/19/08 | ||
M2.13A |
Floor 1 Plan Part 3A | 9/19/08 | ||
M2.13B |
Floor 1 Plan Part 3B | 9/19/08 | ||
M2.13C |
Floor 1 Plan Part 3C | 9/19/08 | ||
M2.14A |
Floor 1 Plan Part 4A | 10/31/08 | ||
M2.14B |
Floor 1 Plan Part 4B | 9/19/08 | ||
M2.14C |
Floor 1 Plan Part 4C | 9/19/08 | ||
M2.14D |
Floor 1 Plan Part 4E | 10/31/08 | ||
M2.14E |
Floor 1 Plan Part 4D | 10/31/08 | ||
M2.14F |
Floor l Plan Part 4F | 1/19/09 | ||
M2.14F-X |
Floor l Plan Part 4F | 12/1/08 | ||
M2.15A |
Floor 1 Plan Part 5A | 10/31/08 | ||
M2.15B |
Floor 1 Plan Part 5B | 10/31/08 | ||
M2.15C |
Floor 1 Plan Part 5C | 10/31/08 | ||
M2.15D |
Floor 1 Plan Part 5D | 10/31/08 | ||
M2.16A |
Floor 1 Plan Part 6A 7 B | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 20 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M2.16C |
Floor 1 Plan Part 6C | 10/31/08 | ||
M2.16D |
Floor 1 Plan Part 6D | 10/31/08 | ||
M2.17A |
Floor 1 Plan Part 7A&B | 9/19/08 | ||
M2.17C |
Floor 1 Plan Part 7C | 10/31/08 | ||
M2.17D |
Floor 1 Plan Part 7D | 10/31/08 | ||
M2.18A |
Floor 1 Plan Part 8A &B | 10/31/08 | ||
M2.18C |
Floor 1 Plan Part 8C | 1/12/09 | ||
M2.18D |
Floor 1 Plan Part 8D | 9/19/08 | ||
M2.19A |
Floor l Plan Part 9A&B | 1/19/09 | ||
M2.19C |
Floor 1 Plan Part 9C | 9/19/08 | ||
M2.19D |
Floor 1 Plan Part 9D | 1/19/09 | ||
M2.21A |
Floor 2 Plan Part 1A | 1/12/09 | ||
M2.21A-X |
Floor 2 Plan Part 1A-Bid Option #03 | 1/19/09 | ||
M2.21B |
Floor 2 Plan Part 1B | 1/12/09 | ||
M2.21B-X |
Floor 2 Plan Part 1B-Bid Option #03 | 1/19/09 | ||
M2.22A |
Floor 2 Plan Part 2A | 10/31/08 | ||
M2.22B |
BSL4 Floor 2 Plan Part 2B | 10/31/08 | ||
M2.22C |
BSL4 Floor 2 Plan Part 2C | 10/31/08 | ||
M2.23A |
Floor 2 Plan Part 3A | 10/31/08 | ||
M2.23B |
BSL4 Floor 2 Plan Part 3B | 10/31/08 | ||
M2.23C |
BSL4 Floor 2 Plan Part 3C | 10/31/08 | ||
M2.24A |
Floor 2 Plan Part 4A | 9/19/08 | ||
M2.24B |
Floor 2 Plan Part 4B | 9/19/08 | ||
M2.24C |
Floor 2 Plan Part 4C | 1/12/09 | ||
M2.24D |
Floor 2 Plan Part 4D | 9/19/08 | ||
M2.24E |
Floor 2 Plan Part 4E | 9/19/08 | ||
M2.24F |
Floor 2 Plan Part 4F | 1/12/09 | ||
M2.25A |
Floor 2 Plan Part 5A | 9/19/08 | ||
M2.25B |
Floor 2 Plan Part 5B | 9/19/08 | ||
M2.25C |
Floor 2 Plan Part 5C | 9/19/08 | ||
M2.25D |
Floor 2 Plan Part 5D | 9/19/08 | ||
M2.26A |
Floor 2 Plan Part 6A & B | 10/31/08 | ||
M2.26C |
Floor 2 Plan Part 6C | 10/31/08 | ||
M2.26D |
Floor 2 Plan Part 6D | 9/19/08 | ||
M2.27C |
Floor 2 Plan Part 7C | 9/19/08 | ||
M2.27D |
Floor 2 Plan Part 7D | 9/19/08 | ||
M2.28A |
Floor 2 Plan Part 8A & B | 9/19/08 | ||
M2.28C |
Floor 2 Plan Part 8C | 9/19/08 | ||
M2.28D |
Floor 2 Plan Part 8D | 9/19/08 | ||
M2.29A |
Floor 2 Plan Part 9A | 10/31/08 | ||
M2.29C |
Floor 2 Plan Part 9C | 9/19/08 | ||
M2.29D |
Floor 2 Plan Part 9D | 10/31/08 | ||
M2.31A |
Floor 3 Plan Part 1A | 1/19/09 | ||
M2.31B |
Floor 3 Plan Part 1B | 10/31/08 | ||
M2.32A |
Floor 3 Plan Part 2A | 10/31/08 | ||
M2.32B |
BSL4 Floor 3 Plan Part 2B | 10/31/08 | ||
MP2.32B |
BSL4 Floor 3 Plan Part 2B | 10/31/08 | ||
M2.32C |
BSL4 Floor 3 Plan Part 2C | 1/12/09 | ||
MP2.32C |
BSL4 Floor 3 Plan Part 2C | 10/31/08 | ||
M2.33A |
Floor 3 Plan Part 3A | 10/31/08 | ||
M2.33B |
BSL4 Floor 3 Plan Part 3B | 10/31/08 | ||
MP2.33B |
BSL4 Floor 3 Plan Part 3B | 10/31/08 | ||
M2.33B |
BSL4 Floor 3 Plan Part 3C | 10/31/08 | ||
MP2.33C |
BSL4 Floor 3 Plan Part 3C | 10/31/08 | ||
M2.34A |
Floor 3 Plan Part 4A | 10/31/08 | ||
M2.34B |
Floor 3 Plan Part 4B | 10/31/08 | ||
M2.34C |
Floor 3 Plan Part 4C | 1/19/09 | ||
M2.34D |
Floor 3 Plan Part 4D | 10/31/08 | ||
M2.34E |
Floor 3 Plan Part 4E | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 21 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M2.34F |
Floor 3 Plan Part 4F | 1/12/09 | ||
M2.35A |
Floor 5 Plan Part 5A | 10/31/08 | ||
M2.35B |
Floor 3 Plan Part 5B | 10/31/08 | ||
M2.35C |
Floor 3 Plan Part 5C | 9/19/08 | ||
M2.35D |
Floor 3 Plan Part 5D | 10/31/08* | ||
M2.36A |
Floor 3 Plan Part 6A & B | 10/31/08* | ||
M2.36C |
Floor 5 Plan Part 6C | 12/1/08 | ||
M2.36D |
Floor 3 Plan Part 6D | 1/19/09 | ||
M2.37C |
Floor 3 Plan Part 7C | 9/19/08 | ||
M2.37D |
Floor 3 Plan Part 7D | 10/31/08 | ||
M2.38A |
Floor 3 Plan Part 8A & B | 10/31/08 | ||
M2.38C |
Floor 5 Plan Part 8C | 9/19/08 | ||
M2.38D |
Floor 3 Plan Part 8D | 9/19/08 | ||
M2.39A |
Floor 3 Plan Part 9A&B | 10/31/08 | ||
M2.39C |
Floor 5 Plan Part 9C | 9/19/08 | ||
M2.39D |
Floor 5 Plan Part 9D | 1/19/09 | ||
M0.012 |
Cover Sheet-Mechanical-Part 2 | 1/12/09* | ||
M0.022 |
Index of Drawings-Mechanical-Part 2 | 12/1/08 | ||
M0.11 |
General Information-Part 1 | 9/19/08 | ||
M0.12 |
General Information-Part 2 | 9/19/08 | ||
M2.41A |
Floor 4 Plan Part 1A | 10/31/08 | ||
M2.41B |
Floor 4 Plan Part 1B | 10/31/08 | ||
M2.41B-X |
Floor 4 Plan Part 1B-Bid Option #03 | 10/31/08 | ||
M2.42A |
Floor 4 Plan Part 2A | 9/19/08 | ||
M2.42B |
Floor 4 Plan Part 2B | 9/19/08 | ||
M242C |
Floor 4 Plan Part 2C | 9/19/08 | ||
M2.43A |
Floor 4 Plan Part 3A | 12/1/08 | ||
M2.43B |
Floor 4 Plan Part 3B | 10/31/08 | ||
M2.43C |
Floor 4 Plan Part 3C | 9/19/08 | ||
M2.44A |
Floor 4 Plan Part 4A | 9/19/08 | ||
M2.44B |
Floor 4 Plan Part 4B | 9/19/08 | ||
M2.44C |
Floor 4 Plan Part 4C | 10/31/08 | ||
M2.44D |
Floor 4 Plan Part 4D | 9/19/08 | ||
M2.44E |
Floor 4 Plan Part 4E | 9/19/08 | ||
M2.44F |
Floor 4 Plan Part 4F | 1/19/09 | ||
M2.45A |
Floor 4 Plan Part 5A | 10/31/08 | ||
M2.45B |
Floor 4 Plan Part 5B | 9/19/08 | ||
M2.45C |
Floor 4 Plan Part 5C | 9/19/08 | ||
M2.45D |
Floor 4 Plan Part 5D | 9/19/08 | ||
M2.46A |
Floor 4 Plan Part 6A & B | 10/31/08 | ||
M2.46C |
Floor 4 Plan Part 6C | 12/1/08 | ||
M2.46D |
Floor 4 Plan Part 6D | 10/31/08 | ||
M2.47C |
Floor 4 Plan Part 7C | 10/31/08 | ||
M2.47D |
Floor 4 Plan Part 7D | 10/31/08 | ||
M2.48A |
Floor 4 Plan Part 8A & B | 10/31/08 | ||
M2.48C |
Floor 4 Plan Part 8C | 9/19/08 | ||
M2.48D |
Floor 4 Plan Part 8D | 10/31/08 | ||
M2.49A |
Floor 4 Plan Part 9A& B | 10/31/08 | ||
M2.49C |
Floor 4 Plan Part 9C | 10/31/08 | ||
M2.49D |
Floor 4 Plan Part 9D | 10/31/08 | ||
M2.51A |
Floor 5 Plan Part 1A | 10/31/08 | ||
M2.51B |
Floor 5 Plan Part 18 | 10/31/08 | ||
M2.51B-X |
Floor 5 Plan Part 18-Bid Option #03 | 10/31/08 | ||
M2.52A |
Floor 5 Plan Part 2A | 10/31/08 | ||
M2.52B |
Floor 5 Plan Part 2B | 10/31/08 | ||
M2.52C |
Floor 5 Plan Part 2C | 10/31/08 | ||
M2.53A |
Floor 5 Plan Part 3A | 10/31/08 | ||
M2.53B |
Floor 5 Plan Part 38 | 10/31/08 | ||
M2.53C |
Floor 5 Plan Part 3C | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 22 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M2.54A |
Floor 5 Plan Part 4A | 10/31/08 | ||
M2.54B |
Floor 5 Plan Part 4B | 10/31/08 | ||
M2.54C |
Floor 5 Plan Part 4C | 9/19/08 | ||
M2.54D |
Floor 5 Plan Part 4D | 9/19/08 | ||
M2.54E |
Floor 5 Plan Part 4E | 10/31/08 | ||
M2.54F |
Floor 5 Plan Part 4F | 1/19/09 | ||
M2.55A |
Floor 5 Plan Part 5A | 10/31/08 | ||
M2.55B |
Floor 5 Plan Part 5B | 9/19/08 | ||
M2.55C |
Floor 5 Plan Part 5C | 10/31/08 | ||
M2.55D |
Floor 5 Plan Part 5D | 9/19/08 | ||
M2.56A |
Floor 5 Plan Part 6A &B | 10/31/08 | ||
M2.56C |
Floor 5 Plan Part 6C | 10/31/08 | ||
M2.56D |
Floor 5 Plan Part 6C | 10/31/08 | ||
M2.57A |
Floor 5 Plan Part 7A & B | 9/19/08 | ||
M2.57C |
Floor 5 Plan Part 7C | 10/31/08 | ||
M2.57D |
Floor 5 Plan Part 7D | 10/31/08 | ||
M2.58C |
Floor 5 Plan Part 8C | 10/31/08 | ||
M2.58D |
Floor 5 Plan Part 8D | 10/31/08 | ||
M2.59A |
Floor 5 Plan Part 9A & B | 9/19/08 | ||
M2.59C |
Floor 5 Plan Part 9C | 10/31/08 | ||
M2.59D |
Floor 5 Plan Part 9D | 10/31/08 | ||
M2.61A |
Floor 6 Plan Part 1A | 10/31/08 | ||
M2.61B |
Floor 6 Plan Part 1B | 10/31/08 | ||
M2.61B-X |
Floor 6 Plan Part 1B-Bid Option #03 | 10/31/08 | ||
M2.62A |
Floor 6 Plan Part 2A | 10/31/08 | ||
M2.62B |
Floor 6 Plan Part 2B | 10/31/08 | ||
M2.62C |
Floor 6 Plan Part 2C | 10/31/08 | ||
M2.63A |
Floor 6 Plan Part 3A | 10/31/08 | ||
M2.63B |
Floor 5 Plan Part 3B | 10/31/08 | ||
M2.63C |
Floor 6 Plan Part 3C | 9/19/08 | ||
M2.64A |
Floor 6 Plan Part 4A | 9/19/08 | ||
M2.64B |
Floor 6 Plan Part 4B | 9/19/08 | ||
M2.64C |
Floor 6 Plan Part 4C | 9/19/08 | ||
M2.64D |
Floor 6 Plan Part 4D | 9/19/08 | ||
M2.64E |
Floor 6 Plan Part 4E | 9/19/08 | ||
M2.64F |
Floor 6 Plan Part 4F | 1/12/09 | ||
M2.65A |
Floor 6 Plan Part 5A | 9/19/08 | ||
M2.655 |
Floor 6 Plan Part 5B | 9/19/08 | ||
M2.65C |
Floor 6 Plan Part 5C | 10/31/08 | ||
M2.65D |
Floor 6 Plan Part 5D | 10/31/08 | ||
M2.66A |
Floor 6 Plan Part 6A | 10/31/08 | ||
M2.66C |
Floor 6 Plan Part 6C | 9/19/08 | ||
M2.66D |
Floor 6 Plan Part 6D | 10/31/08 | ||
M2.67C |
Floor 6 Plan Part 7C | 1/12/09 | ||
M2.67C-X |
Floor 6 Plan Part 7C-Bid Option #42 | 1/12/09 | ||
M2.67D |
Floor 6 Plan Part 7D | 1/12/09 | ||
M2.67D-X |
Floor 6 Plan Part 7D-Bid Option #42 | 1/12/09 | ||
M2.68C |
Floor 6 Plan Part 8C | 10/31/08 | ||
M2.68D |
Floor 6 Plan Part 8D | 9/19/08 | ||
M2.69A |
Floor 6 Plan Part 9A & B | 9/19/08 | ||
M2.69C |
Floor 6 Plan Part 9C | 10/31/08 | ||
M2.69D |
Floor 6 Plan Part 9D | 10/31/08 | ||
M2.6P4F |
Floor 6P Plan Part 4F | 9/19/08 | ||
M2.6P6C |
Floor 6P Plan Part 60 | 10/31/08 | ||
M2.6P6D |
Floor 6P Plan Part 6D | 10/31/08 | ||
M2.6P7C |
Floor 6P Plan Part 7C | 1/12/09 | ||
M2.6P7C-X |
Floor 6P Plan Part 7C-Bid Option #42 | 1/12/09 | ||
M2.6P7D |
Floor 6P Plan Part 7D | 1/12/09 | ||
M2.6P7D-X |
Floor 6P Plan Part 7D-Bid Option #42 | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 23 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M2.6P8C |
Floor 6P Plan Part 8C | 10/31/08 | ||
M2.6P8D |
Floor 6P Plan Part 8D | 10/31/08 | ||
M2.6P9C |
Floor 6P Plan Part 9C | 10/31/08 | ||
M2.6P9D |
Floor 6P Plan Part 9D | 10/31/08 | ||
M2.R4E |
Roof Plan Part 4E | 9/19/08 | ||
M0.013 |
Cover Sheet-Mechanical-Part 3 | l/12/09* | ||
M0.023 |
Index of Drawings-Mechanical-Part 3 | 12/1/08 | ||
M0.11 |
General Information Part 1 | 9/19/08 | ||
M0.12 |
General Information Part 2 | 9/19/08 | ||
M3.01 |
Airflow Diagram (Lab Offices and Amenities) | 9/19/08 | ||
M3.02 |
Airflow Diagram (Atrium) | 9/19/08 | ||
M3.03 |
Airflow Diagram (Logistics and VET MED) | 9/19/08 | ||
M3.04 |
Airflow Diagram (BSL-2) | 9/19/08 | ||
M3.05 |
Airflow Diagram ABSL-2 Zone 6A Main) | 9/19/08 | ||
M3.06 |
Airflow Diagram (ABSL-2 Zone 6A Floor 2S) | 9/19/08 | ||
M3.07 |
Airflow Diagram (ABSL-2 Zone 6A Floor 2N) | 9/19/08 | ||
M3.08 |
Airflow Diagram (ABSL-2 Zone 6A Floor 4S) | 9/19/08 | ||
M3.09 |
Airflow Diagram (ABSL-2 Zone 6A Floor 4N) | 9/19/08 | ||
M3.10 |
Airflow Diagram (ABSL-2 Zone 6B Barrier) | 9/19/08 | ||
M3.11 |
Airflow Diagram ((A)BSL-3E Zone 7) | 10/31/08 | ||
M3.12 |
Airflow Diagram ((A)BSL-SE Zone 8) | 9/19/08 | ||
M3.13 |
Airflow Diagram ((A)BSL-SE Zone 8C) | 9/19/08 | ||
M3.14 |
Airflow Diagram ((A)BSL-SE Zone 15) | 9/19/08 | ||
M3.15 |
Airflow Diagram ((A)BSL-SE Zone 16) | 9/19/08 | ||
M3.16 |
Airflow Diagram ((A)BSL-SE Zone 17) | 9/19/08 | ||
M3.17 |
Airflow Diagram ((A)BSL-SE Zone 18) | 9/19/08 | ||
M3.18 |
Airflow Diagram ((A)BSL-SE Zone 19) | 9/19/08 | ||
M3.19 |
Airflow Diagram (BSL-3E Zone 11) | 9/19/08 | ||
M3.20 |
Airflow Diagram (BSL-3E Zone 12) | 9/19/08 | ||
M3.21 |
Airflow Diagram (BSL-3E Zone 13) | 9/19/08 | ||
M3.22 |
Airflow Diagram (BSL-3E Zone 14) | 9/19/08 | ||
M3.23 |
Airflow and Pressurization Diagram (BSL3-E Aerobiology) | 10/31/08 | ||
M3.24 |
Airflow Diagram ((A)BSL-3E Zone-16C, 18C & 20C) | 10/31/08 | ||
M3.25 |
Clinic and Administration Offices Airflow Diagram | 9/19/08 | ||
M3.26 |
Airflow Diagram (Non-Containment Corridor Zone 10-1) | 10/31/08 | ||
M3.27 |
Airflow Diagram (Non-Containment Corridor Zone 10-2) | 9/19/08 | ||
M3.28 |
Airflow Diagram (Non-Containment Corridor Zone 23-1) | 9/19/08 | ||
M3.29 |
Airflow Diagram (Non-Containment Corridor Zone 23-2) | 9/19/08 | ||
M3.30 |
Airflow Diagram ((A)BSL-3E Zone 20) | 9/19/08 | ||
M3.31 |
Airflow & Pressurization Diagram BSL4Lab Suite AHU System Schematic Zones 25,26,27 | 10/31/08 | ||
M3.32 |
Airflow & Pressurization Diagram BSL4Lab Suite AHU System Schematic Zones 28,29,30 | 10/31/08 | ||
M4.01 |
Chilled Water Distribution Diagram-1 | 1/19/09 | ||
M4.02 |
Chilled Water Distribution Diagram-2 | 9/19/08 | ||
M4.03 |
Heating Hot Water Reheat Distribution Diagram-1 | 9/19/08 | ||
M4.04 |
Heating Hot Water Reheat Distribution Diagram-2 | 9/19/08 | ||
M4.05 |
Preheat Glycol/ Hot Water Distribution Diagram-1 | 9/19/08 | ||
M4.06 |
Preheat Glycol/ Hot Water Distribution Diagram-2 | 9/19/08 | ||
M4.07 |
Preheat/Heat Recovery Distribution Diagram | 9/19/08 | ||
M4.08 |
Steam/ Condensate Distribution Diagram-1 | 1/19/09 | ||
M4.09 |
Steam/ Condensate Distribution Diagram-2 | 9/19/08 | ||
M4.10 |
Clean Steam Distribution Diagram | 9/19/08 | ||
M4.1 I |
Process Water Distribution Diagram | 9/19/08 | ||
M4.12 |
BSL4 Mechanical Piping Schematic | 10/31/08 | ||
M4.13 |
BSL4 Mechanical Piping Schematic | 10/31/08 | ||
M5.01 |
Details | 9/19/08 | ||
M5.02 |
Details | 10/31/08 | ||
M5.03 |
Details | 9/19/08 | ||
M5.04 |
BSL4 Details (Hepas) | 10/31/08 | ||
M5.05 |
Details | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 24 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M5.06 |
BSL4 Details (BSL4 AHU) | 10/31/08 | ||
M5.07 |
Details | 10131/08 | ||
M5.08 |
Details | 10/31/08 | ||
M5.09 |
Details | 9/19/0 | ||
M5.10 |
Details | 1/12/09 | ||
M5.11 |
Details | 10/31/08 | ||
M5.12 |
Details | 9/19/0 | ||
M5.13 |
Details | 10/31/08 | ||
M5.14 |
Details | 12/1/0 | ||
M5.15 |
Details | 1/12/09 | ||
M5.16 |
BSL4 Mechanical Room Fire Damper Details | 10/31/08 | ||
M5.17 |
Details | 9/19/0 | ||
M5.18 |
Details | 10/31/08 | ||
M5.19 |
Details | 9/19/0 | ||
MS5.01 |
Mechanical Security Details | 9/19/0 | ||
M6.01 |
Sections | 1/19/0 | ||
M6.02 |
Sections | 9/19/08 | ||
M6.03 |
Sections | 9/19/08 | ||
M6.04 |
Sections | 9/19/08 | ||
M6.05 |
Sections | 9/19/08 | ||
M6.06 |
Sections | 9/19/08 | ||
M6.07 |
Sections | 9/19/08 | ||
M6.08 |
BSL4 Section A-A | 0/31/08 | ||
M6.09 |
BSL4 Section B-B | 1/12/09 | ||
M6.10 |
BSL4 Section C-C | 10/31/08 | ||
M6.11 |
Sections | 9/19/08 | ||
M6.12 |
Sections | 9/19/08 | ||
M6.13 |
Sections | 9/19/08 | ||
M6.14 |
Sections | 10/31/08 | ||
M6.15 |
Sections | 10/31/08 | ||
M6.16 |
Sections | 9/19/08 | ||
M6.17 |
Sections | 9/19/08 | ||
M6.18 |
Sections | 10/31/08 | ||
M6.30 |
Isometrics | 9/19/08 | ||
M6.31 |
Isometrics | 9/19/08 | ||
M6.32 |
Isometrics | 9/19/08 | ||
M6.33 |
Isometrics | 9/19/08 | ||
M6.34 |
Isometrics | 10/31/08 | ||
M6.35 |
3rd Floor-BSL4 | 10/31/08 | ||
M6.36 |
4th and 5th Floor BSL4 | 10/31/08 | ||
M7.01 |
Schedules | 9/19/08 | ||
M7.02 |
Schedules | 10/31/08 | ||
M7.03 |
Schedules | 1/12/09 | ||
M7.04 |
Schedules | 9/19/08 | ||
M7.05 |
Schedules | 10/31/08 | ||
M7.06 |
Schedules | 9/19/08 | ||
M7.07 |
Schedules | 9/19/08 | ||
M7.08 |
Schedules | 1/19/09 | ||
M7.09 |
Schedules | 9/19/08 | ||
M7.10 |
Schedules | 10/31/08 | ||
M7.11 |
Schedules | 1/19/09 | ||
M7.12 |
Schedules | 10/31/08 | ||
M7.13 |
Schedules | 10/31/08 | ||
M7.14 |
Schedules | 9/19/08 | ||
M7.15 |
Schedules | 10/31/08 | ||
M7.16 |
Schedules | 9/19/08 | ||
M7.17 |
Schedules | 9/19/08 | ||
M7.18 |
Schedules | 9/19/08 | ||
M7.19 |
Schedules | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 25 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
M7.20 |
Schedules | 9/19/08 | ||
M7.21 |
BSL4 Mechanical Schedules | 10/31/08 | ||
M7.22 |
BSL4 Mechanical Schedules | 10/31/08 | ||
M7.23 |
BSL4 Mechanical Schedules | 10/31/08 | ||
M7.24 |
Schedules | 1/12/09 | ||
M7.25 |
Schedules | 1/12/09 | ||
M7.26 |
Schedules | 9/19/08 | ||
M7.27 |
Schedules | 1/12/09 | ||
M7.28 |
Schedules | 1/12/09 | ||
M7.29 |
Schedules | 1/12/09 | ||
M7.30 |
Schedules | 1/12/09 | ||
M7.31 |
Mechanical Schedules | 10/31/08 | ||
M7.32 |
Mechanical Schedules | 9/19/08 | ||
M7.33 |
Schedules | 9/19/08 | ||
M7.34 |
Schedules | 9/19/08 | ||
PLUMBING | ||||
P0.011 |
Cover Sheet-Plumbing-Part 1 | 1/19/09 | ||
P0.021 |
Index of Drawings-Plumbing-Part 1 | 1/19/09 | ||
P0.11 |
General Information | 9/19/08 | ||
P1.11 |
Floor 1 Underslab Plan Part 1 | 10/31/08 | ||
P1.11-X |
Floor 1 Underslab Plan Part 1-Bid Option #03 | 10/31/08 | ||
P1.12 |
Floor l Underslab Plan Part 2 | 10/31/08 | ||
P1.13 |
Floor 1 Underslab Plan Part 3 | 9/19/08 | ||
P1.14 |
Floor 1 Underslab Plan Part 4 | 1/12/09 | ||
P1.15 |
Floor 1 Underslab Plan Part 5 | 1/12/09 | ||
P1.16 |
Floor 1 Underslab Plan Part 6 | 9/19/08 | ||
P1.17 |
Floor 1 Underslab Plan Part 7 | 1/12/09 | ||
P1.18 |
Floor 1 Underslab Plan Part 8 | 1/12/09 | ||
P1.19 |
Floor 1 Underslab Plan Part 9 | 1/12/09 | ||
P1.20 |
Floor Penetration Plan Part 1 | 9/19/08 | ||
P1.71 |
Roof Plan Parts 1 to 5 | 1/19/09 | ||
P1.76 |
Roof Plan Parts 6 to 9 | 1/12/09 | ||
P2.04F |
Basement Plan Part 4F | 1/19/09 | ||
P2.05B |
Basement Plan Part 5B | 9/19/08 | ||
P2.05D |
Basement Plan Part 5D | 9/19/08 | ||
P2.05E |
Basement Plan Part 5E | 9/19/08 | ||
P2.09AB |
Basement Plan Parts 9A & 9B | 1/19/09 | ||
P2.09D |
Basement Plan Parts 9D | 1/19/09 | ||
P2.11A |
Floor 1 Plan Part 1A | 1/12/09 | ||
P2.11A-X |
Floor 1 Plan Part 1A-Bid Option #03 | 1/12/09 | ||
P2.11B |
Floor 1 Plan Part 1B | 1/12/09 | ||
P2.11B-X |
Floor 1 Plan Part 1B-Bid Option #03 | 1/12/09 | ||
P2.12A |
Floor 1 Plan Part 2A | 1/12/09 | ||
P2.12B |
Floor 1 Plan Part 2B | 1/12/09 | ||
P2.12C |
Floor l Plan Part 2C | 1/12/09 | ||
P2.13A |
Floor 1 Plan Part 3A | 1/12/09 | ||
P2.13B |
Floor 1 Plan Part 3B | 1/12/09 | ||
P2.13C |
Floor 1 Plan Part 3C | 1/12/09 | ||
P2.14A |
Floor l Plan Part 4A | 1/19/09 | ||
P2.14B |
Floor 1 Plan Part 4B | 1/19/09 | ||
P2.14C |
Floor 1 Plan Part 4C | 1/19/09 | ||
P2.14D |
Floor 1 Plan Part 4D | 1/19/09 | ||
P2.14E |
Floor 1 Plan Part 4E | 1/19/09 | ||
P2.14F |
Floor 1 Plan Part 4F | 1/19/09 | ||
P2.15A |
Floor l Plan Part 5A | 1/12/09 | ||
P2.15B |
Floor 1 Plan Part 5B | 1/12/09 | ||
P2.15C |
Floor 1 Plan Part 5C | 1/12/09 | ||
P2.15D |
Floor 1 Plan Part 5D | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 26 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
P2.16AB |
Floor 1 Plan Parts 6A & 6B | 9/19/08 | ||
P2.16C |
Floor 1 Plan Parts 6C | 9/19/08 | ||
P2.16D |
Floor 1 Plan Parts 6D | 1/12/09 | ||
P2.17AB |
Floor 1 Plan Parts 7A & 7B | 1/12/09 | ||
P2.17C |
Floor 1 Plan Parts 7C | 10/31/08 | ||
P2.17D |
Floor 1 Plan Parts 7D | 10/31/08 | ||
P2.18AB |
Floor 1 Plan Parts 8A & 8B | 1/12/09 | ||
P2.18C |
Floor 1 Plan Parts 8C | 1/12/09 | ||
P2.18D |
Floor 1 Plan Parts 8D | 1/12/09 | ||
P2.19AB |
Floor 1 Plan Parts 9A & 9B | 1/19/09 | ||
P2.19C |
Floor 1 Plan Parts 9C | 1/12/09 | ||
P2.19D |
Floor 1 Plan Parts 9D | 1/12/09 | ||
P2.21A |
Floor 2 Plan Part 1A | 10/31/08 | ||
P2.21A-X |
Floor 2 Plan Part 1A- Bid Option #03 | 10/31/08 | ||
P2.21B |
Floor 2 Plan Part 1B | 9/19/08 | ||
P2.21B-X |
Floor 2 Plan Part 1B- Bid Option #03 | 9/19/08 | ||
P2.22A |
Floor 2 Plan Part 2A | 1/12/09 | ||
P2.22B |
Floor 2 Plan Part 2B | 1/12/09 | ||
P2.22C |
Floor 2 Plan Part 2C | 1/12/09 | ||
P2.23A |
Floor 2 Plan Part 3A | 1/12/09 | ||
P2.23B |
Floor 2 Plan Part 3B | 1/12/09 | ||
P2.23C |
Floor 2 Plan Part 3C | 1/12/09 | ||
P2.24A |
Floor 2 Plan Part 4A | 1/12/09 | ||
P2.24B |
Floor 2 Plan Part 4B | 1/12/09 | ||
P2.24C |
Floor 2 Plan Part 4C | 1/12/09 | ||
P2.24D |
Floor 2 Plan Part 4D | 1/12/09 | ||
P2.24E |
Floor 2 Plan Part 4E | 1/12/09 | ||
P2.24F |
Floor 2 Plan Part 4F | 1/12/09 | ||
P2.25A |
Floor 2 Plan Part 5A | 1/19/09 | ||
P2.25B |
Floor 2 Plan Part 5B | 1/12/09 | ||
P2.25C |
Floor 2 Plan Part 5C | 1/12/09 | ||
P2.25D |
Floor 2 Plan Part 5D | 1/12/09 | ||
P2.26AB |
Floor 2 Plan Part 6A & 6B | 9/19/08 | ||
P2.26C |
Floor 2 Plan Part 6C | 10/31/08 | ||
P2.26D |
Floor 2 Plan Part 6D | 10/31/08 | ||
P2.27AB |
Floor 2 Plan Part 7A & 7B | 9/19/08 | ||
P2.27C |
Floor 2 Plan Part 7C | 10/31/08 | ||
P2.27D |
Floor 2 Plan Part 7D | 10/31/08 | ||
P2.28AB |
Floor 2 Plan Part 8A & 8B | 9/19/08 | ||
P2.28C |
Floor 2 Plan Part 8C | 10/31/08 | ||
P2.28D |
Floor 2 Plan Part 8D | 10/31/08 | ||
P2.29AB |
Floor 2 Plan Part 9A & 9B | 9/19/08 | ||
P2.29C |
Floor 2 Plan Part 9C | 1/12/09 | ||
P2.29D |
Floor 2 Plan Part 9D | 1/19/09 | ||
P0.012 |
Cover Sheet- Plumbing- Part 2 | 1/19/09 | ||
P0.022 |
Index of Drawings- Plumbing- Part 2 | 10/31/08 | ||
P0.12 |
General Information | 9/19/08 | ||
P2.31A |
Floor 3 Plan Part 1A | 10/31/08 | ||
P2.31B |
Floor 3 Plan Part 1B | 10/31/08 | ||
P2.32A |
Floor 3 Plan Part 2A | 1/12/09 | ||
P2.32B |
Floor 3 Plan Part 2B | 1/12/09 | ||
P2.32C |
Floor 3 Plan Part 2C | 1/12/09 | ||
P2.33A |
Floor 3 Plan Part 3A | 1/19/09 | ||
P2.33B |
Floor 3 Plan Part 3B | 1/12/09 | ||
P2.33C |
Floor 3 Plan Part 3C | 1/12/09 | ||
P2.34A |
Floor 3 Plan Part 4A | 1/19/09 | ||
P2.34B |
Floor 3 Plan Part 4B | 1/19/09 | ||
P2.34C |
Floor 3 Plan Part 4C | 1/12/09 | ||
P2.34D |
Floor 3 Plan Part 4D | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 27 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
P2.34E |
Floor 3 Plan Part 4E | 1/12/09 | ||
P2.34F |
Floor 3 Plan Part 4F | 1/12/09 | ||
P2.35A |
Floor 3 Plan Part 5A | 1/12/09 | ||
P2.35B |
Floor 3 Plan Part 5B | 10/31/08 | ||
P2.35C |
Floor 3 Plan Part 5C | 1/12/09 | ||
P2.35D |
Floor 3 Plan Part 5D | 10/31/08 | ||
P2.36AB |
Floor 3 Plan Part 6A & 6B | 9/19/08 | ||
P2.36C |
Floor 3 Plan Part 6C | 9/19/08 | ||
P2.36D |
Floor 3 Plan Part 6D | 1/12/09 | ||
P2.37AB |
Floor 3 Plan Part 7A & 7B | 9/19/08 | ||
P2.37C |
Floor 3 Plan Part 7C | 10/31/08 | ||
P2.37D |
Floor 3 Plan Part 7D | 10/31/08 | ||
P2.38AB |
Floor 3 Plan Part 8A & 8B | 9/19/08 | ||
P2.38C |
Floor 3 Plan Part 8C | 10/31/08 | ||
P2.38D |
Floor 3 Plan Part 8D | 10/31/08 | ||
P2.39AB |
Floor 3 Plan Part 9A & 9B | 9/19/08 | ||
P2.39C |
Floor 3 Plan Part 9C | 10/31/08 | ||
P2.39D |
Floor 3 Plan Part 9D | 1/12/09 | ||
P2.41A |
Floor 4 Plan Part 1A | 1/12/09 | ||
P2.41B |
Floor 4 Plan Part lB | 1/12/09 | ||
P2.42A |
Floor 4 Plan Part 2A | 1/12/09 | ||
P2.42B |
Floor 4 Plan Part 2B | 1/12/09 | ||
P2.42C |
Floor 4 Plan Part 2C | 1/12/09 | ||
P2.43A |
Floor 4 Plan Part 3A | 1/19/09 | ||
P2.43B |
Floor 4 Plan Part 3B | 1/12/09 | ||
P2.43C |
Floor 4 Plan Part 3C | 1/12/09 | ||
P2.44A |
Floor 4 Plan Part 4A | 1/12/09 | ||
P2.44B |
Floor 4 Plan Part 4B | 1/12/09 | ||
P2.44C |
Floor 4 Plan Part 4C | 1/12/09 | ||
P2.44D |
Floor 4 Plan Part 4D | 1/19/09 | ||
P2.44E |
Floor 4 Plan Part 4E | 1/12/09 | ||
P2.44F |
Floor 4 Plan Part 4F | 1/12/09 | ||
P2.45A |
Floor 4 Plan Part 5A | 9/19/08 | ||
P2.45B |
Floor 4 Plan Part 5B | 1/12/09 | ||
P2.45C |
Floor 4 Plan Part 5C | 1/12/09 | ||
P2.45D |
Floor 4 Plan Part 5D | 1/12/09 | ||
P2.46AB |
Floor 4 Plan Part 6A & 6B | 9/19/08 | ||
P2.46C |
Floor 4 Plan Part 6C | 9/19/08 | ||
P2.46D |
Floor 4 Plan Part 6D | 10/31/08 | ||
P2.47AB |
Floor 4 Plan Part 7A & 7B | 9/19/08 | ||
P2.47C |
Floor 4 Plan Part 7C | 10/31/08 | ||
P2.47D |
Floor 4 Plan Part 7D | 10/31/08 | ||
P2.48AB |
Floor 4 Plan Part 8A & 8B | 9/19/08 | ||
P2.48C |
Floor 4 Plan Part 8C | 10/31/08 | ||
P2.48D |
Floor 4 Plan Part 8d | 10/31/08 | ||
P2.49AB |
Floor 4 Plan Part 9A & 9B | 9/19/08 | ||
P2.49C |
Floor 4 Plan Part 9C | 1/12/09 | ||
P2.49D |
Floor 4 Plan Part 9D | 1/12/09 | ||
P2.51A |
Floor 5 Plan Part lA | 10/31/08 | ||
P2.51B |
Floor 5 Plan Part lB | 10/31/08 | ||
P2.52A |
Floor 5 Plan Part 2A | 10/31/08 | ||
P2.52B |
Floor 5 Plan Part 2B | 10/31/08 | ||
P2.52C |
Floor 5 Plan Part 2C | 10/31/08 | ||
P2.53A |
Floor 5 Plan Part 3A | 10/31/08 | ||
P2.53B |
Floor 5 Plan Part 3B | 10/31/08 | ||
P2.53C |
Floor 5 Plan Part 3C | 10/31/08 | ||
P2.54A |
Floor 5 Plan Part 4A | 10/31/08 | ||
P2.54B |
Floor 5 Plan Part 4B | 10/31/08 | ||
P2.54C |
Floor 5 Plan Part 4C | 1/12/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 28 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
P2.54C_ALT |
Floor 5 Plan Part 4C | 10/31/08 | ||
P2.54D |
Floor 5 Plan Part 4D | 1/12/09 | ||
P2.54E |
Floor 5 Plan Part 4E | 10/31/08 | ||
P2.54F |
Floor 5 Plan Part 4F | 1/19/09 | ||
P2.55A |
Floor 5 Plan Part 5A | 1/12/09 | ||
P2.55B |
Floor 5 Plan Part 5B | 1/19/09 | ||
P2.55C |
Floor 5 Plan Part 5C | 1/12/09 | ||
P2.55D |
Floor 5 Plan Part 5D | 1/19/09 | ||
P2.56AB |
Floor 5 Plan Part 6A & 6B | 9/19/08 | ||
P2.56C |
Floor 5 Plan Part 6C | 9/19/08 | ||
P2.56D |
Floor 5 Plan Part 6D | 10/31/08 | ||
P2.57AB |
Floor 5 Plan Part 7A & 7B | 1/12/09* | ||
P2.57C |
Floor 5 Plan Part 7C | 1/19/09* | ||
P2.57D |
Floor 5 Plan Part 7D | 10/31/08 | ||
P2.58AB |
Floor 5 Plan Part 8A & 8B | 9/19/08 | ||
P2.58C |
Floor 5 Plan Part 8C | 10/31/08 | ||
P2.58D |
Floor 5 Plan Part 8D | 1/19/09 | ||
P2.59AB |
Floor 5 Plan Part 9A & 9B | 9/19/08 | ||
P2.59C |
Floor 5 Plan Part 9C | 10/31/08 | ||
P2.59D |
Floor 5 Plan Part 9D | 1/12/09 | ||
P0.013 |
Cover Sheet- Plumbing- Part 3 | 1/19/09 | ||
P0.023 |
Index of Drawings- Plumbing- Part 3 | 1/12/09 | ||
P0.13 |
General Information | 9/19/08 | ||
P2.61A |
Floor 6 Plan Part 1A | 1/19/09 | ||
P2.61B |
Floor 6 Plan Part 1B | 10/31/08 | ||
P2.62A |
Floor 6 Plan Part 2A | 1/12/09 | ||
P2.62B |
Floor 6 Plan Part 2B | 10/31/08 | ||
P2.62C |
Floor 6 Plan Part 2C | 1/19/09 | ||
P2.63A |
Floor 6 Plan Part 3A | 1/12/09 | ||
P2.63B |
Floor 6 Plan Part 3B | 10/31/08 | ||
P2.63C |
Floor 6 Plan Part 3C | 10/31/08 | ||
P2.64A |
Floor 6 Plan Part 4A | 10/31/08 | ||
P2.64B |
Floor 6 Plan Part 4B | 10/31/08 | ||
P2.64C |
Floor 6 Plan Part 4C | 1/12/09 | ||
P2.64D |
Floor 6 Plan Part 4D | 1/19/09 | ||
P2.64E |
Floor 6 Plan Part 4E | 1/19/09 | ||
P2.64F |
Floor 6 Plan Part 4F | 10/31/08 | ||
P2.65A |
Floor 6 Plan Part 5A | 1/12/09 | ||
P2.65B |
Floor 6 Plan Part 5B | 1/12/09 | ||
P2.65C |
Floor 6 Plan Part 5C | 9/19/08 | ||
P2.65D |
Floor 6 Plan Part 5D | 1/12/09 | ||
P2.66AB |
Floor 6 Plan Part 6A & 6B | 9/19/08 | ||
P2.66C |
Floor 6 Plan Part 6C | 9/19/08 | ||
P2.66D |
Floor 6 Plan Part 6D | 1/19/09 | ||
P2.67AB |
Floor 6 Plan Part 7A & 7B | 9/19/08 | ||
P2.67C |
Floor 6 Plan Part 7C | 10/31/08 | ||
P2.67D |
Floor 6 Plan Part 7D | 1/12/09 | ||
P2.68AB |
Floor 6 Plan Part 8A & 8B | 9/19/08 | ||
P2.68C |
Floor 6 Plan Part 8C | 1/12/09 | ||
P2.68D |
Floor 6 Plan Part 8D | 10/31/08 | ||
P2.69AB |
Floor 6 Plan Part 9A & 9B | 9/19/08 | ||
P2.69C |
Floor 6 Plan Part 9C | 10/31/08 | ||
P2.69D |
Floor 6 Plan Part 9D | 01/12/09 | ||
P2.6P4F |
Floor 6P Plan Part 4F | 9/19/08 | ||
P2.6P6C |
Floor 6P Plan Part 6C | 9/19/08 | ||
P2.6P6D |
Floor 6P Plan Part 6D | 9/19/08 | ||
P2.6P7C |
Floor 6P Plan Part 7C | 1/12/09 | ||
P2.6P7D |
Floor 6P Plan Part 7D | 9/19/08 | ||
P2.6P8C |
Floor 6P Plan Part 8C | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 29 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
P2.6P8D |
Floor 6P Plan Part 8D | 9/19/08 | ||
P2.6P9C |
Floor 6P Plan Part 9C | 9/19/08 | ||
P2.6P9D |
Floor 6P Plan Part 9D | 1/19/09 | ||
P3.01 |
Schedules | 1/19/09 | ||
P3.02 |
Schedules | 1/19/09 | ||
P3.03 |
Schedules | 1/12/09 | ||
P4.01 |
Risers Storm Water | 9/19/08 | ||
P4.02 |
Risers Storm Water | 9/19/08 | ||
P4.03 |
Risers Sanitary Waste | 1/19/09 | ||
P4.04 |
Risers Sanitary Waste | 1/12/09 | ||
P4.05 |
Risers Sanitary Waste | 9/19/08 | ||
P4.06 |
Risers Laboratory Waste | 9/19/08 | ||
P4.07 |
Risers Bio Waste | 1/12/09 | ||
P4.08 |
Risers Bio Waste | 10/31/08 | ||
P4.09 |
Risers Bio Waste | 1/12/09 | ||
P4.10 |
Risers Sanitary Waste BSL-2 Wing | 10/31/08 | ||
P4.11 |
Risers Sanitary Waste BSL-2 Wing | 1/19/09 | ||
P4.12 |
Risers Laboratory Waste BSL-2 Wing | 9/19/08 | ||
P4.13 |
Risers Laboratory Waste BSL-2 Wing | 9/19/08 | ||
P4.14 |
Risers Laboratory WaSite BSL-2 Wing | 9/19/08 | ||
P4.15 |
Risers Bio Waste | 10/31/08 | ||
P4.16 |
Risers Bio Waste | 10/31/08 | ||
P4.17 |
Risers Bio Waste | 10/31/08 | ||
P4.18 |
Risers | 1/12/09 | ||
P4.19 |
Risers | 1/12/09 | ||
P4.20 |
Risers Domestic Water | 1/12/09 | ||
P4.21 |
Risers Domestic Water- High Containment Wing | 1/19/09 | ||
P4.22 |
Risers Domestic Water- BSL-2 Wing | 1/19/09 | ||
P4.23 |
Risers Laboratory Water- BSL-2 Wing | 10/31/08 | ||
P4.24 |
Risers BSL-3/BSL-4 Laboratory Water | 1/12/09 | ||
P4.25 |
Risers ABSL-2 Lab Water | 1/19/09 | ||
P4.26 |
Risers Tempered Water- High Containment Wing | 10/31/08 | ||
P4.27 |
Risers Tempered Water- BSL-2 Wing | 10/31/08 | ||
P4.28 |
Risers Softened Cold Water | 1/19/09 | ||
P4.29 |
Risers RO Water- BSL-2 Wing | 10/31/08 | ||
P4.30 |
Risers RO-4 Water- High Containment Wing | 10/31/08 | ||
P4.31 |
Risers RO-3 Water- High Containment Wing | 10/31/08 | ||
P4.32 |
Risers Laboratory Vacuum | 1/12/09 | ||
P4.33 |
Risers Compressed Air | 1/12/09 | ||
P4.34 |
Risers Liquid Nitrogen | 1/12/09 | ||
P4.35 |
Risers Carbon Dioxide | 1/12/09 | ||
P4.36 |
Clinic Domestic Water Risers | 10/31/08 | ||
P4.37 |
Risers | 1/12/09 | ||
P4.38 |
Clinic Special Services Risers | 9/19/08 | ||
P4.39 |
Risers Detergent Systems | 9/19/08 | ||
P4.40 |
Risers Tampered Water BSL-2 Wing | 10/31/08 | ||
P4.41 |
Risers Laboratory Water-BSL-4 | 1/12/09 | ||
P4.42 |
Risers Laboratory Waste-BSL-5 | 1/12/09 | ||
P4.43 |
Risers Sanitary Waste | 1/12/09 | ||
P4.44 |
Risers Sanitary Waste | 1/12/09 | ||
P4.45 |
Risers Sanitary Waste | 1/12/09 | ||
P4.46 |
Risers Sanitary Waste | 1/12/09 | ||
P4.47 |
Risers Laboratory Vacuum | 1/12/09 | ||
P4.48 |
Risers Carbon Dioxide | 1/12/09 | ||
P4.50 |
Risers Compressed Air | 1/12/09 | ||
P4.51 |
Risers Sanitary Waste | 1/19/09 | ||
P5.01 |
Water Heater Details | 9/19/08 | ||
P5.02 |
Water Heater Details | 9/19/08 | ||
P5.03 |
Water Service Details | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 30 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
P5.04 |
BSL-2 Wing Plumbing Closet South End | 1/19/09 | ||
P5.05 |
BSL-2 Wing Plumbing Closet North End | 1/12/09 | ||
P5.06 |
Containment Area Plumbing Details | 1/12/09 | ||
P5.07 |
Lab Gas Equipment Details | 1/19/09 | ||
P5.08 |
Lab Gas Equipment Details | 10/31/08 | ||
P5.09 |
Plumbing Details | 1/19/09 | ||
P5.10 |
Plumbing Details | 1/19/09 | ||
P5.11 |
Details BSL-4 | 1/12/09 | ||
P5.12 |
Details BSL-4 | 1/19/09 | ||
P5.13 |
BSL-3 Details | 10/31/08 | ||
P5.14 |
Plumbing Details | 9/19/08 | ||
P5.15 |
Plumbing Details | 1/19/09 | ||
P5.16 |
Plumbing Details | 12/1/08 | ||
P5.17 |
RO Water Equipment Details BSL-3 & BSL-4 Areas | 1/19/09 | ||
P5.18 |
RO Water Equipment Details BSL-2 Area | 1/19/09 | ||
P5.19 |
Plumbing Details | 1/12/09 | ||
P5.20 |
Animal Watering Details | 1/19/09 | ||
P5.21 |
Animal Watering Details | 10/31/08 | ||
P5.22 |
Plumbing Details | 1/19/09 | ||
P5.23 |
Plumbing Details | 1/19/09 | ||
P5.24 |
Plumbing Details | 9/19/08 | ||
P5.25 |
Containment Area Plumbing Details | 10/31/08 | ||
P5.26 |
Holding Room Plumbing Details | 10/31/08 | ||
P5.27 |
Detergent System Details | 1/12/09 | ||
P5.28 |
Solar Thermal Heating System- Bid Option #02 | 9/19/09 | ||
P5.29 |
3rd Floor High Containment Plumbing Closet | 1/12/09 | ||
P5.30 |
1st Floor High Containment Plumbing Closet | 9/19/08 | ||
P5.31 |
3rd Floor Plumbing Closet | 1/12/09 | ||
P6.01 |
Chemical Shower System Schematic | 1/12/09 | ||
P6.02 |
Breathing Air System Schematic | 10/31/08 | ||
P6.03 |
Tissue Digester Schematic | 9/19/08 | ||
FIRE PROTECTION | ||||
F0.011 |
Cover Sheet- Fire Protection | 1/19/09 | ||
F0.021 |
Index of Drawings- Fire Protection | 1/19/09 | ||
F0.11 |
General Information | 1/12/09 | ||
F0.401 |
Basement Plan Parts 1 to 5 | 1/19/09 | ||
F0.411 |
Floor 1 Plan Parts 1 to 5 | 12/1/08 | ||
F0.416 |
Floor 1 Plan Parts 6 to 9 | 12/1/08 | ||
F0.421 |
Floor 2 Plan Parts 1 to 5 | 1/19/09 | ||
F0.426 |
Floor 2 Plan Parts 6 to 9 | 10/31/08 | ||
F0.431 |
Floor 3 Plan Parts 1 to 5 | 10/31/08 | ||
F0.436 |
Floor 3 Plan Parts 6 to 9 | 10/31/08 | ||
F0.441 |
Floor 4 Plan Parts 1 to 5 | 1/19/09 | ||
F0.446 |
Floor 4 Plan Parts 6 to 9 | 10/31/08 | ||
F0.451 |
Floor 5 Plan Parts 1 to 5 | 9/19/08 | ||
F0.456 |
Floor 5 Plan Parts 6 to 9 | 10/31/08 | ||
F0.461 |
Floor 6 Plan Parts 1 to 5 | 1/12/09 | ||
F0.466 |
Floor 6 Plan Parts 6 to 9 | 1/12/09 | ||
F0.46P1 |
Floor 6P Plan Parts 1 to 5 | 1/19/09 | ||
F0.46P6 |
Floor 6P Plan Parts 6 to 9 | 9/19/08 | ||
F1.16 |
Floors 1 & 2 BSL-2 Plan Part 6 Enlarged Plans | 10/31/08 | ||
Fl .22 |
Floor 2 BSL4 FP Plan Part 2 | 10/31/08 | ||
Fl .23 |
Floor 2 BSL4 FP Plan Part 3 | 10/31/08 | ||
F1.32 |
Floor 3 BSL4 FP Plan Part 2 | 10/31/08 | ||
F1.33 |
Floor 3 BSL4 FP Plan Part 3 | 10/31/08 | ||
P3.01 |
Schedules | 10/31/08 | ||
F4.01 |
Risers | 10/31/08 | ||
F5.01 |
Details | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 31 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
F5.02 |
Details | 9/19/08 | ||
F5.03 |
Details | 9/19/08 | ||
F5.04 |
BSL-4 Details | 10/31/08 | ||
F5.05 |
Details | 9/19/08 | ||
F5.06 |
Details | 12/01/08* | ||
ELECTRICAL | ||||
E0.011 |
Cover Sheet- Electrical- Part 1 | 1/12/09* | ||
E0.021 |
Index of Drawings- Electrical- Part 1 | 1/12/09* | ||
E0.11 |
Symbol List- Part 1 | 9/19/08 | ||
E0.12 |
Symbol List Part 2 | 10/31/08 | ||
ELS0.01 |
Site Lighting Plan Area 1 Phase 1 | 9/19/08 | ||
ELS0.02 |
Site Lighting Plan Area 2 Phase 1 | 9/19/08 | ||
ELS0.03 |
Site Lighting Plan Area 3 Phase 1 | 9/19/08 | ||
ELS0.04 |
Site Lighting Plan Area 4 Phase 1 | 9/19/08 | ||
ELS0.05 |
Site Lighting Plan Area 5 Phase 1 | 9/19/08 | ||
ELS0.06 |
Site Lighting Plan Area 6 Phase 1 | 9/19/08 | ||
ELS0.07 |
Site Lighting Plan Area 7 Phase 1 | 9/19/08 | ||
ELS0.08 |
Site Lighting Plan Area 8 Phase 1 | 9/19/08 | ||
ELS0.09 |
Site Lighting Plan Area 9 Phase 1 | 9/19/08 | ||
ELSO.17 |
Site Lighting Schedule and Details | 9/19/08 | ||
EPS0.01 |
Partial Site Plan-Power | 1/19/09 | ||
EL1.04 |
Basement Floor Plan Part 4- Lighting | 1/19/09 | ||
EL1.05 |
Basement Floor Plan Part 5- Lighting | 9/19/08 | ||
EL1.05E |
Basement Floor Plan Part 5E Tunnel- Lighting | 9/19/08* | ||
EL1.09 |
Basement Floor Plan Part 9- Lighting | 1/19/09 | ||
EL1.11 |
Floor 1 Plan Part 1- Lighting | 10/31/08 | ||
EL1.11-X |
Floor 1 Plan Part 1- Lighting- Bid Option #03 | 10/31/08 | ||
EL1.12 |
Floor 1 Plan Part 2- Lighting | 9/19/08 | ||
EL1.13 |
Floor 1 Plan Part 3- Lighting | 9/19/08 | ||
EL1.14 |
Floor 1 Plan Part 4- Lighting | 1/19/09 | ||
EL1.15 |
Floor 1 Plan Part 5- Lighting | 10/31/08 | ||
EL1.16 |
Floor 1 Plan Part 6- Lighting | 10/31/08 | ||
EL1.17 |
Floor 1 Plan Part 7- Lighting | 10/31/08 | ||
EL1.18 |
Floor 1 Plan Part 8- Lighting | 10/31/08 | ||
EL1.19 |
Floor 1 Plan Part 9- Lighting | 1/19/09 | ||
EL1.21 |
Floor 2 Plan Part 1- Lighting | 9/19/08 | ||
EL1.21-X |
Floor 2 Plan Part 1- Lighting Bid Option #03 | 10/31/08 | ||
EL1.22 |
Floor 2 Plan Part 2- Lighting | 10/31/08 | ||
EL1.23 |
Floor 2 Plan Part 3- Lighting | 10/31/08 | ||
EL1.24 |
Floor 2 Plan Part 4- Lighting | 9/19/08 | ||
EL1.25 |
Floor 2 Plan Part 5- Lighting | 9/19/08 | ||
EL1.26 |
Floor 2 Plan Part 6- Lighting | 9/19/08 | ||
EL1.27 |
Floor 2 Plan Part 7- Lighting | 9/19/08 | ||
EL1.28 |
Floor 2 Plan Part 8- Lighting | 9/19/08 | ||
EL1.29 |
Floor 2 Plan Part 9- Lighting | 10/31/08 | ||
EL1.2TZ2 |
Floor 2 Transition Zone Plan Part 2- Lighting | 9/19/08 | ||
EL1.2TZ3 |
Floor 2 Transition Zone Plan Part 3- Lighting | 9/19/08 | ||
EL1.2TZ4 |
Floor 2 Transition Zone Plan Part 4- Lighting | 9/19/08 | ||
EL1.31 |
Floor 3 Plan Part 1- Lighting | 10/31/08 | ||
EL1.32 |
Floor 3 Plan Part 2- Lighting | 9/19/08 | ||
EL1.33 |
Floor 3 Plan Part 3- Lighting | 9/19/08 | ||
EL1.34 |
Floor 3 Plan Part 4- Lighting | 9/19/08 | ||
EL1.35 |
Floor 3 Plan Part 5- Lighting | 9/19/08 | ||
EL1.36 |
Floor 3 Plan Part 6- Lighting | 9/19/08 | ||
EL1.37 |
Floor 3 Plan Part 7- Lighting | 9/19/08 | ||
EL1.38 |
Floor 3 Plan Part 8- Lighting | 9/19/08 | ||
EL1.39 |
Floor 3 Plan Part 9- Lighting | 9/19/08 | ||
EL1.41 |
Floor 4 Plan Part 1- Lighting | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 32 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
EL1.42 |
Floor 4 Plan Part 2- Lighting | 9/19/08 | ||
EL1.43 |
Floor 4 Plan Part 3- Lighting | 9/19/08 | ||
EL1.44 |
Floor 4 Plan Part 4- Lighting | 9/19/08 | ||
EL1.45 |
Floor 4 Plan Part 5- Lighting | 9/19/08 | ||
EL1.46 |
Floor 4 Plan Part 6- Lighting | 10/31/08 | ||
EL1.47 |
Floor 4 Plan Part 7- Lighting | 9/19/08 | ||
EL1.48 |
Floor 4 Plan Part 8- Lighting | 9/19/08 | ||
EL1.49 |
Floor 4 Plan Part 9- Lighting | 9/19/08 | ||
EL1.4TZ2 |
Floor 4 Transition Zone Plan Part 2- Intrusion Alarm | 9/19/08 | ||
EL1.4TZ3 |
Floor 4 Transition Zone Plan Part 3- Intrusion Alarm | 9/19/08 | ||
EL1.4TZ4 |
Floor 4 Transition Zone Plan Part 4- Intrusion Alarm | 9/19/08 | ||
EL1.51 |
Floor 5 Plan Part 1- Lighting | 9/19/08* | ||
EL1.52 |
Floor 5 Plan Part 2- Lighting | 9/19/08* | ||
EL1.53 |
Floor 5 Plan Part 3- Lighting | 9/19/08* | ||
EL1.54 |
Floor 5 Plan Part 4- Lighting | 9/19/08* | ||
EL1.55 |
Floor 5 Plan Part 5- Lighting | 9/19/08* | ||
EL1.56 |
Floor 5 Plan Part 6- Lighting | 9/19/08 | ||
EL1.57 |
Floor 5 Plan Part 7- Lighting | 9/19/08 | ||
EL1.58 |
Floor 5 Plan Part 8- Lighting | 9/19/08 | ||
EL1.59 |
Floor 5 Plan Part 9- Lighting | 9/19/08 | ||
EL1.61 |
Floor 6 Plan Part 1- Lighting | 9/19/08* | ||
EL1.62 |
Floor 6 Plan Part 2- Lighting | 9/19/08* | ||
EL1.63 |
Floor 6 Plan Part 3- Lighting | 9/19/08* | ||
EL1.64 |
Floor 6 Plan Part 4- Lighting | 9/19/08* | ||
EL1.65 |
Floor 6 Plan Part 5- Lighting | 9/19/08* | ||
EL1.66 |
Floor 6 Plan Part 6- Lighting | 9/19/08 | ||
EL1.67 |
Floor 6 Plan Part 7- Lighting | 9/19/08* | ||
EL1.68 |
Floor 6 Plan Part 8- Lighting | 9/19/08 | ||
EL1.69 |
Floor 6 Plan Part 9- Lighting | 9/19/08* | ||
EL1.6P4 |
Floor 6P Plan Part 4- Lighting | 9/19/08 | ||
EL1.6P6 |
Floor 6P Plan Part 6- Lighting | 9/19/08 | ||
EL1.6P7 |
Floor 6P Plan Part 7- Lighting | 10/31/08 | ||
EL1.6P8 |
Floor 6P Plan Part 8- Lighting | 10/31/08 | ||
EL1.6P9 |
Floor 6P Plan Part 9- Lighting | 9/19/08 | ||
EP1.04 |
Basement Floor Plan Part 4- Power | 1/19/09 | ||
EP1.05 |
Basement Floor Plan Part 5- Power | 9/19/08 | ||
EP1.05E |
Basement Floor Plan Part 5E Tunnel- Power | 9/19/08 | ||
EP1.09 |
Basement Floor Plan Part 9- Power | 1/19/09 | ||
EP1.11 |
Floor 1 Plan Part 1- Power | 10/31/08 | ||
EP1.11-X |
Floor 1 Plan Part 1- Power- Bid Option #03 | 10/31/08 | ||
EP1.12 |
Floor 1 Plan Part 2- Power | 9/19/08* | ||
EP1.13 |
Floor 1 Plan Part 3- Power | 9/19/08 | ||
EP1.14 |
Floor 1 Plan Part 4- Power | 1/19/09 | ||
EP1.14-X |
Floor 1 Plan Part 4- Power- Bid Option #29 | 12/1/08 | ||
EP1.15 |
Floor 1 Plan Part 5- Power | 1/12/09 | ||
EP1.16 |
Floor 1 Plan Part 6- Power | 1/12/09 | ||
EP1.17 |
Floor 1 Plan Part 7- Power | 9/19/08 | ||
EP1.18 |
Floor 1 Plan Part 8- Power | 12/1/08 | ||
EP1.19 |
Floor 1 Plan Part 9- Power | 1/19/09 | ||
EP1.19-X |
Floor 1 Plan Part 9- Power- Bid Option #29 | 12/1/08 | ||
EP1.21 |
Floor 2 Plan Part 1- Power | 9/19/08 | ||
EP1.21-X |
Floor 2 Plan Part 1- Power- Bid Option #03 | 10/31/08 | ||
EP1.22 |
Floor 2 Plan Part 2- Power | 9/19/08 | ||
EP1.23 |
Floor 2 Plan Part 3- Power | 9/19/08 | ||
EP1.24 |
Floor 2 Plan Part 4- Power | 10/31/08 | ||
EP1.25 |
Floor 2 Plan Part 5- Power | 10/31/08 | ||
EP1.26 |
Floor 2 Plan Part 6- Power | 10/31/08 | ||
EP1.27 |
Floor 2 Plan Part 7- Power | 10/31/08 | ||
EEP1.28 |
Floor 2 Plan Part 8- Power | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 33 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
EP1.29 |
Floor 2 Plan Part 9- Power | 10/31/08 | ||
EP1.2TZ2 |
Floor 2 Transition Zone Plan Part 2- Power | 9/19/08 | ||
EP1.2TZ3 |
Floor 2 Transition Zone Plan Part 3- Power | 9/19/08 | ||
EP1.2TZ4 |
Floor 2 Transition Zone Plan Part 4- Power | 10/31/08 | ||
EP2.22B |
BSL4 Floor 2 Plan Part 2B- Power | 10/31/08 | ||
EP2.22C |
BSL4 Floor 2 Plan Part 2C- Power | 9/19/08 | ||
EP2.23B |
BSL4 Floor 2 Plan Part 3B- Power | 10/31/08 | ||
EP2.23C |
BSL4 Floor 2 Plan Part 3C- Power | 9/19/08 | ||
EP1.31 |
Floor 3 Plan Part 1- Power | 9/19/08* | ||
EP1.32 |
Floor 3 Plan Part 2- Power | 1/19/09 | ||
EP1.33 |
Floor 3 Plan Part 3- Power | 1/19/09 | ||
EP1.34 |
Floor 3 Plan Part 4- Power | 10/31/08* | ||
EP1.35 |
Floor 3 Plan Part 5- Power | 10/31/08* | ||
EP1.36 |
Floor 3 Plan Part 6- Power | 10/31/08* | ||
EP1.37 |
Floor 3 Plan Part 7- Power | 9/19/08 | ||
EP1.38 |
Floor 3 Plan Part 8- Power | 9/19/08 | ||
EP1.39 |
Floor 3 Plan Part 9- Power | 10/31/08 | ||
EP1.41 |
Floor 4 Plan Part 1- Power | 10/31/08 | ||
EP1.42 |
Floor 4 Plan Part 2- Power | 9/19/08 | ||
EP1.43 |
Floor 4 Plan Part 3- Power | 01/12/09 | ||
EP1.44 |
Floor 4 Plan Part 4- Power | 10/31/08 | ||
EP1.45 |
Floor 4 Plan Part 5- Power | 9/19/08 | ||
EP1.46 |
Floor 4 Plan Part 6- Power | 9/19/08 | ||
EP1.47 |
Floor 4 Plan Part 7- Power | 9/19/08 | ||
EP1.48 |
Floor 4 Plan Part 8- Power | 9/19/08 | ||
EP1.49 |
Floor 4 Plan Part 9- Power | 10/31/08 | ||
EP1.4TZ2 |
Floor 4 Transition Zone Plan Part 2- Power | 10/31/08 | ||
EP1.4TZ3 |
Floor 4 Transition Zone Plan Part 3- Power | 10/31/08 | ||
EP1.4TZ4 |
Floor 4 Transition Zone Plan Part 4- Power | 10/31/08 | ||
EP1.51 |
Floor 5 Plan Part 1- Power | 10/31/08 | ||
EP1.52 |
Floor 5 Plan Part 2- Power | 10/31/08 | ||
EP1.53 |
Floor 5 Plan Part 3- Power | 10/31/08 | ||
EP1.54 |
Floor 5 Plan Part 4- Power | 10/31/08 | ||
EP1.55 |
Floor 5 Plan Part 5- Power | 10/31/08 | ||
EP1.56 |
Floor 5 Plan Part 6- Power | 10/31/08 | ||
EP1.57 |
Floor 5 Plan Part 7- Power | 9/19/08 | ||
EP1.58 |
Floor 5 Plan Part 8- Power | 9/19/08 | ||
EP1.59 |
Floor 5 Plan Part 9- Power | 10/31/08 | ||
EP1.61 |
Floor 6 Plan Part 1- Power | 9/19/08 | ||
EP1.62 |
Floor 6 Plan Part 2- Power | 10/31/08 | ||
EP1.63 |
Floor 6 Plan Part 3- Power | 10/31/08 | ||
EP1.64 |
Floor 6 Plan Part 4- Power | 10/31/08 | ||
EP1.65 |
Floor 6 Plan Part 5- Power | 10/31/08 | ||
EP1.66 |
Floor 6 Plan Part 6- Power | 10/31/08 | ||
EP1.67 |
Floor 6 Plan Part 7- Power | 1/12/09 | ||
EP1.67-X |
Floor 6 Plan Part 7- Power- Bid Option #42 | 1/12/09 | ||
EP1.68 |
Floor 6 Plan Part 8- Power | 10/31/08 | ||
EP1.69 |
Floor 6 Plan Part 8- Power | 10/31/08 | ||
EP1.6P4 |
Floor 6P Plan Part 4- Power | 10/31/08 | ||
EP1.6P6 |
Floor 6P Plan Part 6- Power | 9/19/08* | ||
EP1.6P7 |
Floor 6P Plan Part 7- Power | 9/19/08* | ||
EP1.6P8 |
Floor 6P Plan Part 8- Power | 9/19/08* | ||
EP0.28A |
Roof Plan Part 1-5- Power | 9/19/08* | ||
EP0.28B |
Roof Plan Part 6-9- Power | 9/19/08* | ||
E0.012 |
Cover Sheet- Electrical- Part 2 | 1/12/09* | ||
E0.022 |
Index of Drawings- Electrical- Part 2 | 1/19/09 | ||
E0.11 |
Symbol List Part 1 | 9/19/08 | ||
E0.12 |
Symbol List Part 2 | 10/31/08 | ||
ECS0.01 |
Site Plan Communications | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 34 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
EC1.04 |
Basement Floor Plan Part 4- Communications | 1/19/09 | ||
EC1.05 |
Basement Floor Plan Part 5- Communications | 9/19/08 | ||
EC1.05E |
Basement Floor Plan Part 5E Tunnel- Communications | 9/19/08 | ||
EC1.09 |
Basement Floor Plan Part 9- Communications | 1/19/09 | ||
EC1.11 |
Floor 1 Plan Part 1- Communications | 10/31/08 | ||
EC1.11-X |
Floor 1 Plan Part 1- Communications- Bid Option #03 | 10/31/08 | ||
EC1.12 |
Floor 1 Plan Part 2- Communications | 9/19/08 | ||
EC1.13 |
Floor 1 Plan Part 3- Communications | 9/19/08 | ||
EC1.14 |
Floor 1 Plan Part 4- Communications | 1/19/09 | ||
EC1.15 |
Floor 1 Plan Part 5- Communications | 10/31/08 | ||
EC1.16 |
Floor 1 Plan Part 6- Communications | 10/31/08 | ||
EC1.17 |
Floor 1 Plan Part 7- Communications | 10/31/08 | ||
EC1.18 |
Floor 1 Plan Part 8- Communications | 10/31/08 | ||
EC1.19 |
Floor 1 Plan Part 9- Communications | 10/31/08 | ||
EC1.21 |
Floor 2 Plan Part 1- Communications | 9/19/08 | ||
EC1.21-X |
Floor 2 Plan Part 1- Communications- Bid Option #03 | 9/19/08 | ||
EC1.22 |
Floor 2 Plan Part 2- Communications | 10/31/08 | ||
EC1.23 |
Floor 2 Plan Part 3- Communications | 9/19/08 | ||
EC1.24 |
Floor 2 Plan Part 4- Communications | 9/19/08 | ||
EC1.25 |
Floor 2 Plan Part 5- Communications | 10/31/08 | ||
EC1.26 |
Floor 2 Plan Part 6- Communications | 9/19/08 | ||
EC1.27 |
Floor 2 Plan Part 7- Communications | 9/19/08 | ||
EC1.28 |
Floor 2 Plan Part 8- Communications | 9/19/08 | ||
EC1.29 |
Floor 2 Plan Part 9- Communications | 9/19/08 | ||
EC1.31 |
Floor 3 Plan Part 1- Communications | 9/19/08 | ||
EC1.32 |
Floor 3 Plan Part 2- Communications | 9/19/08 | ||
EC1.33 |
Floor 3 Plan Part 3- Communications | 9/19/08 | ||
EC1.34 |
Floor 3 Plan Part 4- Communications | 9/19/08 | ||
EC1.35 |
Floor 3 Plan Part 5- Communications | 9/19/08 | ||
EC1.36 |
Floor 3 Plan Part 6- Communications | 9/19/08 | ||
EC1.37 |
Floor 3 Plan Part 7- Communications | 9/19/08 | ||
EC1.38 |
Floor 3 Plan Part 8- Communications | 9/19/08 | ||
EC1.39 |
Floor 3 Plan Part 9- Communications | 9/19/08 | ||
EC1.41 |
Floor 4 Plan Part 1- Communications | 9/19/08 | ||
EC1.42 |
Floor 4 Plan Part 2- Communications | 9/19/08 | ||
EC1.43 |
Floor 4 Plan Part 3- Communications | 9/19/08 | ||
EC1.44 |
Floor 4 Plan Part 4- Communications | 9/19/08 | ||
EC1.45 |
Floor 4 Plan Part 5- Communications | 1/19/09 | ||
EC1.46 |
Floor 4 Plan Part 6- Communications | 9/19/08 | ||
EC1.47 |
Floor 4 Plan Part 7- Communications | 9/19/08 | ||
EC1.48 |
Floor 4 Plan Part 8- Communications | 9/19/08 | ||
EC1.49 |
Floor 4 Plan Part 9- Communications | 9/19/08 | ||
EC1.51 |
Floor 5 Plan Part 1- Communications | 9/19/08 | ||
EC1.52 |
Floor 5 Plan Part 2- Communications | 9/19/08 | ||
EC1.53 |
Floor 5 Plan Part 3- Communications | 9/19/08 | ||
EC1.54 |
Floor 5 Plan Part 4- Communications | 9/19/08 | ||
EC1.55 |
Floor 5 Plan Part 5- Communications | 9/19/08 | ||
EC1.56 |
Floor 5 Plan Part 6- Communications | 9/19/08 | ||
EC1.57 |
Floor 5 Plan Part 7- Communications | 9/19/08 | ||
EC1.58 |
Floor 5 Plan Part 8- Communications | 9/19/08 | ||
EC1.59 |
Floor 5 Plan Part 9- Communications | 10/31/08 | ||
EC1.61 |
Floor 6 Plan Part 1- Communications | 9/19/08 | ||
EC1.62 |
Floor 6 Plan Part 2- Communications | 9/19/08 | ||
EC1.63 |
Floor 6 Plan Part 3- Communications | 9/19/08 | ||
EC1.64 |
Floor 6 Plan Part 4- Communications | 9/19/08 | ||
EC1.65 |
Floor 6 Plan Part 5- Communications | 9/19/08 | ||
EC1.66 |
Floor 6 Plan Part 6- Communications | 9/19/08 | ||
EC1.67 |
Floor 6 Plan Part 7- Communications | 9/19/08 | ||
EC1.68 |
Floor 6 Plan Part 8- Communications | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 35 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
EC1.69 |
Floor 6 Plan Part 9- Communications | 9/19/08 | ||
EC1.6P4 |
Floor 6P Plan Part 4- Communications | 9/19/08 | ||
EC1.6P8 |
Floor 6P Plan Part 8- Communications | 9/19/08 | ||
EF1.04 |
Basement Floor Plan Part 4- Fire Alarm | 1/19/09 | ||
EF1.05 |
Basement Floor Plan Part 5- Fire Alarm | 9/19/08 | ||
EF1.05E |
Basement Floor Plan Part 5E Tunnel- Fire Alarm | 9/19/08 | ||
EF1.09 |
Basement Floor Plan Part 9- Fire Alarm | 1/19/09 | ||
EF1.11 |
Floor 1 Plan Part 1- Fire Alarm | 9/19/08 | ||
EF1.11-X |
Floor 1 Plan Part 1- Fire Alarm- Bid Option #03 | 9/19/08 | ||
EF1.12 |
Floor 1 Plan Part 2- Fire Alarm | 9/19/08 | ||
EF1.13 |
Floor 1 Plan Part 3- Fire Alarm | 9/19/08 | ||
EF1.14 |
Floor 1 Plan Part 4- Fire Alarm | 1/19/09 | ||
EF1.15 |
Floor 1 Plan Part 5- Fire Alarm | 9/19/08 | ||
EF1.16 |
Floor 1 Plan Part 6- Fire Alarm | 10/31/08 | ||
EF1.17 |
Floor 1 Plan Part 7- Fire Alarm | 9/19/08 | ||
EF1.18 |
Floor 1 Plan Part 8- Fire Alarm | 9/19/08 | ||
EF1.19 |
Floor 1 Plan Part 9- Fire Alarm | 10/31/08* | ||
EF1.21 |
Floor 2 Plan Part 1- Fire Alarm | 9/19/08 | ||
EF1.21-X |
Floor 2 Plan Part 1- Fire Alarm- Bid Option #03 | 9/19/08 | ||
EF1.22 |
Floor 2 Plan Part 2- Fire Alarm | 12/1/08 | ||
EF1.23 |
Floor 2 Plan Part 3- Fire Alarm | 12/1/08 | ||
EF1.24 |
Floor 2 Plan Part 4- Fire Alarm | 12/1/08 | ||
EF1.25 |
Floor 2 Plan Part 5- Fire Alarm | 9/19/08 | ||
EF1.26 |
Floor 2 Plan Part 6- Fire Alarm | 10/31/08 | ||
EF1.27 |
Floor 2 Plan Part 7- Fire Alarm | 9/19/08 | ||
EF1.28 |
Floor 2 Plan Part 8- Fire Alarm | 9/19/08 | ||
EF1.29 |
Floor 2 Plan Part 9- Fire Alarm | 9/19/08 | ||
EF1.31 |
Floor 3 Plan Part 1- Fire Alarm | 10/31/08 | ||
EF1.32 |
Floor 3 Plan Part 2- Fire Alarm | 9/19/08 | ||
EF1.33 |
Floor 3 Plan Part 3- Fire Alarm | 9/19/08 | ||
EF1.34 |
Floor 3 Plan Part 4- Fire Alarm | 10/31/08 | ||
EF1.35 |
Floor 3 Plan Part 5- Fire Alarm | 9/19/08 | ||
EF1.36 |
Floor 3 Plan Part 6- Fire Alarm | 10/31/08 | ||
EF1.37 |
Floor 3 Plan Part 7- Fire Alarm | 9/19/08 | ||
EF1.38 |
Floor 3 Plan Part 8- Fire Alarm | 9/19/08 | ||
EF1.39 |
Floor 3 Plan Part 9- Fire Alarm | 10/31/08 | ||
EF1.41 |
Floor 4 Plan Part 1- Fire Alarm | 9/19/08 | ||
EF1.42 |
Floor 4 Plan Part 2- Fire Alarm | 12/1/08 | ||
EF1.43 |
Floor 4 Plan Part 3- Fire Alarm | 12/1/08 | ||
EF1.44 |
Floor 4 Plan Part 4- Fire Alarm | 12/1/08 | ||
EF1.45 |
Floor 4 Plan Part 5- Fire Alarm | 9/19/08 | ||
EF1.46 |
Floor 4 Plan Part 6- Fire Alarm | 10/31/08 | ||
EF1.47 |
Floor 4 Plan Part 7- Fire Alarm | 9/19/08 | ||
EF1.48 |
Floor 4 Plan Part 8- Fire Alarm | 9/19/08 | ||
EF1.49 |
Floor 4 Plan Part 9- Fire Alarm | 10/31/08* | ||
EF1.51 |
Floor 5 Plan Part 1- Fire Alarm | 9/19/08 | ||
EF1.52 |
Floor 5 Plan Part 2- Fire Alarm | 9/19/08 | ||
EF1.53 |
Floor 5 Plan Part 3- Fire Alarm | 9/19/08 | ||
EF1.54 |
Floor 5 Plan Part 4- Fire Alarm | 9/19/08 | ||
EF1.55 |
Floor 5 Plan Part 5- Fire Alarm | 9/19/08 | ||
EF1.56 |
Floor 5 Plan Part 6- Fire Alarm | 10/31/08 | ||
EF1.57 |
Floor 5 Plan Part 7- Fire Alarm | 1/12/09 | ||
EF1.58 |
Floor 5 Plan Part 8- Fire Alarm | 9/19/08 | ||
EF1.59 |
Floor 5 Plan Part 9- Fire Alarm | 9/19/08 | ||
EF1.61 |
Floor 6 Plan Part 1- Fire Alarm | 9/19/08 | ||
EF1.62 |
Floor 6 Plan Part 2- Fire Alarm | 9/19/08 | ||
EF1.63 |
Floor 6 Plan Part 3- Fire Alarm | 9/19/08 | ||
EF1.64 |
Floor 6 Plan Part 4- Fire Alarm | 9/19/08 | ||
EF1.65 |
Floor 6 Plan Part 5- Fire Alarm | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 36 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
EF1.66 |
Floor 6 Plan Part 6- Fire Alarm | 9/19/08 | ||
EF1.66-X |
Floor 6 Plan Part 6- Fire Alarm- Bid Option #26 | 9/19/08 | ||
EF1.67 |
Floor 6 Plan Part 7- Fire Alarm | 1/19/09 | ||
EF1.67-X |
Floor 6 Plan Part 7- Fire Alarm- Bid Option #26 | 1/12/09 | ||
EF1.68 |
Floor 6 Plan Part 8- Fire Alarm | 9/19/08 | ||
EF1.68-X |
Floor 6 Plan Part 8- Fire Alarm- Bid Option #26 | 9/19/08 | ||
EF1.69 |
Floor 6 Plan Part 9- Fire Alarm | 9/19/08 | ||
EF1.69-X |
Floor 6 Plan Part 9- Fire Alarm- Bid Option #26 | 9/19/08 | ||
EF1.6P4 |
Floor 6P Plan Part 4- Fire Alarm- Bid Option #26 | 9/19/08 | ||
EF1.6P8 |
Floor 6P Plan Part 8- Fire Alarm- Bid Option #27 | 9/19/08 | ||
E0.013 |
Cover Sheet- Electrical- Part 3 | 1/12/09* | ||
E0.023 |
Index of Drawings- Electrical- Part 3 | 1/12/09* | ||
E0.11 |
Symbol List- Part 1 | 9/19/08 | ||
E0.12 |
Symbol List- Part 2 | 10/31/08 | ||
E2.01 |
Partial Floor Plans- Power | 10/31/08 | ||
E2.02 |
Partial Floor Plans- Power | 10/31/08 | ||
E2.03 |
Partial Floor Plans- Power | 10/31/08 | ||
E2.04 |
Partial Floor Plans- Power | 10/31/08 | ||
E2.05 |
Partial Floor Plans- Power | 10/31/08 | ||
E2.06 |
Partial Floor Plans- Power | 9/19/08 | ||
E2.06-X |
Partial Floor Plans- Power- Bid Option #03 | 9/19/08 | ||
E2.07 |
Partial Floor Plans- Power | 10/31/08 | ||
E2.08 |
Partial Floor Plans- Power | 9/19/08 | ||
E2.09 |
Partial Floor Plans- Power | 9/19/08 | ||
E2.10 |
Partial Floor Plans- Power | 9/19/08 | ||
E2.11 |
Partial Floor Plans- Power | 9/19/08 | ||
E2.12 |
Partial Floor Plans- Power | 9/19/08 | ||
E2.21 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.22 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.23 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.24 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.25 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.26 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.27 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.28 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.29 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.30 |
Partial Floor Plans- Communications | 9/19/08 | ||
E2.31 |
Partial Floor Plans- Communications | 9/19/08 | ||
E3.01 |
Lighting Fixture Schedule | 10/31/08 | ||
E3.02 |
Lighting Fixture Schedule | 10/31/08 | ||
E3.03 |
Lighting Fixture Schedule | 10/31/08 | ||
E3.04 |
Lighting Details | 9/19/08 | ||
E3.05 |
Lighting Details | 9/19/08 | ||
E3.06 |
Lighting Plate Details | 9/19/08 | ||
E3.07 |
Lighting Plate Details | 9/19/08 | ||
E3.08 |
Lighting Plate Details | 9/19/08 | ||
E3.09 |
Lighting Control System Riser Diagram and Details | 9/19/08 | ||
E3.10 |
Lighting Control System Relay Panel Schedules | 9/19/08 | ||
E3.11 |
Lighting Control System Relay Panel Schedules | 10/31/08 | ||
E3.12 |
Lighting Control System Relay Panel Schedules | 9/19/08 | ||
E3.13 |
Lighting Control System Relay Panel Schedules | 9/19/08 | ||
E3.14 |
Lighting Details Multi-Purpose Room 1EA605 | 9/19/08 | ||
E3.15 |
Lighting Control System Dimming Systems | 9/19/08 | ||
E3.16 |
Lighting Control System Dimming Systems | 9/19/08 | ||
E3.17 |
Lighting Control System Dimming Systems | 12/1/08 | ||
E3.20 |
Panel Schedules | 9/19/08 | ||
E3.21 |
Panel Schedules | 9/19/08 | ||
E3.22 |
Panel Schedules | 9/19/08 | ||
E3.23 |
Panel Schedules | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 37 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
E3.24 |
Panel Schedules | 9/19/08 | ||
E3.25 |
Panel Schedules | 1/19/09 | ||
E3.26 |
Panel Schedules | 10/31/08 | ||
E3.27 |
Panel Schedules | 1/19/09 | ||
E3.28 |
Panel Schedules | 9/19/08 | ||
E3.29 |
Panel Schedules | 1/19/09 | ||
E3.30 |
Panel Schedules | 9/19/08 | ||
E3.31 |
Panel Schedules | 10/31/08 | ||
E3.32 |
Panel Schedules | 9/19/08 | ||
E3.33 |
Panel Schedules | 9/19/08 | ||
E3.34 |
Panel Schedules | 9/19/08 | ||
E3.35 |
Panel Schedules | 9/19/08 | ||
E3.36 |
Panel Schedules | 9/19/08 | ||
E3.37 |
Panel Schedules | 9/19/08 | ||
E3.38 |
Panel Schedules | 9/19/08 | ||
E3.39 |
Panel Schedules | 10/31/08 | ||
E3.40 |
Panel Schedules | 1/19/09 | ||
E3.41 |
Panel Schedules | 9/19/08 | ||
E3.42 |
Panel Schedules | 1/19/09 | ||
E3.43 |
Panel Schedules | 10/31/08 | ||
E3.44 |
Panel Schedules | 10/31/08 | ||
E3.45 |
Panel Schedules | 9/19/08 | ||
E3.46 |
Panel Schedules | 10/31/08 | ||
E3.47 |
Panel Schedules | 9/19/08 | ||
E3.48 |
Panel Schedules | 9/19/08 | ||
E3.49 |
Panel Schedules | 9/19/08 | ||
E3.50 |
Panel Schedules | 1031/08 | ||
E3.51 |
Panel Schedules | 9/19/08 | ||
E3.52 |
Panel Schedules | 1/12/09 | ||
E3.53 |
Panel Schedules | 9/19/08 | ||
E3.54 |
Panel Schedules | 9/19/08 | ||
E3.55 |
Panel Schedules | 10/31/08 | ||
E3.56 |
Panel Schedules | 9/19/08 | ||
E3.57 |
Panel Schedules | 10/31/08 | ||
E3.58 |
Panel Schedules | 9/19/08 | ||
E3.59 |
Panel Schedules | 9/19/08 | ||
E3.60 |
Panel Schedules | 9/19/08 | ||
E3.61 |
Panel Schedules | 10/31/08 | ||
E3.62 |
Panel Schedules | 10/31/08 | ||
E3.63 |
Panel Schedules | 9/19/08 | ||
E3.64 |
Panel Schedules | 9/19/08 | ||
E3.65 |
Panel Schedules | 9/19/08 | ||
E3.66 |
Panel Schedules | 9/19/08 | ||
E3.67 |
Panel Schedules | 9/19/08 | ||
E4.01 |
Single Line Diagram | 1/12/09 | ||
E4.02 |
Single Line Diagram | 10/31/08 | ||
E4.03 |
Single Line Diagram | 10/31/08 | ||
E4.04 |
Single Line Diagram | 10/31/08 | ||
E4.05 |
Single Line Diagram | 10/31/08 | ||
E4.06 |
Single Line Diagram | 10/31/08 | ||
E4.07 |
Single Line Diagram | 10/31/08 | ||
E4.08 |
Single Line Diagram | 9/19/08 | ||
E4.08-X |
Single Line Diagram- Bid Option #03 | 9/19/08 | ||
E4.09 |
Single Line Diagram | 1/12/09 | ||
E4.10 |
Single Line Diagram | 10/31/08 | ||
E4.11 |
Single Line Diagram | 10/31/08 | ||
E4.12 |
Single Line Diagram | 9/19/08 | ||
E4.13 |
Single Line Diagram | 12/1/08 | ||
E4.14 |
Single Line Diagram | 12/1/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 38 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
E4.15 |
Single Line Diagram | 10/31/08 | ||
E4.16 |
Single Line Diagram | 10/31/08 | ||
E4.17 |
Single Line Diagram | 10/31/08 | ||
E4.18 |
Single Line Diagram | 9/19/08 | ||
E4.19 |
Single Line Diagram | 9/19/08 | ||
E4.20 |
Single Line Diagram | 10/31/08 | ||
E4.21 |
Single Line Diagram | 9/19/08 | ||
E4.22 |
Single Line Diagram | 9/19/08 | ||
E4.23 |
Single Line Diagram | 9/19/08 | ||
E4.24 |
Single Line Diagram | 1/12/09 | ||
E4.24-X |
Single Line Diagram- Bid Option #42 | 1/12/09 | ||
E4.25 |
Single Line Diagram | 1/12/09 | ||
Ef.25-X |
Single Line Diagram- Bid Option #42 | 1/12/09 | ||
E4.26 |
Single Line Diagram | 9/19/08 | ||
E4.27 |
Single Line Diagram | 9/19/08 | ||
E4.28 |
Single Line Diagram | 9/19/08 | ||
E4.29 |
Building Distribution Riser Diagram | 9/19/08 | ||
E4.30 |
Building Distribution Riser Diagram | 12/1/08 | ||
E4.31 |
Electrical Service Zones | 9/19/08 | ||
E4.32 |
Electrical Service Zones | 9/19/08 | ||
E4.33 |
Electrical Service Zones | 9/19/08 | ||
E4.34 |
Electrical Service Zones | 9/19/08 | ||
E4.35 |
Electrical Service Zones | 9/19/08 | ||
E4.40 |
Grounding Riser Diagram | 9/19/08 | ||
E4.41 |
Fire Alarm System Diagrams | 9/19/08 | ||
E4.42 |
Fire Alarm System Diagrams | 1/19/09 | ||
E4.43 |
Fire Alarm System Diagrams | 1/19/08 | ||
E4.44 |
Fire Alarm System Diagrams | 1/19/08 | ||
E4.45 |
Fire Alarm System Diagrams | 1/19/08 | ||
E4.50 |
Communications Systems Diagrams | 9/19/08 | ||
E4.51 |
Communications Systems Diagrams | 9/19/08 | ||
E4.52 |
Communications Systems Diagrams | 9/19/08 | ||
E4.53 |
Communications Systems Diagrams | 9/19/08 | ||
E4.54 |
Communications Systems Diagrams . | 9/19/08 | ||
E4.55 |
Communications Systems Diagrams | 9/19/08 | ||
E4.56 |
Communications Systems Diagrams | 9/19/08 | ||
E4.57 |
Communications Systems Diagrams | 9/19/08 | ||
E4.58 |
Communications Systems Diagrams | 9/19/08 | ||
E5.00 |
Electrical Details | 9/19/08 | ||
E5.01 |
Electrical Details | 9/19/08 | ||
E5.02 |
Electrical Details | 9/19/08 | ||
E5.03 |
Electrical Details | 9/19/08 | ||
E5.04 |
Electrical Details | 9/19/08 | ||
E5.05 |
Electrical Details | 9/19/08 | ||
E5.06 |
Electrical Details | 9/19/08 | ||
E5.07 |
Electrical Details | 10/31/08 | ||
E5.11 |
Electrical Details | 10/31/08 | ||
E5.12 |
Electrical Details | 9/19/08 | ||
E5.13 |
Electrical Details | 9/19/08 | ||
E5.14 |
Electrical Details | 9/19/08 | ||
E5.51 |
Electrical Details | 9/19/08 | ||
SIGNAGE | ||||
GR0.011 |
Cover Sheet- Signage | 10/31/08 | ||
GR0.0212 |
Index of Drawings- Signage | 10/31/08 | ||
GR1.100 |
Site Signage Placement Plan Phase 1 & 2 | 10/31/08 | ||
GR3.100 |
Site Signage Details | 10/31/08 | ||
GR.404 |
Basement Signage Location Plan- Key Plan Parts 4 & 5 | 10/31/08 | ||
GR.409 |
Basement Signage Location Plan- Key Plan Part 9 | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 39 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
GR.411 |
Floor 1 Signage Location Plan- Key Plan Parts 1 to 5 | 10/31/08 | ||
GR.416 |
Floor 1 Signage Location Plan- Key Plan Parts 6 to 9 | 10/31/08 | ||
GR.421 |
Floor 2 Signage Location Plan- Key Plan Parts 1 to 5 | 10/31/08 | ||
GR.426 |
Floor 2 Signage Location Plan- Key Plan Parts 6 to 9 | 10/31/086 | ||
GR.431 |
Floor 3 Signage Location Plan- Key Plan Parts 1 to 5 | 10/31/086 | ||
GR.436 |
Floor 3 Signage Location Plan- Key Plan Parts 6 to 9 | 10/31/08 | ||
GR.441 |
Floor 4 Signage Location Plan- Key Plan Parts 1 to 5 | 10/31/08 | ||
GR.446 |
Floor 4 Signage Location Plan- Key Plan Parts 6 to 9 | 10/31/08 | ||
GR.451 |
Floor 5 Signage Location Plan- Key Plan Parts 1 to 5 | 10/31/08 | ||
GR.456 |
Floor 5 Signage Location Plan- Key Plan Parts 6 to 9 | 10/31/08 | ||
GR.461 |
Floor 6 Signage Plan- Key Plan Parts 1 to 5 | 10/31/08 | ||
GR.466 |
Floor 6 Signage Location Plan- Key Plan Parts 6 to 9 | 10/31/08 | ||
GR.501 |
Sign Details | 10/31/08 | ||
GR.502 |
Sign Details | 10/31/08 | ||
GR.503 |
Sign Details | 10/31/08 | ||
GR7.01 |
Signage Message Schedule Basement and Floors 1 and 6 | 10/31/08 | ||
GR7.02 |
Signage Message Schedule Floor 2 | 10/31/08 | ||
GR7.03 |
Signage Message Schedule Floors 3 and 5 | 10/31/08 | ||
GR7.04 |
Signage Message Schedule Floor 4 | 10/31/08 | ||
SHIELDING | ||||
SH0.011 |
Cover Sheet- Consultant- Sheilding | 10/31/08 | ||
SH0.021 |
Index of Drawings- Consultant- Sheilding | 9/19/08 | ||
SH0.11 |
Specialty Details Imaging- General Information | 10/31/08 | ||
SH2.01 |
Specialty Details Imaging- Foundation Plan | 9/19/08 | ||
SH2.11 |
Specialty Details Imaging- Floor Plan | 10/31/08 | ||
SH3.01 |
Specialty Details Imaging- Elevations | 9/19/08 | ||
SH5.01 |
Specialty Details Imaging- RF Details | 10/31/08 | ||
SH5.02 |
Specialty Details Imaging- Unistrut Layout | 10/31/08 | ||
SH5.03 |
Specialty Details Imaging- M36 Silicon Steel Elevations | 9/19/08 | ||
SH5.04 |
Specialty Details Imaging- Remote Sheilds | 10/31/08 | ||
SH5.05 |
Specialty Details Imaging- RF Filter Box | 9/19/08 | ||
SECTION |
DESCRIPTION | |||
INTRODUCTORY INFORMATION AND INFORMATION AVAILABLE | ||||
00 00 01 |
PROJECT TITLE PAGE | |||
00 00 10 |
BID SCHEDULE | 1/23/09 | ||
TABLE OF CONTENTS | 1/23/09 | |||
SUBMITTAL REGISTER | 1/23/09 | |||
CONTRACTING REQUIREMENTS | ||||
DIVISION 1 GENERAL REQUIREMENTS | ||||
01 00 00 |
ADMINISTRATIVE REQUIREMENTS | 12/5/08 | ||
01 05 00 |
JOB CONSIDERATIONS | 1/23/09 | ||
01 07 00 |
CUTTING, PATCHING AND REPAIRING | 9/19/08 | ||
01 11 00 |
SUMMARY OF WORK | 10/31/08 | ||
01 20 00 |
WARRANTY REQUIREMENT | 9/19/08 | ||
01 27 00 |
MEASUREMENT AND PAYMENT | 1/23/09 | ||
01 31 11 |
SUSPENDED LOADING-COORDINATION AND LIMITATIONS | 9/19/08 | ||
01 31 15 |
CONTAINMENT CONSTRUCTION COORDINATION | 10/31/08 | ||
01 31 19 |
PROJECT MEETINGS | 10/31/08 | ||
01 32 01.001 |
PROJECT SCHEDULE | 1/23/09 | ||
01 33 00 |
SUBMITTAL PROCEDURES | 10/31/08 | ||
01 33 10 |
SPECIAL SUBMITTAL PROCEDURES | 12/5/08 | ||
01 33 29 |
LEED(TM) DOCUMENTATION | 1/23/09 | ||
01 33 40 |
COLOR/FINISH SAMPLE BOARDS | 9/19/08 | ||
01 35 29 |
SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 40 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
01 41 50 |
SEISMIC CONTROL REQUIREMENTS | 10/31/08 | ||
01 41 60 |
WIND LOAD DESIGN CRITERIA | 9/19/08 | ||
01 42 00 |
SOURCES FOR REFERENCE PUBLICATIONS | 1/23/09 | ||
01 42 13 |
REFERENCE STANDARDS, ABBREVIATIONS AND DEFINITIONS | 1/23/09 | ||
01 45 02.001 |
QUALITY CONTROL SYSTEM (QCS) | 10/31/08 | ||
01 45 10 |
CONTRACTOR QUALITY CONTROL | 11/26/08 | ||
01 45 35 |
SPECIAL INSPECTION | 9/19/08 | ||
01 45 70 |
ROOM INTEGRITY TESTING | 10/31/08 | ||
01 51 00 |
TEMPORARY CONSTRUCTION ITEMS | 1/23/09 | ||
01 57 20.001 |
ENVIRONMENTAL PROTECTION | 11/18/08 | ||
01 57 23.001 |
STORM WATER POLLUTION PREVENTION MEASURES | 9/19/08 | ||
01 60 00 |
PRODUCT REQUIREMENTS | 9/19/08 | ||
01 61 23 |
CONTRACTOR FURNISHED CONTRACTOR INSTALLED (CFCI) | 10/31/08 | ||
01 62 35 |
RECYCLED/RECOVERED MATERIALS | 9/19/08 | ||
01 64 01 |
GOVERNMENT FURNISHED CONTRACTOR INSTALLED (GFCI) | 11/26/08 | ||
01 64 02 |
GOVERNMENT FURNISHED GOVERNMENT INSTALLED (GFCI) | 1/23/09 | ||
01 67 00 |
MATERIAL/PRODUCT RESISTANCE | 9/19/08 | ||
01 72 00 |
AS-BUILT DRAWINGS CADD | 9/19/08 | ||
01 74 19 |
CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT | 9/19/08 | ||
01 75 00 |
STARTING AND ADJUSTING | 11/26/08 | ||
01 77 00 |
CLOSEOUT PROCEDURES | 10/31/08 | ||
01 78 23 |
OPERATION AND MAINTENANCE DATA | 12/5/08 | ||
01 79 00 |
DEMONSTRATION AND TRAINING | 11/26/08 | ||
01 81 19 |
INDOOR AIR QUALITY | 9/19/08 | ||
01 91 00 |
COMMISSIONING | 1/23/09 | ||
01 91 01 |
COMMISSIONING COMPONENT VERIFICATION | 1/23/09 | ||
01 91 02 |
COMMISSIONING SYSTEM TEST | 1/23/09 | ||
01 91 03 |
COMMISSIONING INTEGRATED SYSTEM TEST | 1/23/09 | ||
01 91 04 |
COMMISSIONING FUNCTIONAL OPERATIONAL SYSTEM TEST | 11/26/08 | ||
DIVISION 2 EXISTING CONDITIONS | ||||
02 41 00 |
DEMOLITION AND DECONSTRUCTION | 9/19/08 | ||
DIVISION 3 CONCRETE | ||||
03 08 00 |
COMMISSIONING OF CONCRETE | 9/19/08 | ||
03 11 13.001 |
STRUCTURAL CONCRETE FORMWORK | 9/19/08 | ||
03 15 13.001 |
EXPANSION JOINTS, CONTRACTION JOINTS, AND WATERSTOPS | 9/19/08 | ||
03 20 01.001 |
CONCRETE REINFORCEMENT | 9/19/08 | ||
03 31 00.001 |
CAST-IN-PLACE STRUCTURAL CONCRETE | 1/23/09 | ||
03 31 05 |
HIGH CONTAINMENT CAST-IN-PLACE STRUCTURAL CONCRETE | 10/31/08 | ||
03 35 13 |
HIGH-TOLERANCE CONCRETE FLOOR FINISHING | 9/19/08 | ||
03 41 33.001 |
PRECAST/PRESTRESSED CONCRETE FLOOR AND ROOF UNITS | 09/19/08 | ||
03 45 01.001 |
PRECAST ARCHITECTURAL CONCRETE | 9/19/08 | ||
DIVISION 4 MASONRY | ||||
04 20 00 |
MASONRY | 1/23/09 | ||
04 43 30 |
CUT STONE | 919/08 | ||
04 72 00 |
CAST STONE | 9/19/08 | ||
DIVISION 5 METALS | ||||
05 05 13 |
FACTORY-APPLIED METAL COATINGS | 9/19/08 | ||
05 08 00 |
COMMISSIONING OF METALS | 9/19/08 | ||
05 12 00 |
STRUCTURAL STEEL | 10/31/08 | ||
05 30 00 |
STEEL DECKS | 1/23/09 | ||
05 40 00 |
COLD-FORMED METAL FRAMING | 9/19/08 | ||
05 50 00 |
METAL: MISCELLANEOUS AND FABRICATIONS` | 10/31/08 | ||
05 50 10.00 |
SPECIAL METAL FABRICATIONS | 12/5/08 | ||
05 51 00 |
METAL STAIRS | 12/5/08 | ||
05 71 00 |
ORNAMENTAL STAIRS | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 41 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
05 72 00 |
ORNAMENTAL HANDRAILS AND RAILINGS | 9/19/08 | ||
DIVISION 6 WOOD AND PLASTICS | ||||
06 10 00 |
ROUGH CARPENTRY | 9/19/08 | ||
06 20 00 |
FINISH CARPENTRY | 11/26/08 | ||
06 41 16.00 10 |
LAMINATE CLAD ARCHITECTURAL CASEWORK | 9/19/08 | ||
06 51 50 |
FIBERGLASS (FRP) GRATINGS | 10/31/08 | ||
06 61 16 |
SOLID POLYMER (SOLID SURFACING) FABRICATIONS | 9/19/08 | ||
DIVISION 7 THERMAL AND MOISTURE PROTECTION | ||||
07 08 00 |
COMMISSIONING OF THERMAL AND MOISTURE PROTECTION | 9/19/08 | ||
07 13 53 |
ELASTOMERIC SHEET WATERPROOFING | 9/19/08 | ||
07 14 00 |
FLUID-APPLIED WATERPROOFING | 1/23/09 | ||
07 16 19 |
METALLIC OXIDE WATERPROOFING | 9/19/08 | ||
07 18 00 |
TRAFFIC COATINGS | 9/19/08 | ||
07 21 00 |
BUILDING INSULATION | 9/19/08 | ||
07 21 16 |
MINERAL FIBER BLANKET INSULATION | 9/19/08 | ||
07 21 19 |
SPRAYED POLYURETHANE INSULATION | 9/19/08 | ||
07 21 29 |
SPRAYED THERMAL INSULATION | 9/19/08 | ||
07 22 00 |
ROOF AND DECK INSULATION | 9/19/08 | ||
07 41 13 |
NON-STRUCTURAL METAL ROOFING | 1/23/09 | ||
07 42 13 |
METAL WALL PANELS | 11/26/08 | ||
07 42 50 |
ALUMINUM AND PLASTIC COMPOSITE PANELS | 9/19/08 | ||
07 52 00 |
MODIFIED BITUMINOUS MEMBRANE ROOFING | 1/23/09 | ||
07 55 56 |
RUBBERIZED ASPHALT PROTECTED MEMBRANE ROOFING | 1/23/09 | ||
07 60 00 |
FLASHING AND SHEET METAL | 9/19/08 | ||
07 71 00 |
ROOF SPECIALTIES AND ACCESSORIES | 9/19/08 | ||
07 81 00 |
SPRAY-APPLIED FIREPROOFING | 9/19/08 | ||
07 81 23 |
INTUMESCENT FIREPROOFING | 9/19/08 | ||
07 84 00 |
FIRESTOPPING | 9/19/08 | ||
07 92 00 |
JOINT SELANTS | 1/23/09 | ||
07 95 13 |
EXPANSION JOINT COVER ASSEMBLIES | 9/19/08 | ||
DIVISION 08- OPENINGS | ||||
08 05 00 |
COMMON WORK RESULTS FOR OPENINGS (FOUO) | 1/23/09 | ||
08 06 00 |
DOOR AND FRAME SCHEDULE | 1/23/09 | ||
08 08 00 |
COMMISSIONING OF OPENINGS | 9/19/08 | ||
08 11 13 |
STEEL DOORS AND FRAMES | 1/23/09 | ||
08 11 16 |
ALUMINUM DOORS AND FRAMES | 1/23/09 | ||
08 11 19 |
STAINLESS STEEL DOORS AND FRAMES | 9/19/08 | ||
08 12 16 |
ALUMINUM DOOR FRAMES | 9/19/08 | ||
08 14 00 |
WOOD DOORS | 9/19/08 | ||
08 15 00 |
PLASTIC DOORS | 9/19/08 | ||
08 31 13 |
ACCESS DOORS | 9/19/08 | ||
08 33 23 |
OVERHEAD COILING DOORS | 1/23/09 | ||
08 34 59 |
SECURITY VAULT DOOR | 9/19/08 | ||
08 38 13 |
STRIP DOORS | 9/19/08 | ||
08 39 15 |
PNEUMATIC AIR PRESSURE RESISTANT DOORS | 1031/08 | ||
08 41 13 |
METAL-FRAMED STOREFRONTS | 9/19/08 | ||
08 41 23 |
FIRE RATED GLAZED WALL ASSEMBLIES | 9/19/08 | ||
08 44 00 |
GLAZED CURTAIN WALL | 1/23/09 | ||
08 44 13 |
GLAZED CURTAIN WALL (INTERIOR) | 9/19/08 | ||
08 44 23 |
STRUCTURAL GLASS CURTAIN WALL | 9/19/08 | ||
08 55 00 |
AIR PRESSURE RESISTANT WINDOWS | 11/26/08 | ||
08 62 00 |
SKYLIGHTS | 9/19/08 | ||
08 71 00 |
DOOR HARDWARE | 10/31/08 | ||
08 71 01 |
SECURITY DOOR HARDWARE (FOUO) | 9/19/08 | ||
08 81 00 |
GLAZING | 1/23/09 | ||
08 91 00 |
METAL WALL LOUVERS | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 42 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
DIVISION 09 FINISHES | ||||
09 05 00 |
COMMON WORK RESULTS FOR FINISHES (FOUO) | 9/19/08 | ||
09 08 00 |
COMMISSIONING OF FINISHES | 9/19/08 | ||
09 22 00 |
METAL SUPPORT ASSEMBLIES | 9/19/08 | ||
09 24 23 |
PLASTER | 10/31/08 | ||
09 27 13 |
GLASS FIBER REINFORCED GYPSUM FABRICATIONS | 9/19/08 | ||
09 29 00 |
GYPSUM BOARD | 9/19/08 | ||
09 30 00 |
CERAMIC TILE | 9/19/08 | ||
09 51 00 |
ACOUSTICAL CEILINGS | 1/23/09 | ||
09 57 13 |
SANITARY CEILINGS | 9/19/08 | ||
09 60 05 |
VAPOR TRANSMISSION TESTING | 9/19/08 | ||
09 61 10 |
CONCRETE FLOOR TREATMENT | 9/19/08 | ||
09 64 13 |
WOOD FLOORING | 9/19/08 | ||
09 65 00 |
RESILIENT FLOORING | 9/19/08 | ||
09 66 13 |
PRECAST TERRAZZO | 9/19/08 | ||
09 66 23 |
RESINOUS TERRAZZO FLOORING | 9/19/08 | ||
09 67 00 |
FLUID-APPLIED FLOORING | 10/31/08 | ||
09 68 00 |
CARPET | 12/5/08 | ||
09 69 13 |
RIGID GRID ACCESS FLOORING | 9/19/08 | ||
09 83 13 |
ACOUSTICAL WALL AND CEILING TREATMENTS | 9/19/08 | ||
09 90 00 |
PAINTS AND COATINGS | 9/19/08 | ||
09 97 00 |
SPECIAL COATINGS | 12/5/08 | ||
DIVISION 10 SPECIALTIES | ||||
10 10 00 |
VISUAL COMMUNICATIONS SPECIALTIES | 11/18/08 | ||
10 14 02 |
INTERIOR SIGNAGE | 10/31/08 | ||
10 21 13 |
TOILET COMPARTMENTS | 10/31/08 | ||
10 21 23.16 |
CUBICLE TRACK AND HARDWARE | 9/19/08 | ||
10 22 13 |
WIRE MESH PARTITIONS | 9/19/08 | ||
10 22 26 |
OPERABLE PARTITIONS | 9/19/08 | ||
10 25 00 |
SERVICE WALLS | 9/19/08 | ||
10 25 13 |
PATIENT BED SERVICE WALLS | 9/19/08 | ||
10 26 13 |
WALL AND CORNER GUARDS | 11/26/08 | ||
10 28 13 |
TOILET ACCESSORIES | 11/26/08 | ||
10 44 16 |
FIRE EXTINGUISHERS | 9/19/08 | ||
10 45 40 |
OPTICAL PEDESTRIAN SECURITY LANES | 9/19/08 | ||
10 51 00 |
LOCKERS | 10/31/08 | ||
10 56 26 |
MOBILE STORAGE UNITS | 11/18/08 | ||
10 56 26.13 |
MANUAL MOBILE STORAGE SHELVING | 9/19/08 | ||
DIVISION 11 EQUIPMENT | ||||
11 05 13 |
GENERAL REQUIREMENTS FOR EQUIPMENT | 10/31/08 | ||
11 08 00 |
COMMISSIONING OF EQUIPMENT | 11/26/08 | ||
11 13 10 |
DOCK LEVELERS | 1/23/09 | ||
11 19 00 |
DETENTION EQUIPMENT | 9/19/08 | ||
11 24 33.01 |
ROOF MAINTENANCE SYSTEMS | 9/19/08 | ||
11 47 00 |
ICE MACHINES | 9/19/08 | ||
11 52 00 |
AUDIO VISUAL EQUIPMENT | 1/23/09 | ||
11 52 13 |
PROJECTION SCREENS | 9/19/08 | ||
11 53 13 |
FUME HOODS | 1/23/09 | ||
11 53 36 |
DUST COLLECTION SYSTEM | 9/19/08 | ||
11 53 53 |
BIOLOGICAL SAFETY CABINETS | 9/19/08 | ||
11 53 59 |
CLASS III BIOLOGICAL SAFETY CABINET LINES | 9/19/08 | ||
11 53 63.00 |
STERILIZERS | 1/23/09 | ||
11 53 64 |
ETO STERILIZER | 9/19/08 | ||
11 53 67 |
DEPYROGENATION OVENS | 9/19/08 | ||
11 53 69 |
TISSUE DIGESTER SYSTEM | 1/23/09 | ||
11 53 73 |
MODULAR STAINLESS STEEL WALLS | 1/23/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 43 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
11 53 91 |
TUNNEL WASHERS | 9/19/08 | ||
11 53 93 |
PIT MOUNTED WASHER | 9/19/08 | ||
11 60 00 |
GLASSWARE WASHING EQUIPMENT | 9/19/08 | ||
11 72 00 |
EXAMINATION AND TREATMENT EQUIPMENT | 9/19/08 | ||
11 72 13 |
MEDICAL EQUIPMENT, MISCELLANEOUS | 11/18/08 | ||
11 73 23.13 |
VACUUM BEDDING DELIVERY AND DUST COLLECTION EQUIPMENT | 11/26/08 | ||
11 73 23.19 |
VACUUM BEDDING WASTE AND DUST COLLECTION EQUIPMENT | 11/26/08 | ||
11 73 24 |
BEDDING DISPENSER | 11/26/08 | ||
11 94 00 |
DECONTAMINATION MISTING TUNNEL | 9/19/08 | ||
DIVISION 12 FURNISHINGS | ||||
12 08 00 |
COMMISSIONING OF FURNISHINGS | 9/19/08 | ||
12 24 13 |
ROLLER WINDOW SHADES | 9/19/08 | ||
12 35 53.13 |
METAL LABORATORY CASEWORK | 9/19/08 | ||
12 35 53.19 |
ADAPTABLE LABORATORY CASEWORK SYSTEM | 9/19/08 | ||
12 35 53.26 |
CUSTOM STAINLESS STEEL LABORATORY CASEWORK | 10/31/08 | ||
12 48 13.13 |
ENTRANCE FLOOR MATS | 9/19/08 | ||
12 93 00 |
SITE FURNISHINGS | 1/23/09 | ||
DIVISION 13 SPECIAL CONSTRUCTION | ||||
13 08 00 |
COMMISSIONING OF SPECIAL CONSTRUCTION | 9/19/08 | ||
13 21 00 |
CONTROLLED ENVIRONMENT ROOMS | 10/31/08 | ||
13 27 53 |
SECURITY VAULT (FOUO) | 10/31/08 | ||
13 48 00 |
SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT | 9/19/08 | ||
13 49 19 |
RADIATION SHIELDING | 12/5/08 | ||
13 49 23 |
MRI, RF SHIELDED ENCLOSURE | 10/31/08 | ||
DIVISION 14 CONVEYING SYSTEMS | ||||
14 21 23 |
ELECTRIC TRACTION PASSENGER ELEVATORS | 11/26/08 | ||
14 24 00 |
HYDRAULIC ELEVATORS | 11/26/08 | ||
14 42 00 |
WHEELCHAIR LIFTS | 9/19/08 | ||
14 83 16 |
SCISSOR LIFT | 9/19/08 | ||
DIVISION 21 FIRE SUPPRESSION | ||||
21 08 00 |
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS | 9/19/08 | ||
21 10 01 |
COMBINED STANDPIPE AND WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION | 10/31/08 | ||
21 30 00 |
FIRE PUMPS | 11/26/08 | ||
DIVISION 22 PLUMBING | ||||
22 00 00 |
PLUMBING, GENERAL PURPOSE | 1/23/09 | ||
22 05 19 |
PLUMBING THERMOMETERS AND GAUGES | 9/19/08 | ||
22 05 29 |
PLUMBING HANGERS AND SUPPORTS | 9/19/08 | ||
22 05 03 |
PLUMBING HEAT TRACING SYSTEM | 10/31/08 | ||
22 05 48 |
PLUMBING SOUND, VIBRATION, AND SEISMIC CONTROL | 1/23/09 | ||
22 05 53 |
PLUMBING IDENTIFICATION | 9/19/08 | ||
22 05 75 |
DRAINS AND CLEANOUTS | 1/23/09 | ||
22 07 00 |
THERMAL INSULATION FOR PLUMBING SYSTEMS | 10/31/08 | ||
22 08 00 |
COMMISSIONING OF PLUMBING SYSTEMS | 9/19/08 | ||
22 10 05 |
BUILDING SERVICES AND PROCESS PIPING SYSTEMS | 10/31/08 | ||
22 10 06 |
BUILDING SERVICES AND PROCESS PIPING SCHEDULES | 1/23/09 | ||
22 10 19 |
PLUMBING, PIPING SPECIALTIES | 1/23/09 | ||
22 11 23 |
WATER PRESSURE BOOSTER SYSTEM | 10/31/08 | ||
22 14 29 |
WASTEWATER PUMP | 9/19/08 | ||
22 15 19.19 |
NONLUBRICATED ROTARY SCREW AIR COMPRESSORS | 11/18/08 | ||
22 31 00 |
WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE) | 1/23/09 | ||
22 33 00 |
WATER HEATERS | 11/18/08 | ||
22 33 30.00 10 |
SOLAR WATER HEATING EQUIPMENT | 9/19/08 | ||
22 36 00 |
CHEMICAL SHOWER SYSTEM | 12/5/08 | ||
22 42 00 |
COMMERCIAL PLUMBING FIXTURES | 1/23/09 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 44 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
22 62 16 |
MEDICAL AND LABORATORY GAS AND VACUUM SYSTEM | 1/23/09 | ||
22 63 17 |
LIQUID NITROGEN SYSTEM | 1/23/09 | ||
22 64 00 |
BREATHING AIR SYSTEMS | 12/5/08 | ||
22 67 00 |
PURIFIED WATER GENERATING EQUIPMENT (REVERSE OSMOSIS WATER SKID/TANKS) | 10/31/08 | ||
22 71 00 |
AUTOMATIC ANIMAL WATER SYSTEMS | 11/26/08 | ||
22 72 00 |
DETERGENT TRANSFER SYSTEMS | 10/31/08 | ||
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING | ||||
23 00 00 |
AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS | 1/23/09 | ||
23 03 00 |
BASIC MECHANICAL MATERIALS AND METHODS | 10/31/08 | ||
23 05 48 |
VIBRATION AND SEISMIC CONTROLS FOR HVAC DUCTWORK, PIPING AND EQUIPMENT | 9/19/08 | ||
23 05 93.00 10 |
TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS | 10/31/08 | ||
23 07 00 |
THERMAL INSULATION FOR MECHANICAL SYSTEMS | 10/31/08 | ||
23 08 00 |
COMMISSIONING OF HEATING VENTILATING AND AIR CONDITIONING SYSTEMS | 10/31/08 | ||
23 25 00 |
CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS | 10/31/08 | ||
23 40 00.00 10 |
CHEMICAL, BIOLOGICAL, AND RADIOLOGICAL (CBR) AIR FILTRATION SYSTEM | 10/31/08 | ||
23 64 26 |
CHILLED, CHILLED-HOT, PROCESS AND CONDENSER WATER PIPING SYSTEMS | 12/5/08 | ||
23 65 00.00 10 |
COOLING TOWER | 9/19/08 | ||
23 70 03.00 10 |
HEATING AND UTILITIES SYSTEMS, CENTRAL STEAM | 12/5/08 | ||
23 81 23 |
COMPUTER ROOM AIR CONDITIONING UNITS | 10/31/08 | ||
DIVISION 25 INTEGRATED AUTOMATION | ||||
26 06 00 |
BUILDING MANAGEMENT SYSTEM (BMS) POINTS LIST | 1/23/09 | ||
25 08 00 |
COMMISSIONING OF INTEGRATED AUTOMATION SYSTEM | 10/31/08 | ||
25 10 00 |
BUILDING MANAGEMENT SYSTEM (BMS) | 1/23/09 | ||
25 10 01 |
BUILDING MANAGEMENT SYSTEM (BMS) -OPTION 15A (LNS Based LonWorks) | 9/19/08 | ||
25 10 02 |
BUILDING MANAGEMENT SYSTEM OPTION 15B (Non-LNS Based LonWorks/Non-Native BACnet) | 9/19/08 | ||
25 10 03 |
BUILDING MANAGEMENT SYSTEM (BMS) OPTION 15C (Native BACnet) | 12/5/08 | ||
25 30 00 |
BUILDING MANAGEMENT SYSTEM (BMS) FIELD EQUIPMENT | 12/15/08 | ||
25 50 00 |
ENVIRONMENTAL MONITORING SYSTEM | 9/19/08 | ||
25 90 00 |
BUILDING MANAGEMENT SYSTEM (BMS) SEQUENCE OF OPERATION | 1/23/09 | ||
DIVISION 26 ELECTRICAL | ||||
26 00 00 |
BASIC ELECTRICAL MATERIALS AND METHODS | 10/31/08 | ||
26 05 48.00 10 |
SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT | 9/19/08 | ||
26 06 00 |
COMMISSIONING OF ELECTRICAL SYSTEMS | 10/31/08 | ||
26 08 00.13 |
APPARATUS INSPECTION AND TESTING | 10/31/08 | ||
26 09 13 |
POWER MONITORING SYSTEM | 1/23/08 | ||
26 09 23 |
INTEGRATED LOW VOLTAGE LIGHTING CONTROL SYSTEM | 9/19/08 | ||
26 09 23.13 |
LIGHTING CONTROL DEVICES | 9/19/08 | ||
26 11 16 |
SECONDARY UNIT SUBSTATIONS | 10/31/08 | ||
26 20 00 |
INTERIOR DISTRIBUTION SYSTEM | 10/31/08 | ||
26 23 00 |
SWITCHBOARDS AND SWITCHGEAR | 1/23/09 | ||
26 28 00.00 10 |
MOTOR CONTROL CENTERS AND PANELBOARDS | 1/23/09 | ||
26 28 01.00 10 |
COORDINATED POWER SYSTEM PROTECTION | 1/23/09 | ||
26 29 23 |
VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS | 9/19/08 | ||
26 32 15.00 10 |
DIESEL-GENERATOR SET STATIONARY 100-2500 KW, WITH AUXILIARIES | 9/19/08 | ||
26 33 53 |
STATIC UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM | 9/19/08 | ||
26 36 00.00 10 |
AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH | 10/31/08 | ||
26 41 01.00 10 |
LIGHTING PROTECTION SYSTEM | 9/19/08 | ||
26 42 14.00 10 |
CATHOLIC PROTECTION SYSTEM (SACRIFICIAL ANODE) | 9/19/08 | ||
26 51 00 |
INTERIOR LIGHTING | 10/31/08 | ||
26 56 00 |
EXTERIOR LIGHT | 9/19/08 | ||
26 60 13 |
LOW-VOLTAGE MOTORS | 9/19/08 | ||
DIVISION 27-COMMUNICATIONS |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 45 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
27 05 28.36 |
CABLE TRAYS FOR COMMUNICATIONS SYSTEMS | 9/19/08 | ||
27 10 00 |
BUILDING TELECOMMUNICATIONS CABLING SYSTEM | 9/19/08 | ||
27 53 16.23 |
RADIO FREQUENCY SYSTEM (RFRS) | 11/26/08 | ||
27 54 00 |
COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS | 9/19/08 | ||
DIVISION 28 ELECTRONIC SAFETY AND SECURITY | ||||
28 08 00 |
COMMISSIONING OF FIRE ALARM AND MASS NOTIFICATION SYSTEMS | 9/19/08 | ||
28 20 01.00 10 |
ELECTRONIC SECURITY SYSTEM (FOUO) | 1/23/09 | ||
28 31 76 |
INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM | 1/23/09 | ||
DIVISION 31 EARTHWORK | ||||
31 00 00 |
EARTHWORK | 1/23/09 | ||
31 40 00 |
SHORING AND UNDERPINNING | 11/18/08 | ||
31 63 26 |
DRILLED PIERS (CAISSONS) | 1/23/09 | ||
DIVISION 32 EXTERIOR IMPROVEMENTS | ||||
32 05 33 |
LANDSCAPE ESTABLISHMENT | 9/19/08 | ||
32 11 10 |
PAVEMENT DRAINAGE LAYER (RDM) | 9/19/08 | ||
32 11 23 |
AGGREGATE BASE COURSE (DGA) | 9/19/08 | ||
32 12 17 |
BITUMINOUS PAVING MARYLAND (SUPERPAVE) | 9/19/08 | ||
32 12 23 |
CONCRETE GRID (GRASS) PAVERS | 1/23/09 | ||
32 16 13 |
CONCRETE SIDEWALKS AND CURBS AND GUTTERS | 9/19/08 | ||
32 16 15 |
CONCRETE BLOCK PAVEMENTS | 9/19/08 | ||
32 17 24.00 10 |
PAVEMENT MARKINGS | 9/19/08 | ||
32 31 13.00 |
CHAIN LINK FENCES AND GATES | 9/19/08 | ||
32 31 51 |
INTEGRATED BARRIER SYSTEMS (FOUO) | 9/19/08 | ||
32 92 19 |
SEEDING | 9/19/08 | ||
32 92 26 |
SPRIGGING | 9/19/08 | ||
32 93 00 |
EXTERIOR PLANTS | 9/19/08 | ||
DIVISION 33 UTILITIES | ||||
33 08 00 |
COMMISSIONING OF UTILITIES | 9/19/08 | ||
33 11 00 |
WATER DISTRIBUTION | 9/19/08 | ||
33 30 00 |
SANITARY SEWERS | 9/19/08 | ||
33 40 01 |
STORM DRAINAGE | 9/19/08 | ||
33 46 00 |
SUBDRAINAGE SYSTEMS | 1/23/09 | ||
33 60 01 |
VALVES, PIPING, AND EQUIPMENT IN VALVE MANHOLES | 9/19/08 | ||
33 61 00 |
PREFABRICATED UNDERGROUND HEATING/COOLING DISTRIBUTION SYSTEM | 9/19/08 | ||
33 61 13 |
PRE-ENGINEERED UNDERGROUND HEAT DISTRIBUTION SYSTEM | 9/19/08 | ||
33 70 02.00 10 |
ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND | 9/19/08 | ||
33 82 00 |
TELECOMMUNICATIONS OUTSIDE PLANT (OSP) | 9/19/08 | ||
DIVISION 44 MATERIAL PROCESSING AND HANDLING EQUIPMENT | ||||
41 22 03.13 |
MONORAILS WITH MANUAL HOIST | 9/19/08 | ||
41 22 03.19 |
MONORAILS WITH ELECTRIC POWERED HOISTS | 9/19/08 | ||
ADDENDUM NO. | ||||
ADDITIONAL DOCUMENTS | ||||
COMMISSION APPENDICES | ||||
TABLE OF CONTENTS | 1/23/09 | |||
APPENDIX A | ||||
DIVISION 03 CONCRETE | ||||
03 08 00A |
CVF INDEX | 9/19/08 | ||
03 08 00A |
HIGH CONTAINMENT CONCRETE CVF | 9/19/08 | ||
DIVISION 05 METALS |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 46 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
05 08 00A |
CVF INDEX | 9/19/08 | ||
05 08 00A |
SPECIAL METAL FABRICATION (DUNK TANK) CVF | 9/19/08 | ||
DIVISION 07-THERMAL AND MOISTURE PROTECTION | ||||
07 08 00A |
CVF INDEX | |||
07 08 00A |
MODIFIED BITUMINOUS MEMBRANE ROOFING CVF | 9/19/08 | ||
07 08 00A |
RUBBERIZED ASPHALT PROTECTED MEMBRANE ROOFING CVF | 9/19/08 | ||
DIVISION 08 OPENINGS | ||||
08 08 00A |
CVF INDEX | 9/19/08 | ||
08 08 00A |
ARP DOORS CVF | 9/19/08 | ||
08 08 00A |
ARP WINDOWS CVF | 9/19/08 | ||
08 08 00A |
GLAZED CURTAIN WALL CVF | 9/19/08 | ||
08 08 00A |
SKYLIGHT CVF | 9/19/08 | ||
08 08 00A |
STRUCTURAL GLASS CURTAIN WALL-CVF | 9/19/08 | ||
DIVISION 09 FINISHES | ||||
09 08 00A |
CVF INDEX | 9/19/08 | ||
09 08 00A |
RESINOUS FLOORING RES5 CVF | 9/19/08 | ||
09 08 00A |
RESINOUS FLOORING RES6 CVF | 9/19/08 | ||
09 08 00A |
SPECIAL COATINGS CVF | 9/19/08 | ||
DIVISION 11 EQUIPMENT | ||||
11 08 00A |
CVF INDEX | 10/31/08 | ||
11 08 00A |
BEDDING DISPENSER CVF | 9/19/08 | ||
11 08 00A |
BIOLOGICAL SAFETY CABINET CVF | 9/19/08 | ||
11 08 00A |
CLASS II BSC Z3420-CVF | 9/19/08 | ||
11 08 00A |
CLASS III BSC Z3432 IN 2SB112 AND 2SD112-CVF | 9/19/08 | ||
11 08 00A |
CLASS III BSC Z3432 IN 2SJ218-CVF | 9/19/08 | ||
11 08 00A |
CLASS III BSC Z3432 IN 4SJ220 AND 4SJ246-CVF | 9/19/08 | ||
11 08 00A |
CLASS III BSC Z3434-CVF | 9/19/08 | ||
11 08 00A |
DECON MISTING TUNNEL-CVF | 9/19/08 | ||
11 08 00A |
DEPYROGENATION OVEN-CVF | 9/19/08 | ||
11 08 00A |
DOWNDRAFT Z4504 | 9/19/08 | ||
11 08 00A |
ETO STERILIZER-CVF | 9/19/08 | ||
11 08 00A |
FUME HOOD-CVF | 9/19/08 | ||
11 08 00A |
GLASSWARE WASHER-CVF | 9/19/08 | ||
11 08 00A |
RACK WASHER-CVF | 9/19/08 | ||
11 08 00A |
STERILIZER Z3315 | 9/19/08 | ||
11 08 00A |
STERILIZER Z3320 | 9/19/08 | ||
11 08 00A |
STERILIZER Z3321 | 9/19/08 | ||
11 08 00A |
STERILIZER Z3335 | 9/19/08 | ||
11 08 00A |
STERILIZER Z3345 | 9/19/08 | ||
11 08 00A |
STERILIZER Z3350 BSL-2-CVF | 9/19/08 | ||
11 08 00A |
STERILIZER Z3350 BSL-3E & 4-CVF | 9/19/08 | ||
11 08 00A |
TISSUE DIGESTER-CVF | 9/19/08 | ||
11 08 00A |
TUNNEL WASHER-CVF | 9/19/08 | ||
11 08 00A |
VACUUM BEDDING AND DUST COLLECTION EQUIPMENT-CVF | 9/19/08 | ||
DIVISION 12 FURNISHINGS | ||||
12 08 00A |
CVF INDEX | 9/19/08 | ||
12 08 00A |
STAINLESS STEEL LAB CASEWORK | 9/19/08 | ||
DIVISION 13 SPECIAL CONDITIONS | ||||
13 06 00A |
CVF INDEX | 9/19/08 | ||
13 06 00A |
CONTROLLER ENVIRONMENTAL ROOM-CVF | 9/19/08 | ||
13 06 00A |
RADIATION SHIELDING-CVF | 9/19/08 | ||
13 06 00A |
RF SHIELDING-CVF | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 47 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
DIVISION 21 FIRE SUPPRESSION | ||||
21 08 00A |
CVF INDEX | 9/19/08 | ||
21 08 00A |
FIRE PUMP-CVF | 9/19/08 | ||
21 08 00A |
STANDPIPE AND SPRINKLER PIPING-CVF | 9/19/08 | ||
DIVISION 22 PLUMBING | ||||
22 08 00A |
CVF INDEX | 1/23/09 | ||
22 08 00A |
AIR COMPRESSOR-CVF | 10/31/08 | ||
22 08 00A |
ANIMAL WATERING SYSTEM-CVF | 10/31/08 | ||
22 08 00A |
BREATHING AIR SYSTEM-CVF | 10/31/08 | ||
22 08 00A |
BRINE MAKING SYSTEM-CVF | 9/19/08 | ||
22 08 00A |
CHEMICAL SHOWER-CVF | 10/31/08 | ||
22 08 00A |
CIRCULATION PUMPS HOT WATER RETURN-CVF | 9/19/08 | ||
22 08 00A |
CRYOGENIC BULK TANK-CVF | 10/31/08 | ||
22 08 00A |
DETERGENT TRANSFER SYSTEM-CVF | 9/19/08 | ||
22 08 00A |
DRAINAGE PIPING-CVF | 10/31/08 | ||
22 08 00A |
ELEVATOR SUMP PUMP-CVF | 9/19/08 | ||
22 08 00A |
LAB GAS DISTRIBUTION PIPING-CVF | 10/31/08 | ||
22 08 00A |
LN2 DISTRIBUTION PIPING-CVF | 9/19/08 | ||
22 08 00A |
PLUMBING FIXTURE-CVF | 10/31/08 | ||
22 08 00A |
PRESSURE BOOSTER PUMPS AND COLDWATER-CVF | 10/31/08 | ||
22 08 00A |
RO WATER PIPING SYSTEM-CVF | 10/31/08 | ||
22 08 00A |
RO WATER SKID-CVF | 9/19/08 | ||
22 08 00A |
SOLAR THERMAL HEATING EQUIPMENT-CVF | 9/19/08 | ||
22 08 00A |
VACUUM PUMP-CVF | 10/31/08 | ||
22 08 00A |
WASTEWATER LIFT STATION-CVF | 9/19/08 | ||
22 08 00A |
WATER DISTRIBUTION PIPING-CVF | 9/19/08 | ||
22 08 00A |
WATER HEATER-CVF | 9/19/08 | ||
22 08 00A |
WATER SOFTENER-CVF | 9/19/08 | ||
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING | ||||
23 08 00A |
CVF INDEX-CVF | 10/31/08 | ||
23 08 00A |
AIR CURTAIN-CVF | 9/19/08 | ||
23 08 00A |
AIR HANDLING UNIT-CVF | 10/31/08 | ||
23 08 00A |
BSL-4-HEPA-CVF | 10/31/08 | ||
23 08 00A |
CLEAN STEAM GENERATOR-CVF | 9/19/08 | ||
23 08 00A |
CONDENSATE RETURN UNIT-CVF | 9/19/08 | ||
23 08 00A |
COOLING TOWER-CVF | 9/19/08 | ||
23 08 00A |
CW MAKEUP-CVF | 9/19/08 | ||
23 08 00A |
DUCTWORK-CVF | 9/19/08 | ||
23 08 00A |
EXPANSION TANK-CVF | 9/19/08 | ||
23 08 00A |
FAN COIL UNIT-CVF | 9/19/08 | ||
23 08 00A |
FAN-CVF | 9/19/08 | ||
23 08 00A |
FILTERS-CVF | 9/19/08 | ||
23 08 00A |
GLYCOL FILL-CVF | 9/19/08 | ||
23 08 00A |
HEAT EXCHANGER-CVF | 9/19/08 | ||
23 08 00A |
HEAT RECOVERY UNIT-CVF | 9/19/08 | ||
23 08 00A |
HUMIDIFIER-CVF | 9/19/08 | ||
23 08 00A |
PIPING-CVF | 9/19/08 | ||
23 08 00A |
REHEAT COIL-CVF | 9/19/08 | ||
23 08 00A |
STEAM FLASH TANK-CVF | 9/19/08 | ||
23 08 00A |
STEAM POWERED PUMP-CVF | 9/19/08 | ||
23 08 00A |
STEAM PRV-CVF | 9/19/08 | ||
23 08 00A |
STEAM TRAP-CVF | 9/19/08 | ||
23 08 00A |
TERMINAL UNIT-CVF | 9/19/08 | ||
DIVISION 25 INTEGRATED AUTOMATION | ||||
25 08 00A |
CVF INDEX | 9/19/08 | ||
25 08 00A |
COMMUNICATION GATEWAYS-CVF | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 48 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
25 08 00A |
COMPRESSED AIR PRV STATION-CVF | 9/19/08 | ||
25 08 00A |
COMPUTER EQUIPMENT-CVF | 9/19/08 | ||
25 08 00A |
CONTROL ENCLOSURES-CVF | 9/19/08 | ||
25 08 00A |
EMS GLP PANELS-CVF | 9/19/08 | ||
25 08 00A |
FIREMANS OVERRIDE PANEL-CVF | 9/19/08 | ||
25 08 00A |
INSTRUMENTATION-CVF | 9/19/08 | ||
25 08 00A |
IT JACKS FOR SPACE MONITORING-CVF | 9/19/08 | ||
25 08 00A |
LAPTOP-CVF | 9/19/08 | ||
25 08 00A |
LIGHTING CONTROL PANEL-CVF | 9/19/08 | ||
25 08 00A |
PRINTERS-CVF | 9/19/08 | ||
25 08 00A |
ROOM PRESSURE MONITORING-CVF | 9/19/08 | ||
DIVISION 26 ELECTRICAL | ||||
26 08 00A |
CVF INDEX | 11/26/08 | ||
26 08 00A |
15kV DUPLEX SWITCHES-CVF | 9/19/08 | ||
26 08 00A |
15kV FEEDER-CVF | 9/19/08 | ||
26 08 00A |
15kV SWITCHES-CVF | 9/19/08 | ||
26 08 00A |
AUTO TRANSFER SWITCHES-CVF | 9/19/08 | ||
26 08 00A |
BUSWAY-CVF | 9/19/08 | ||
26 08 00A |
CAST COIL TRANSFORMER-CVF | 9/19/08 | ||
26 08 00A |
CATHODIC PROTECTION-CVF | 9/19/08 | ||
26 08 00A |
DISCONNECT-CVF | 9/19/08 | ||
26 08 00A |
DISTRIBUTION TRANSFORMERS-CVF | 9/19/08 | ||
26 08 00A |
GENERATOR-CVF | 9/19/08 | ||
26 08 00A |
GROUNDING AND LIGHTING PROTECTION-CVF | 9/19/08 | ||
26 08 00A |
LOW VOLTAGE DRAWOUT SWITCHGEAR-CVF | 9/19/08 | ||
26 08 00A |
MANUAL MOTOR STARTER-CVF | 9/19/08 | ||
26 08 00A |
MASTER CONTROL UNIT-CVF | 10/31/08 | ||
26 08 00A |
MCC-MOTOR CONTROL UNIT-CVF | 10/31/08 | ||
26 08 00A |
METER-POWER MONITORING-CVF | 9/19/08 | ||
26 08 00A |
MOTOR STARTER-CVF | 9/19/08 | ||
26 08 00A |
PANELBOARDS-CVF | 9/19/08 | ||
26 08 00A |
POWER DISTRIBUTION UNIT (PDU)-CVF | 11/26/08 | ||
26 08 00A |
POWER FACTOR CORRECTION CAPACITORS-CVF | 11/26/08 | ||
26 08 00A |
ROOM LEVEL-CVF | 11/26/08 | ||
26 08 00A |
SWITCHBOARDS-CVF | 9/19/08 | ||
26 08 00A |
UPS UNINTERRUPTABLE POWER SOURCE-CVF | 1/23/09 | ||
26 08 00A |
VFD-VARIABLE FREQUENCY DRIVES-CVF | |||
DIVISION 33 UTILITIES | ||||
33 08 00A |
CVF INDEX | 10/31/08 | ||
33 08 00A |
SITE CHILLED WATER PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE DOMESTIC WATER PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE FIRE WATER PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE LAB WASTE PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE PUMPED CONDENSATE PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE SANITARY PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE STEAM PIPING-CVF | 10/31/08 | ||
33 08 00A |
SITE STORM DRAIN PIPING-CVF | 10/31/08 | ||
33 08 00A |
TUNNEL BIO-WASTE PIPING-CVF | 10/31/08 | ||
APPENDIX B | ||||
DIVISION 08 OPENINGS | ||||
08 08 00B |
ST INDEX | 9/19/08 | ||
08 08 00B |
APR BSL-3E DECON ROOM DOOR-ST | 9/19/08 | ||
08 08 00B |
APR BSL-3E IMAGING ROOM DOOR -ST | 9/19/08 | ||
08 08 00B |
APR BSL-4 AIRLOCK WITH CHEMICAL SHOWER DOOR-ST | 9/19/08 | ||
08 08 00B |
APR BSL-4 AIRLOCK WITHOUT CHEMICAL SHOWER DOOR ST | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 49 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
08 08 00B |
APR BSL-4 PASSAGE DOOR-ST | 9/19/08 | ||
08 08 00B |
APR CHEMICAL SHOWER DOOR-ST | 9/19/08 | ||
DIVISION 11 EQUIPMENT | ||||
11 08 00B |
ST INDEX | 9/19/08 | ||
11 08 00B |
STERILIZER ST | 9/19/08 | ||
11 08 00B |
TISSUE DIGESTER ST | 9/19/08 | ||
DIVISION 21 FIRE SUPPRESSION | ||||
21 08 00B |
ST INDEX | 9/19/08 | ||
21 08 00B |
FIRE PROTECTION SYSTEM ST | 9/19/08 | ||
DIVISION 22 PLUMBING | ||||
22 08 00B |
ST INDEX | 1/23/09 | ||
22 08 00B |
BREATHING AIR SYSTEM-ST | 10/31/08 | ||
22 08 00B |
BRINE SYSTEM -ST | 10/31/08 | ||
22 08 00B |
COMPRESSED AIR SYSTEM-ST | 1/23/09 | ||
22 08 00B |
CHEMICAL SHOWER SKID-ST | 1/23/09 | ||
22 08 00B |
CHEMICAL SHOWER TRAINING ROOM-ST | 10/31/08 | ||
22 08 00B |
DETERGENT SYSTER-ST | 10/31/08 | ||
22 08 00B |
DOMESTIC HOT WATER SYSTEM-ST | 10/31/08 | ||
22 08 00B |
LAB COLD WATER SYSTEM-ST | 10/31/08 | ||
22 08 00B |
LAB GAS SYSTEM-ST | 9/19/08 | ||
22 08 00B |
LAB HOT WATER SYSTEM-ST | 10/31/08 | ||
22 08 00B |
RO WATER SYSTEM-ST | 1/23/09 | ||
22 08 00B |
SOLAR THERMAL HEATING SYSTEM-ST | 1/23/09 | ||
22 08 00B |
TEMPERED WATER SYSTEM-ST | 10/31/08 | ||
22 08 00B |
VACUUM SYSTEM-ST | 1/23/09 | ||
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING | ||||
23 08 008B |
ST INDEX | 1/23/09 | ||
23 08 008B |
AHU (A)BSL-3E-ST | 9/19/08 | ||
23 08 008B |
AHU ABSL-2 ANIMAL & LAB-ST | 9/19/08 | ||
23 08 008B |
AHU ADMIN/CLINIC-ST | 9/19/08 | ||
23 08 008B |
AHU ADMIN/CLINIC (SHELL)-ST | 9/19/08 | ||
23 08 008B |
AHU ADMIN/CLINIC (SC)-ST | 9/19/08 | ||
23 08 008B |
AHU ADMIN WORK ROOM-ST | 9/19/08 | ||
23 08 008B |
AHU ATRIUM ADMIN-ST | 9/19/08 | ||
23 08 008B |
AHU BARRIER-ST | 9/19/08 | ||
23 08 008B |
AHU BSL-2 HEPA-ST | 9/19/08 | ||
23 08 008B |
AHU BSL-2 LAB FUME HOOD-ST | 9/19/08 | ||
23 08 008B |
AHU BSL-2 LAB/OFFICE-ST | 9/19/08 | ||
23 08 008B |
AHU BSL-2 LAB-ST | 9/19/08 | ||
23 08 008B |
AHU BSL-4-ST | 10/31/08 | ||
23 08 008B |
AHU LOGISTIC/OFFICES-ST | 9/19/08 | ||
23 08 008B |
AHU NONCONTAINMENT CORRIDOR-ST | 9/19/08 | ||
23 08 008B |
BSL-4 AEROBIOLOGY-ST | 1/23/08 | ||
23 08 008B |
CHILLED WATER-ST | 9/19/08 | ||
23 08 008B |
COOLING WATER-ST | 9/19/08 | ||
23 08 008B |
EF ABSL-2-ST | 9/19/08 | ||
23 08 008B |
EF ABSL-2 CAGEWASH-ST | 9/19/08 | ||
23 08 008B |
EF ABSL-2 LAB-ST | 9/19/08 | ||
23 08 008B |
EF ABSL-3E AEROBIOLOGY-ST | 9/19/08 | ||
23 08 008B |
HRU-EF (A)BSL-3E-ST | 1/23/09 | ||
23 08 008B |
HRU-EF ABSL-3E AEROBIOLOGY-ST | 9/19/08 | ||
23 08 008B |
HRU-EF ABSL-3E HS-ST | 9/19/08 | ||
23 08 008B |
HRU-EF NONCONTAINMENT CORR-ST | 9/19/08 | ||
23 08 008B |
PREHEAT GLYCOL-ST | 9/19/08 | ||
23 08 008B |
PREHEAT HEAT RECOVERY GLYCOL-ST | 9/19/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 50 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
23 08 008B |
REHEAT ST | 9/19/08 | ||
23 08 008B |
STEAM SYSTEM-ST | 9/19/08 | ||
23 08 008B |
TERMINAL UNITS-ST | 9/19/08 | ||
23 08 008B |
TRIM HUMIDIFIERS-ST | 9/19/08 | ||
DIVISION 25 INTEGRATED AUTOMATION | ||||
25 08 00B |
ST INDEX | 10/31/08 | ||
25 08 00B |
ALARM (A)BSL-3E-ST | 9/19/08 | ||
25 08 00B |
ALARM ABSL-2-ST | 9/19/08 | ||
25 08 00B |
ALARM BSL-2-ST | 9/19/08 | ||
25 08 00B |
ALARM BSL-4-ST | 10/31/08 | ||
25 08 00B |
ALARM BSL-4 AEROBIOLOGY-ST | 10/31/08 | ||
25 08 00B |
ALARM EMS-ST | 9/19/08 | ||
25 08 00B |
ALARM FOP-ST | 9/19/08 | ||
25 08 00B |
ALARM LAB/OFFICE-ST | 9/19/08 | ||
25 08 00B |
GRAPHICS BMS-ST | 10/31/08 | ||
25 08 00B |
GRAPHICS EMS-ST | 9/19/08 | ||
25 08 00B |
POINT 3RD PARTY MONITORING-ST | 9/19/08 | ||
25 08 00B |
POINT ADMINISTRATION-ST | 9/19/08 | ||
25 08 00B |
POINT AHU-A()BSL-2-ST | 9/19/08 | ||
25 08 00B |
POINT AHU-BSL-2-ST | 9/19/08 | ||
25 08 00B |
POINT AHU-BSL-4-ST | 10/31/08 | ||
25 08 00B |
POINT AHU-BSL-4 AEROBIOLOGY-ST | 10/31/08 | ||
25 08 00B |
POINT AHU-HRU-(A) BSL-3E-ST | 10/31/08 | ||
25 08 00B |
POINT EMS-ST | 9/19/08 | ||
25 08 00B |
POINT FIRE ALARM SYSTEM-ST | 9/19/08 | ||
25 08 00B |
POINT LAB/OFFICE BSL-2-ST | 9/19/08 | ||
25 08 00B |
POINT MECHANICAL SYSTEM-ST | 9/19/08 | ||
25 08 00B |
POINT ROOMS ABSL-2-ST | 9/19/08 | ||
25 08 00B |
POINT ROOMS BSL2-ST | 9/19/08 | ||
25 08 00B |
POINT ROOMS BSL-4-ST | 10/31/08 | ||
25 08 00B |
POINT ROOMS BSL-4 AEROBIOLOGY-ST | 10/31/08 | ||
25 08 00B |
POINT ROOMS LAB/OFFICE-ST | 10/31/08 | ||
25 08 00B |
POINT SECURITY SYSTEM-ST | 9/19/08 | ||
25 08 00B |
SERVER BACKUP FUNCTIONS-ST | 9/19/08 | ||
25 08 00B |
SERVER DDC PANEL COMMUNICATION-ST | 9/19/08 | ||
25 08 00B |
SERVER OC SECURITY-ST | 9/19/08 | ||
25 08 00B |
USER SECURITY LEVEL-ST | 9/19/08 | ||
DIVISION 26 ELECTRICAL | ||||
26 08 00B |
ST INDEX | 11/26/08 | ||
26 08 00B |
EMERGENCY POWER SYSTEM-ST | 9/19/08 | ||
26 08 00B |
POWER DISTRIBUTION UNIT (PDU)-ST | 11/26/08 | ||
26 08 00B |
POWER FACTOR CORRECTION CAPACITORS-ST | 11/26/08 | ||
26 08 00B |
POWER MONITORING-ST | 9/19/08 | ||
26 08 00B |
SUB AUTO TRANSFER-ST | 1/23/09 | ||
26 08 00B |
UPS-ST | 9/19/08 | ||
DIVISION 28 SAFETY AND SECURITY | ||||
28 08 00B |
ST INDEX | 9/19/08 | ||
28 08 00B |
(FA & MNS) FIRE ALARM & MASS NOTIFICATION SYSTEM -ST | 1/23/09 | ||
APPENDIX C | ||||
DIVISION 22 PLUMBING | ||||
22 08 00C |
1ST INDEX | 11/26/08 | ||
22 08 00C |
DETERGENT TRANSFER SYSTEM 1ST | 9/19/08 | ||
DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING | ||||
23 08 00C |
1ST INDEX | 10/31/08 |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 51 of 52 |
DESCRIPTION | ||||
TITLE | DRAWING INDEX | DATE | ||
23 08 00C |
ABSL-2 AIR-1ST | 9/19/08 | ||
23 08 00C |
ADMIN CLINIC AIR-1ST | 9/19/08 | ||
23 08 00C |
ADMIN WORK ROOM-1ST | 9/19/08 | ||
23 08 00C |
ATRIUM AIR-1ST | 1/23/09 | ||
23 08 00C |
ATRIUM SMOKE CONTROL-1ST | 9/19/08 | ||
23 08 00C |
BARRIER HOLDING AREA-1ST | 9/19/08 | ||
23 08 00C |
BSL-2 LAB-1ST | 9/19/08 | ||
23 08 00C |
BSL-3E LAB-1ST | 9/19/08 | ||
23 08 00C |
BSL-4 AEROBIOLOGY-1ST | 10/31/08 | ||
23 08 00C |
BSL-4 AREA-1ST | 10/31/08 | ||
23 08 00C |
EMERGENCY SHUTDOWN-1ST | 9/19/08 | ||
23 08 00C |
LAB OFFICE AIR-1ST | 9/19/08 | ||
23 08 00C |
LOGISTICS OFFICE AIR-1ST | 9/19/08 | ||
23 08 00C |
NON-CONTAINMENT CORRIDOR-1ST | 9/19/08 | ||
23 08 00C |
ROOM LEVEL-1ST | 10/31/08 | ||
DIVISION 25 INTEGRATED AUTOMATION | ||||
25 08 00C |
1ST INDEX | 9/19/08 | ||
25 08 00C |
AIR COMPRESSOR -1ST | 10/31/08 | ||
25 08 00C |
EMS ENVIRONMENTAL MONITORING SYSTEM INTEGRATION-1ST | 9/19/08 | ||
25 08 00C |
ENERGY MONITORING-1ST | 9/19/08 | ||
25 08 00C |
LIGHTING INTEGRATION-1ST | 9/19/08 | ||
25 08 00C |
SPEED OF RESPONSE-1ST | 10/31/08 | ||
25 08 00C |
STEAM PRV-1ST | 9/19/08 | ||
25 08 00C |
TIME SYNC-1ST | 9/19/08 | ||
25 08 00C |
VFD VARIABLE FREQUENCY DRIVES-1ST | 9/19/08 | ||
DIVISION 26 ELECTRICAL | ||||
26 08 00C |
1ST INDEX | 1/23/09 | ||
26 08 00C |
EMERGENCY POWER SYSTEM-1ST | 1/23/09 | ||
26 08 00C |
POWER MONITORING SYSTEM-1ST | 1/23/09 | ||
AMENDMENTS | ||||
AMENDMENT 0001 | 9/8/08 | |||
AMENDMENT 0002 | 9/18/08 | |||
AMENDMENT 0003 | 10/22/08 | |||
AMENDMENT 0004 | 10/31/08 | |||
AMENDMENT 0005 | 11/18/08 | |||
AMENDMENT 0006 | 11/25/08 | |||
AMENDMENT 0007 | 11/26/08 | |||
AMENDMENT 0008 | 12/5/08 | |||
AMENDMENT 0009 | 12/9/08 | |||
AMENDMENT 0010 | 12/15/08 | |||
AMENDMENT 0011 | 12/16/08 | |||
AMENDMENT 0012 | 1/23/09 |
* | Document re-issued in Amendment with date that does not match issue date. |
Exhibit A-1, Contract Documents, USAMRIID, Ft Detrick MD | 52 of 52 |
ATTEST: |
||||||
(Principal) | (Seal) | |||||
By |
||||||
(Name and Title) |
||||||
(Signature) | ||||||
WITNESS: |
||||||
(Principal) | (Seal) | |||||
By |
||||||
(Name and Title) |
||||||
(Signature) | ||||||
ATTEST: |
||||||
(Principal) | (Seal) | |||||
By |
||||||
(Name and Title) |
||||||
(Signature) | ||||||
WITNESS: |
||||||
(Principal) | (Seal) | |||||
By |
||||||
(Name and Title) |
||||||
(Signature) | ||||||
1.0 | Definitions (for purposes of this Exhibit C only) |
Certificate of Insurance: | Evidence of the insurance coverage afforded under the CCIP. | |||
Contract: | The written agreement between Manhattan Torcon A Joint Venture and Subcontractor describing the Work, Contract Terms and Conditions, or a portion thereof. Also includes a written agreement between a subcontractor and any lower tier subcontractor. | |||
General Contractor: | Manhattan Torcon A Joint Venture | |||
Contractor Controlled Insurance Program (CCIP): |
A coordinated insurance program providing certain coverages, as defined herein, for the General Contractor and Enrolled Subcontractors, along with their Eligible Employees, performing Work at the Project Site. | |||
Eligible Employees: | Employees of enrolled Subcontractors who are not excluded from the CCIP under the Excluded Parties definition. | |||
Enrolled Parties: | Those Subcontractors that have submitted all necessary enrollment information and been accepted into the CCIP as evidenced by the issuance of a Certificate of Insurance. | |||
Excluded Parties: | No insurance coverage provided by General Contractor under the CCIP shall extend to the activities or products of the following: |
(1) | Any person or organization that fabricates or manufactures products, materials or supplies away from the project site(s); | |
(2) | Hazardous materials remediation, removal, or transportation companies and their consultants; | |
(3) | Any architect, engineer or surveyor and their consultants except when approved by General Contractor; |
-2-
(4) | Truckers, material dealers, vendors, suppliers, and Contractor/operators (independent contractors) whose operations or employees are engaged solely in the loading, hauling, unloading, or some combination of the same, of material, supplies or equipment to or from the Project Site, or their employees; | |
(5) | Any employee of an enrolled Subcontractor, who does not work or generate payroll at the Project Site; | |
(6) | Any employees of an enrolled Subcontractor who occasionally visits the Project Site to make deliveries, pick-up supplies or personnel, to perform supervisory or progress inspections, or for any other reason; | |
(7) | Any Day Labor Employees (labor service employees whose coverage is provided by their employer); or | |
(8) | Any other person or entity specifically excluded by General Contractor, in its sole discretion, from participation as Enrolled Parties. |
The CCIP, CCIP Policies and CCIP Coverages shall not apply to Excluded Parties, even if erroneously enrolled in the CCIP. Excluded Parties and parties no longer enrolled or covered by the CCIP or erroneously enrolled in the CCIP shall obtain and maintain, and require by contract that each of their lower-tier Subcontractors obtain and maintain, the insurance coverages as required by Paragraph 11.1.4, below, and as required by the CCIP Manual. | ||||
Insured: | The General Contractor, and Enrolled Subcontractors and their Eligible Employees and any other party named in the insurance policies. | |||
Insurers: | Those Insurance Companies providing the required coverages that are included in the CCIP. The Insurers will be identified in the Project Insurance Manual. | |||
Deductive Option Bid: | Obligation of any enrolled party to delete insurance costs for coverages provided by the CCIP from its bid and all change orders. Such costs will then be shown as |
-3-
a separate Deductive Option. All deductions are subject to verification by CCIP Administrator through the providing of contractors rate and declaration pages from their insurance policies. | ||||
CCIP Administrator: | TBD | |||
Off-Site Work: | Work performed away from the Project Site. | |||
Payroll: | Any requests for payroll information for the CCIP refer to Unburdened Straight Time Payroll per Workers Compensation Class Code. | |||
Project: | USAMRIID Ft. Detrick, MD | |||
Project Site: | Project Site shall mean those areas designated in writing by the General Contractor in a Contract document for performance of the Work and such additional areas as may be designated in writing for Contractors use in performance of the Work. Subject to CCIP Insurers written approval, the term Project Site shall also include: (1) field office sites, (2) property used for bonded storage of material for the Project approved by the General Contractor (3) staging areas dedicated to the Project, and (4) areas where activities incidental to the Project are being performed by General Contractor or Subcontractors covered by the workers compensation policy included in the CCIP, but excluding any permanent locations of General Contractor or such covered Subcontractors. | |||
Subcontract: | The written agreement between General Contractor and Subcontractor, or between Subcontractor and a lower tier Subcontractor, describing the Work, Subcontract Terms and Conditions, or a portion thereof. | |||
Subcontractor: | Includes those persons, firms, joint venture entities, corporations, or other parties that enter into a Subcontract with General Contractor to perform Work at the Project Site and any of these Subcontractors lower-tier subcontractors. | |||
Work: | Operations, as fully described in the Contract and Subcontract, performed at the Project Site. |
-4-
2.0 | General Information |
2.1 | General Contractor may arrange for this Project to be insured under a CCIP. It is General Contractors intention to provide Workers Compensation, Employers Liability, General Liability, and Excess Liability as outlined herein and defined by the individual policies for the time period from the start of Work through completion and final acceptance by General Contractor, except as otherwise provided herein. The insurance limits of liability, as specified in Paragraph 3.0: lnsurance Provided by General Contractor under the CCIP, are for any Contracts that General Contractor elects to include in this CCIP. | ||
2.2 | The CCIP will provide certain insurance coverages for the General Contractor, and enrolled subcontractors, along with their Eligible Employees performing Work at the Project Site. Off-site operations shall be covered only if all operations at such site are identified and solely dedicated to the Project. It shall be the responsibility of the General Contractor and Subcontractors to notify the CCIP Administrator, in writing, to request coverage for specified off-site operations. Coverage is not provided at the site unless confirmed in writing by the CCIP Administrator. | ||
2.3 | All insurance underwriting, payroll, rating or loss history information requested by General Contractor or the CCIP Administrator shall be provided by the Subcontractor within five (5) working days of the request. Subcontractor agrees (and will require each lower-tier subcontractor to agree) that General Contractor, General Contractors insurer or General Contractors representative may audit the Subcontractors and the records of lower-tier subcontractors to confirm the accuracy of all insurance information provided, including, without limitation, any such information that may have any effect on insurance resulting from changes in the Work. At all times during performance of the Contract and Subcontracts, the Subcontractor and lower-tier subcontractors shall cooperate with General Contractor, CCIP Administrator and CCIP insurers. | ||
2.4 | Participation in the CCIP is mandatory but not automatic. When the Subcontractors and lower-tier subcontractors are properly enrolled in the CCIP, the CCIP Administrator will issue or have issued to the Subcontractor and lower-tier subcontractors, prior to their commencing Work on the Project Site, a Certificate of Insurance evidencing the coverages arranged by the General Contractor. | ||
2.5 | This is an Deductive Option Bid. Subcontractor will exclude the cost of CCIP coverages from their cost of work and ensure that each lower-tier subcontractor exclude the costs of CCIP coverages from their bids or proposals. However, the cost of insurance removed from each bid will be listed as a separate Deduct Option to the bid. The Costs of CCIP Coverages is defined as the amount of Subcontractors and eligible lower-tier subcontractors reduction in Insurance costs due to the CCIP Program. The calculation of these costs will be determined using the CCIP Administrators enrollment Forms 1, 2 and 3 found in the Project |
-5-
Insurance Manual. The Costs of CCIP Coverages includes reductions in insurance premiums, all relevant taxes and assessments, markup on insurance premiums, and losses retained through large deductibles or self-insurance retentions, or self-funded other programs. Change orders will also exclude the Cost of CCIP Coverages. | |||
2.6 | General Contractor will pay the insurance premiums for the CCIP coverages. The General Contractor is responsible for all adjustments to the premiums and will be the sole beneficiary of all dividends, retroactive adjustments, return premiums, and any other monies due through audits or otherwise. The Subcontractor assigns to the General Contractor the right to receive all such adjustments, and will require that each lower-tier subcontractor assign to General Contractor all such adjustments. | ||
2.7 | General Contractor reserves the right to exclude any Subcontractor or lower-tier subcontractor from the CCIP, prior to or after enrollment by the Subcontractor into the CCIP. If Contractor elects to exclude a Subcontractor from the CCIP, or elects not to use a CCIP on this project, the Subcontractor will be responsible for ensuring the insurance coverages outlined in the Subcontract Agreement are provided to the General Contractor before the Subcontractor can begin or resume work on the Project. | ||
2.8 | As soon as practicable, a CCIP Insurance Manual will be sent to the enrolled Subcontractors and any lower-tier subcontractors, and will become a part of the Contract with Subcontractor. The CCIP Insurance Manual will contain the administrative and claim reporting procedures. Subcontractor agrees to and will require that its lower-tier subcontractors also cooperate with the CCIP Administrator in providing all information as required in the CCIP Insurance Manual. | ||
2.9 | Notwithstanding the CCIP, the Subcontractor shall initiate, maintain and supervise all safety precautions and programs in connection with the Work. Subcontractor is solely responsible, at no adjustment to the contract sum payable or contract time, for initiating, maintaining, and supervising all safety precautions and programs relating to the conduct of Work, including, without limitation, any safety programs or procedures that are required by any applicable state or federal laws, rules or regulations, or by the terms of the CCIP Insurance Manual. | ||
2.10 | Subcontractor will cooperate fully with the CCIP Administrator and all CCIP Insurers with regard to enrollment, provision of required information and compliance with reasonable safety suggestions. Subcontractor and their lower-tier subcontractors shall assist and cooperate in every manner possible in connection with the adjustment of all claims arising out of their operations conducted in connection with the Work and shall cooperate with General Contractor, CCIP lnsurers and CCIP Administrator with the adjustment, settlement, mediation, arbitration or litigation of all said claims, including, without limitation, providing light or modified duty for injured workers, |
-6-
appearances in mediation, arbitration or court proceedings and/or participating in settlement meetings, as may be required. |
3.0 | Insurance Provided by GENERAL CONTRACTOR under the CCIP: |
3.1 | Unless otherwise provided herein, prior to commencement of the Work. General Contractor, at its sole option and expense, shall secure and maintain at all times during the performance of this Contract the insurance specified in Subparagraphs 3.2.1, 3.2.2, 3.2.3, and 3.2.4 below, with the General Contractor, its Subcontractors and such other persons or interests General Contractor may designate in connection with the performance of the Work as insured parties and with limits not less than those specified below for each coverage. | ||
3.2 | Unless otherwise provided herein, General Contractor will furnish the following insurance coverages as set forth in Subparagraphs 3.2.1, 3.2.2, 3.2.3, and 3.2.4 for the benefit of all Enrolled Subcontractors, lower-tier subcontractors and their Eligible Employees performing Work at the Project Site. |
3.2.1 | Workers Compensation & Employers Liability: |
Coverage: | Statutory limits required by the Workers Compensation | |||
Laws of the State of Maryland: | ||||
Part One:
|
Workers Compensation: | Statutory Limits | ||
Part Two:
|
Employers Liability: | |||
Bodily Injury by Accident: | $1,000,000 each accident | |||
Bodily Injury by Disease: | $1,000,000 each employee | |||
Bodily Injury by Disease: | $1,000,000 policy limit |
The premium and losses of each participant in the CCIP will be filed with the appropriate rating bureau by the Insurer. Experience modifiers of the CCIP participant could be affected, either positively or negatively, by their loss experience while performing Work under this Contract. Insurance coverage will cease for any employee when he or she leaves the Project Site either to perform other Work not covered by this Contract, or for employee personal time. |
3.2.2 | General Liability (excluding Automobile Liability and Professional Liability): | ||
Coverage: Third party personal injury, bodily injury and property damage liability |
Limits of Liability: | All Insureds Combined: | |||
General Aggregate |
$ | 4,000,000 | ||
Products/Completed Operations Aggregate |
$ | 4,000,000 | ||
Personal/Advertising Injury Aggregate |
$ | 2,000,000 | ||
Each Occurrence Limit |
$ | 2,000,000 |
-7-
Coverage under this policy includes, but is not limited to, the following: |
Coverage exclusions include, but are not limited to the following: |
This is a summary of coverage only. The CCIP Insurance policies will be made available to all enrolled Subcontractors upon request. Each Subcontractor should review the CCIP policies with its insurance and/or legal advisors. |
(a) | The CCIP coverages are limited solely to Work performed at the Project Site. As such, products/completed operations coverage provided under the Commercial General Liability and the Excess Liability do not apply to any insured party, Subcontractor, vendor, supplier, material dealer, or other product or material manufactured, assembled, or otherwise worked upon while away from the Project Site. | ||
(b) | This insurance will include a maximum of ten (10) years products & completed operations extension, beyond Substantial Completion of the project with a single, non-reinstated aggregate limit. | ||
3.2.4 | Excess/Umbrella Liability Insurance: | ||
Coverage: Written on a strict following form basis over the primary Excess/Umbrella policy. |
Minimum Limits of Liability: | All Insureds Combined: | |||
Combined Single Limit |
$ | 50,000,000 | ||
General Aggregate |
$ | 50,000,000 | ||
Products/Completed Operations Aggregate |
$50,000,000 for 10-years |
-8-
3.3 | General Contractor assumes no obligations to provide insurance other than that evidenced by the policies referred to in Paragraph 3.0. General Contractor, however, reserves the right to furnish insurance coverage of various types and limits provided that such coverage shall not be less than that specified above and the costs of such insurance shall be paid by General Contractor. |
4.0 | Alternative Insurance |
4.1 | In the event General Contractor for any reason is either unable to furnish or after commencement of Work elects not to furnish or to continue to furnish the insurance as specified in Subparagraphs 3.2.1, 3.2.2, 3.23 and following written notice from General Contractor, Subcontractor and lower-tier subcontractors shall secure and maintain at General Contractors cost, not to exceed the lesser of: (1) Sub-contractors actual net cost for the insurance coverage, or (2) the insurance cost identified in the Subcontractors Deductive Option Bid. | ||
4.2 | In the event the Subcontractor has been required to secure insurance specified in the Contract which was to have been provided by General Contractor under the CCIP, General Contractor is no longer obligated to furnish that part of the insurance specified in Subparagraphs 3.2.1, 32.2, 3.23 above. All insurance secured by the Subcontractor pursuant to General Contractors requirements under the provisions of the Contract shall be through policies subject to General Contractors approval. |
5.0 | Required Subcontractor Insurance Coverages |
5.1 | Insurance provided to the Subcontractors and lower-tier subcontractors under CCIP does not cover their automobiles, tools and equipment. The CCIP also does not cover Workers Compensation claims or Commercial General Liability claims arising from Off-Site Work. Off-Site Work as used in this document means Work performed under the Contract that is not performed at the designed Project Site. The CCIP does not cover Professional Liability claims or Pollution Liability claims arising from Work or services performed under contract at or from the designated Project Site. At their own expense, the Subcontractors and lower-tier subcontractors must carry the following minimum coverages and limits: |
5.1.1 | Commercial Automobile Liability Insurance for contract work both occurring on-site and off-site limits of liability not less than: |
This insurance must apply to all owned, leased, non-owned or hired vehicles to be used in the performance of work. Such insurance shall allow Subcontractor to |
-9-
waive subrogation against the General Contractor and/or its representatives prior to loss or shall include a waiver of the insurers right of subrogation. |
5.1.2 | Off-Site Workers Compensation Insurance, including Employers Liability with minimum limits of |
Coverage to protect Subcontractor from and against all claims arising from performance of Work outside the Project Site under the Contract. Such insurance (where permissible by law) shall waive subrogation against General Contractor. |
5.1.3 | Off-Site Commercial General Liability Insurance for Contract operations not physically occurring within the Project Site with a limit of liability not less than: |
Such policy shall include coverage for contractual liability assumed under the Contract, contractors protective liability, and explosion, collapse and underground property damage hazards. The Policy Form should be CG 00 01 12 04 or equivalent. |
5.1.4 | Off-Site Umbrella Liability Insurance for Contract operations not physically occurring within the Project Site with limits of liability not less than: |
5.2 | The Subcontractor or lower-tier subcontractor shall provide and maintain the following insurance of the type and in limits as set forth by General Contractors risk management should construction operations warrant such coverage. |
5.2.1 | Aircraft/Aviation Liability: | ||
Should aircraft of any kind be used by the Subcontractor, or by anyone else on its behalf, the Subcontractor shall contact General Contractor risk management to ensure the appropriate aircraft/aviation liability is in place. All limits, coverages, and endorsements will be set and enforced by General Contractors risk management. |
-10-
5.2.2 | Contractors Pollution Liability Insurance | ||
Should the Subcontractor or lower-tier subcontractor be involved in remediation or removal activities or disposal of hazardous substances of any kind, General Contractors risk management must be contacted to obtain instructions as to pollution liability insurance requirements. The General Contractors risk management department will establish and enforce the appropriate limits, coverages, and endorsements based on the identified exposure. |
Subcontractors of all tiers will be required to provide additional Insured status to the General Contractor for policies required in 5.1.1 and 5.1.3; |
The additional Insured status shall provide coverage for the Premises/Operations and Products/Completed Operations exposures and shall indicate that such coverage is primary to any insurance carried by the General Contractor. |
6.0 | Insurance Requirements for Excluded Parties: |
6.1 | Subcontractor and each lower-tier subcontractor shall require all Excluded Parties, as defined herein, to provide and maintain insurance of the type and in limits as set forth in the Subcontract Agreement. |
7.0 | Subcontractor Warranties and Agreements |
7.1 | All information submitted to the General Contractor or the CCIP Administrator shall be accurate and complete to the best of its knowledge. Subcontractor will notify the General Contractor or Administrator immediately in writing of any errors discovered during the performance of the work. | ||
7.2 | Neither the General Contractor, their insurance Broker, nor the CCIP Administrator are agents or guarantors of the insurance companies providing coverage under the CCIP. Nor are they responsible for claims or other disputes between any Subcontractor or lower-tier subcontractor, and the CCIP Insurers. Nor do they guarantee the solvency of any CCIP Insurer, the adequacy of the limits of liability, or that the CCIP policies provide adequate coverage terms and conditions. | ||
7.3 | General Contractor acknowledges that all references to CCIP policy terms, conditions, and limits of liability in this document, as well as the Project Insurance Manual, are for reference only. Subcontractor and its lower-tier subcontractors are responsible for conducting their own independent review and analysis of the CCIP coverages in formulating any opinion or belief as to the applicability to such coverages in the event of any loss or potential claim. |
-11-
7.4 | In the event of conflicting language, the provisions of the CCIP Insurance policies shall govern then the provisions of the Contract documents, and finally the provisions of the Project Insurance Manual. | ||
7.5 | In the event that an audit of subcontractors records, as permitted in the Contract or other CCIP documents, reveals a discrepancy in the insurance, payroll, safety, or any other information required to be provided to General Contractor or CCIP Administrator, or reveals inclusion of costs for CCIP coverages in any payment for the work, General Contractor will have the right to deduct from payments due Subcontractor all such insurance costs as well as all audit costs. | ||
7.6 | A claims charge-back will be assessed for the amount of any loss payable under the CCIP Commercial General Liability Policy. The enrolled Subcontractor or lower-tier subcontractor primarily responsible for causing any bodily injury or property damage liability loss shall be responsible for payment of the charge-back. The charge-back will equal the deductible under the Subcontractors or lower-tier subcontractors regular (non-CCIP) commercial general liability policy up to a maximum charge-back of $25,000. The minimum charge-back shall be the actual loss of $5,000 which is ever less. The charge-back shall be applied on the same basis as applied under the Contractors or subcontractors regular (non-CCIP) general liability insurance policy. All enrolled Subcontractors are required to provide the General Contractor a copy of their commercial general liability insurance deductible endorsement for the purpose of determining the charge-back. If the loss exceeds $5,000 and information necessary to determine a Subcontractors deductible as stated on its commercial general insurance endorsement is not available to the General Contractor, the General Contractor will charge the Subcontractor the actual loss up to a $25,000 maximum per occurrence until receipt of documentation from the Subcontractors commercial general insurance policy evidencing their actual deductible. If the loss is less than $5,000, the General Contractor will charge the actual loss. The charge-back does not apply to workers compensation claims for a Subcontractors own employee. | ||
7.7 | A claims charge-back will be assessed for the amount of any loss payable under the CCIP Builders Risk Policy. The first $10,000 of any such occurrence will be paid by the Subcontractor. This includes all expenses or claims payments incurred by the CCIP Insurer for losses attributable to the Subcontractors work, acts or omissions, or the work, acts or omissions of any tier of subcontractor. Subcontractor may elect to pass this charge through to any responsible subcontractor but in no event may require total subcontractor reimbursement in excess of $10,000. |
8.0 | General Contractor Obligations |
8.1 | General Contractor shall furnish each bidding Subcontractor, vendor, supplier, material dealer or other party a copy of this CCIP Exhibit and shall incorporate the terms of this Exhibit in all contracts and agreements entered into for performance of any portion of the Work. |
-12-
8.2 | Subcontractor shall enroll in the CCIP within five (5) days of receiving a request by General Contractor or its CCIP Administrator. Subcontractor shall notify each lower-tier subcontractor of the procedure for enrolling in General Contractors CCIP and confirm that enrollment is mandatory but not automatic. Subcontractor shall assure that its lower-tier subcontractors shall not commence work until verification of enrollment is confirmed by the CCIP Administrator by the issuance of a Certificate of Insurance. | ||
8.3 | Subcontractor shall not violate any condition of the policies of insurance provided by the General Contractor under the terms of this CCIP Attachment or the CCIP Insurance Manual. All requirements imposed by the subject policies and to be performed by General Contractor shall likewise be imposed on, assumed and performed by each Subcontractor and their lower-tier subcontractors. | ||
8.4 | Subcontractor shall participate in the claim reporting procedures of the General Contractors CCIP. Subcontractor agrees to assist and cooperate in every manner possible in connection with the adjustment of all claims arising out of operations within the scope of the Work provided for by the Contract awarded pursuant to the bid specifications, and to cooperate with the insurer in all claims and demands which the General Contractors insurer(s) is called upon to adjust or to defend against. General Contractor shall take all necessary action to assure that its Subcontractors and their lower-tier subcontractors comply with any such request for assistance and cooperation. | ||
8.5 | All Subcontractors and their lower-tier subcontractors shall submit monthly payrolls and worker-hour reports to General Contractor or CCIP Administrator on CCIP Form-4 Monthly On-Site Payroll Report. This reporting form will be provided to all Subcontractors at time of enrollment into the CCIP. Failure to submit these reports may result in funds being held or delayed from monthly progress payments. The CCIP Form-4 Monthly On-Site Payroll Report must be submitted for each month, including zero (0) payroll, if applicable, until completion of the Work under each Contract and Subcontract. For those Subcontractors and lower-tier subcontractors performing Work under multiple Subcontracts, a separate CCIP Form-4 is required for each Subcontract under which Work is being performed. |
9.0 | Notices, Costs |
9.1 | The cost of the insurance, specified in Paragraph 3.0 above, to be obtained by General Contractor will be paid for by the General Contractor, and the General Contractor shall receive and pay, as the case may be, all adjustments in such costs, whether by way of dividends or otherwise. General Contractor shall execute such instruments of assignment as may be necessary to permit General Contractors receipt of such adjustments and shall cause all Subcontractors and their lower-tier subcontractors covered by such insurance to do the same. |
-13-
9.2 | Any Subcontractor or lower-tier subcontractor who has completed their work at the Project site and whose CCIP insurance has been terminated, who returns to the site to perform warranty work must do so under their own insurance. | ||
9.3 | Contractors Equipment insurance for all construction tools and equipment whether owned, leased, rented, borrowed or used on work at the Project Site is the responsibility of the Subcontractor and/or lower-tier subcontractor, and the General Contractor shall not be responsible for any loss or damage to tools and equipment. This Contractors Equipment insurance shall contain a waiver of subrogation against General Contractor and/or its representatives and all approved Subcontractors and lower-tier subcontractors. If an individual approved Subcontractor or lower-tier subcontractor does not purchase such insurance, he will hold harmless General Contractor and/or its representatives and other approved Subcontractors and lower-tier subcontractors for damage to his tools and equipment. | ||
9.4 | Nothing herein shall relieve Subcontractors and their lower-tier subcontractors of their respective obligations to exercise due care in the performance of their duties in connection with the Work or to complete the Work in strict compliance with this Contract and subsequent subcontracts. | ||
9.5 | Any type of insurance or increase of limits not described above which the Subcontractor require for its own protection or on account of statute shall be its own responsibility and at its own expense. | ||
9.6 | In addition to any other rights of withholding that General Contractor may have under the Contract Documents, General Contractor has the right to withhold any payments otherwise due to the Subcontractor in the event of a failure by Subcontractor or any lower-tier subcontractor to comply with the requirements of this Exhibit C or the CCIP Insurance Manual. General Contractor may withhold from any payment owed to Subcontractor the Costs of CCIP Coverages if included in a request for payment. Such withholding by General Contractor shall not be deemed to be a default under the Construction Contract. General Contractor shall withhold from Subcontractor the Costs of CCIP Coverages attributable to an increase in Subcontractors and the lower-tier subcontractors total payroll for the Work over the amount reported to General Contractor and CCIP Administrator at time of enrollment in the CCIP. | ||
9.7 | Without limitation upon any of General Contractors other rights or remedies, any failure by Subcontractor or any lower-tier subcontractor to comply with any provision of this Exhibit C or the CCIP Insurance Manual shall be deemed a material breach of this Construction Contract, thereby entitling General Contractor, at its option, upon notice to Subcontractor to suspend performance by Subcontractor, without any adjustment to Contract Sum Payable or Contract Time, until there is full compliance, or (2) or terminate this Construction Contract for cause. |
-14-
9.8 | The provision of the CCIP shall in no way be interpreted as relieving Subcontractor or any lower-tier subcontractor of any responsibility or liability under the Contract Documents, the CCIP Policies, or Applicable Laws, including, without limitation, Subcontractors and lower-tier subcontractors responsibilities relative to indemnification and their obligation to exercise due care in the performance of the Work and to complete the Work in strict compliance with the Contract Documents. |
-15-
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 1 of 29 | |
FT DETRICK, MD |
52.202-1
|
Definitions | JUL 2004 | ||
52.203-3
|
Gratuities | APR 1984 | ||
52.203-5
|
Covenant Against Contingent Fees | APR 1984 | ||
52.203-6
|
Restrictions On Subcontractor Sales To The Government | SEP 2006 | ||
52.203-7
|
Anti-Kickback Procedures | JUL 1995 | ||
52.203-8
|
Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity | JAN 1997 | ||
52.203-10
|
Price Or Fee Adjustment For Illegal Or Improper Activity | JAN 1997 | ||
52.203-12
|
Limitation On Payments To Influence Certain Federal Transactions | SEP 2007 | ||
52.203-13
|
Contractor Code of Business Ethics and Conduct | DEC 2007 | ||
52.204-4
|
Printed or Copied Double-Sided on Recycled Paper | AUG 2000 | ||
52.204-7
|
Central Contractor Registration | APR 2008 | ||
52.209-6
|
Protecting the Governments Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment | SEP 2006 | ||
52.211-18
|
Variation in Estimated Quantity | APR 1984 | ||
52.215-2 Alt III
|
Audit and RecordsNegotiation (Jun 1999) Alternate III | JUN 1999 | ||
52.215-10
|
Price Reduction for Defective Cost or Pricing Data | OCT 1997 | ||
52.215-12
|
Subcontractor Cost or Pricing Data | OCT 1997 | ||
52.215-15
|
Pension Adjustments and Asset Reversions | OCT 2004 | ||
52.215-18
|
Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other than Pensions | JUL 2005 | ||
52.215-19
|
Notification of Ownership Changes | OCT 1997 | ||
52.215-2 1
|
Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing DataModifications | OCT 1997 | ||
52.219-4
|
Notice of Price Evaluation Preference for HUBZone Small Business Concerns | JUL 2005 | ||
52.219-8
|
Utilization of Small Business Concerns | MAY 2004 | ||
52.219-9 Alt II
|
Small Business Subcontracting Plan (Apr 2008) Alternate II | OCT 2001 | ||
52.219-14
|
Limitations On Subcontracting | DEC 1996 | ||
52.219-16
|
Liquidated Damages-Subcontracting Plan | JAN 1999 | ||
52.222-3
|
Convict Labor | JUN 2003 |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 2 of 29 | |
FT DETRICK, MD |
52.222-4
|
Contract Work Hours and Safety Standards Act Overtime Compensation | JUL 2005 | ||
52.222-6
|
Davis Bacon Act | JUL 2005 | ||
52.222-7
|
Withholding of Funds | FEB 1988 | ||
52.222-8
|
Payrolls and Basic Records | FEB 1988 | ||
52.222-9
|
Apprentices and Trainees | JUL 2005 | ||
52.222-10
|
Compliance with Copeland Act Requirements | FEB 1988 | ||
52.222-11
|
Subcontracts (Labor Standards) | JUL 2005 | ||
52.222-12
|
Contract Termination-Debarment | FEB 1988 | ||
52.222-13
|
Compliance with Davis-Bacon and Related Act Regulations. | FEB 1988 | ||
52.222-14
|
Disputes Concerning Labor Standards | FEB 1988 | ||
52.222-15
|
Certification of Eligibility | FEB 1988 | ||
52.222-21
|
Prohibition Of Segregated Facilities | FEB 1999 | ||
52.222-26
|
Equal Opportunity | MAR 2007 | ||
52.222-27
|
Affirmative Action Compliance Requirements for Construction | FEB 1999 | ||
52.222-35
|
Equal Opportunity For Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans | SEP 2006 | ||
52.222-36
|
Affirmative Action For Workers With Disabilities | JUN 1998 | ||
52.222-37
|
Employment Reports On Special Disabled Veterans, Veterans Of The Vietnam Era, and Other Eligible Veterans | SEP 2006 | ||
52.223-5
|
Pollution Prevention and Right-to-Know Information | AUG 2003 | ||
52.223-6
|
Drug-Free Workplace | MAY 2001 | ||
52.223-14
|
Toxic Chemical Release Reporting | AUG 2003 | ||
52.225-13
|
Restrictions on Certain Foreign Purchases | JUN 2008 | ||
52.226-1
|
Utilization Of Indian Organizations And Indian-Owned Economic Enterprises | JUN 2000 | ||
52.227-1
|
Authorization and Consent | DEC 2007 | ||
52.227-2
|
Notice And Assistance Regarding Patent And Copyright Infringement | DEC 2007 | ||
52.227-4
|
Patent Indemnity-Construction Contracts | DEC 2007 | ||
52.228-2
|
Additional Bond Security | OCT 1997 | ||
52.228-5
|
Insurance Work On A Government Installation | JAN 1997 | ||
52.228-11
|
Pledges Of Assets | FEB 1992 | ||
52.228-12
|
Prospective Subcontractor Requests for Bonds | OCT 1995 | ||
52.228-14
|
Irrevocable Letter of Credit | DEC 1999 | ||
52.228-15
|
Performance and Payment BondsConstruction | NOV 2006 | ||
52.229-3
|
Federal, State And Local Taxes | APR 2003 | ||
52.232-5
|
Payments under Fixed-Price Construction Contracts | SEP 2002 | ||
52.232-17
|
Interest | JUN 1996 | ||
52.232-23
|
Assignment Of Claims | JAN 1986 | ||
52.232-27
|
Prompt Payment for Construction Contracts | SEP 2005 | ||
52.232-33
|
Payment by Electronic Funds TransferCentral Contractor Registration | OCT 2003 | ||
52.233-1
|
Disputes | JUL 2002 | ||
52.233-4
|
Applicable Law for Breach of Contract Claim | OCT 2004 | ||
52.236-2
|
Differing Site Conditions | APR 1984 | ||
52.236-3
|
Site Investigation and Conditions Affecting the Work | APR 1984 | ||
52.236-5
|
Material and Workmanship | APR 1984 | ||
52.236-8
|
Other Contracts | APR 1984 | ||
52.236-9
|
Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements | APR 1984 | ||
52.236-10
|
Operations and Storage Areas | APR 1984 | ||
52.236-11
|
Use and Possession Prior to Completion | APR 1984 | ||
52.236-12
|
Cleaning Up | APR 1984 | ||
52.236-13
|
Accident Prevention | NOV 1991 |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 3 of 29 | |
FT DETRICK, MD |
52.236-15
|
Schedules for Construction Contracts | APR 1984 | ||
52.236-21
|
Specifications and Drawings for Construction | FEB 1997 | ||
52.236-26
|
Preconstruction Conference | FEB 1995 | ||
52.242-13
|
Bankruptcy | JUL 1995 | ||
52.242-14
|
Suspension of Work | APR 1984 | ||
52.243-4
|
Changes | JUN 2007 | ||
52.244-6
|
Subcontracts for Commercial Items | MAR 2007 | ||
52.248-3
|
Value Engineering-Construction | SEP 2006 | ||
52.249-2 Alt I
|
Termination for Convenience of the Government (Fixed Price) (May 2004) Alternate I | SEP 1996 | ||
52.249-10
|
Default (Fixed-Price Construction) | APR 1984 | ||
52.253-1
|
Computer Generated Forms | JAN 1991 | ||
252.203-7001
|
Prohibition On Persons Convicted of Fraud or Other Defense Contract-Related-Felonies | DEC 2004 | ||
252.204-7003
|
Control Of Government Personnel Work Product | APR 1992 | ||
252.204-7004 Alt A
|
Central Contractor Registration (52.204-7) Alternate A | SEP 2007 | ||
252.205-7000
|
Provision Of Information To Cooperative Agreement Holders | DEC 1991 | ||
252.209-7004
|
Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country | DEC 2006 | ||
252.209-7004
|
Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country | DEC 2006 | ||
252.2 19-7003
|
Small Business Subcontracting Plan (DOD Contracts) | APR 2007 | ||
252.223-7004
|
Drug Free Work Force | SEP 1988 | ||
252.223-7006
|
Prohibition On Storage And Disposal Of Toxic And Hazardous Materials | APR 1993 | ||
252.225-7012
|
Preference For Certain Domestic Commodities | MAR 2008 | ||
252.226-7001
|
Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns | SEP 2004 | ||
252.227-7022
|
Government Rights (Unlimited) | MAR 1979 | ||
252.232-7003
|
Electronic Submission of Payment Requests and Receiving Reports | MAR 2008 | ||
252.236-7000
|
Modification Proposals-Price Breakdown | DEC 1991 | ||
252.243-7001
|
Pricing Of Contract Modifications | DEC 1991 | ||
252.243-7002
|
Requests for Equitable Adjustment | MAR 1998 | ||
252.243-7002
|
Requests for Equitable Adjustment | MAR 1998 | ||
252.247-7023 Alt III
|
Transportation of Supplies by Sea (May 2002) Alternate III | MAY 2002 |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 4 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 5 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 6 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 7 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 8 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 9 of 29 | |
FT DETRICK, MD |
Construction material description | Unit of measure | Quantity | Price (dollars) | |||||||||
Item 1: |
||||||||||||
Foreign construction material |
||||||||||||
Domestic construction material |
||||||||||||
Item 2: |
||||||||||||
Foreign construction material |
||||||||||||
Domestic construction material |
||||||||||||
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 10 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 11 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 12 of 29 | |
FT DETRICK, MD |
EXHIBIT D
|
W9I2DR-09-C-0026 | |
FAR REGULATIONS |
||
USAMRIID REPLACEMENT
|
Page 13 of 29 | |
FT DETRICK, MD |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 14 of 29 | |
FT DETRICK, MD | ||
52.236-1
|
Performance of Work by the Contractor | APR 1984 | ||
52.242-14
|
Suspension of Work | APR 1984 | ||
52.246-12
|
Inspection of Construction | AUG 1996 | ||
52.246-21
|
Warranty of Construction | MAR 1994 | ||
252.201-7000
|
Contracting Officers Representative | DEC 1991 |
252.232-7007 LIMITATION OF GOVERNMENTS OBLIGATION (MAY 2006) ALTERNATE I (MAY 2006) |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 15 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 16 of 29 | |
FT DETRICK, MD | ||
On execution of contract: |
$ | 147,000,000.00 | ||
February 15 2009: |
$ | 186,000,000.00 | ||
January 15, 2010: |
$ | 94,000,000.00 | ||
January 15, 2011: |
$ | 115,000,000.00 | ||
January 15, 2012: |
$ | 10,000,000.00 |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 17 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 18 of 29 | |
FT DETRICK, MD | ||
Type | Amount | |||
Comprehensive General Liability |
$500,000 per occurrence | |||
Bodily injury or death |
||||
Motor Vehicle Liability (for each motor vehicle): |
$200,000 per person | |||
Bodily injury or death |
$500,000 per occurrence | |||
Property Damage: |
$20,000 per occurrence | |||
Workers Compensation and Employer Liability: |
$100,000 per person |
Type | Amount | |||
Comprehensive General Liability |
$500,000 per occurrence | |||
Bodily injury or death |
||||
Marine Liability |
||||
Excess towers liability |
$1,000,000 per occurrence | |||
Excess protection and indemnity insurance |
$1,000,000 per occurrence | |||
Workers Compensation and Employers Liability: |
||||
(including Longshore & Harbor Workers Compensation) |
$100,000 per person |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 19 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 20 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 21 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 22 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 23 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 24 of 29 | |
FT DETRICK, MD | ||
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 25 of 29 | |
FT DETRICK, MD |
* | WAGE DETERMINATIONS: The provisions of the Davis-Bacon Act also apply to employees who work at off-site facilities such as batch plants, rock quarries, sand pits, and the like, which are setup exclusively to furnish material to the on-site construction site. Accordingly, contractors are required to maintain complete records on such employees. However, operations of a commercial supplies or material-man established in proximity to but not on the actual site of work prior to the opening of bids are not covered by the Act even if dedicated exclusively to the Federal project for a time. (29 CFR 5.2 (1)) |
Modification Number | Publication Date | |
0
|
02/08/2008 | |
1
|
05/02/2008 | |
2
|
05/16/2008 | |
3
|
07/18/2008 | |
4
|
12/05/2008 | |
5
|
12/19/2008 |
* | ASBE0024-00l 10/0 1/2008 |
Rates | Fringes | |||||||
Asbestos Worker/Heat and Frost Insulator |
||||||||
Includes the application of all insulating materials,
protective coverings, coatings and finishes to all
types of mechanical systems |
$ | 29.18 | 14.18 |
* | ASBE0024-005 10/01/2008 |
Rates | Fringes | |||||||
Fire Stop Technician |
$ | 22.85 | 6.59 | |||||
Includes the application of materials or devices
within or around penetrations and openings in all
rated wall or floor assemblies, in order to prevent
the passage of fire, smoke of other gases. The
application includes all components involved in
creating the rated barrier at perimeter slab edges and
exterior cavities, the head of gypsum board or
concrete walls, joints between rated wall or floor
components, sealing |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 26 of 29 | |
FT DETRICK, MD |
of penetrating items and blank
openings. |
ELEC0024-00I 11/30/2008 |
Rates | Fringes | |||||||
Electricians |
$ | 32.15 | 5.25%+11.90 | |||||
IRON000S-002 06/01/2008 |
||||||||
From the waters edge of point Look-Out, Maryland
running in a straight line to the northeast City
Limits and including Parole, Maryland; from there
running in a straight line to the southern outskirts
and excluding Laurel, Maryland; from there running in
a straight line to the southern outskirts and
excluding Frederick, Maryland; from there running in a
straight line to the northwest City Limits and
including Boonsboro, Maryland; from there running in a
straight line to the southeast City Limits and
excluding Charlestown, West Virginia; from there in a
straight line to the southeast City Limits and
excluding Winchester, Virginia; from there in a
straight line to the northwest City Limits and
including Front Royal, Virginia; from there in a
straight line to the Culpeper County Line and
encompassing the County of Culpeper. |
Rates | Fringes | |||||||
Ironworkers, Structural and Sheeting |
$ | 27.83 | 12.595 | |||||
IRON00L6-002 04/01/2008 |
||||||||
From the water edge of Point Lookout, Maryland, from
there running in a straight line to the Northeast City
Limits and excluding Parole, Maryland, from there
running in a straight line to the Southern outskirts
and including Laurel, Maryland (Cherry Lane) from
there running in a straight line to the Southern
outskirts and including Frederick, Maryland, from
there running in a straight line to the Northwest City
Limits and excluding Boonesboro, Maryland, and from
there in a straight line running to the direction of
Waynesboro, Pennsylvania, from there in a straight
line to Holtwood, Pennsylvania, from Holtwood to the
Northeast Shore of Conowingo, from Conowingo to Port
Deposit, from Port Deposit using the halfway point
between Local #451 and Local #16. Offshore drilling or
construction projects 100 miles from coastal line of
Maryland. |
Rates | Fringes | |||||||
Ironworker, reinforcing and structural |
$ | 26.73 | 14.10 |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 27 of 29 | |
FT DETRICK, MD |
Rates | Fringes | |||||||
Sheeters |
$ | 26.98 | 14.10 | |||||
IRON020I -002 05/01/2008 |
||||||||
From the waters edge of Point Look Out, Maryland,
running in a straight line to the northeast City
Limits and including Parole, Maryland; from there
running in a straight line to the southern outskirts
and excluding Laurel, Maryland; from there running in
a straight line to the southern outskirts and
excluding Frederick, Maryland; from there running in a
straight line to the northwest City Limits and
including Boonsboro, Maryland; from there running in a
straight line to the southeast City Limits and
excluding Charlestown, West Virginia; from there in a
straight line to the southeast City Limits and
excluding Winchester, Virginia; from there in a
straight line to northwest City Limits and including
Front Royal, Virginia; from there in a straight line
to the Culpeper County Line and encompassing the
County of Culpeper. |
Rates | Fringes | |||||||
Ironworker (Reinforcing) |
$ | 26.15 | 12.08 | |||||
SUMD1999-003 04/07/1999 |
Rates | Fringes | |||||||
BRICKLAYER |
$ | 14.74 | .81 | |||||
Carpenters (Including Drywall Hanging and Acoustical
Ceiling-Installation) |
$ | 12.89 | 2.71 | |||||
Cement Mason/Concrete Finisher |
$ | 15.12 | 3.06 | |||||
FENCE ERECTOR |
$ | 10.28 | .85 | |||||
Glaziers |
$ | 13.60 | .99 | |||||
Laborers: |
||||||||
Mason Tenders, Brick |
$ | 8.37 | .81 | |||||
Unskilled |
$ | 9.29 | 2.81 | |||||
Painters: |
||||||||
Brush and Roller |
$ | 11.35 | ||||||
Drywall Finishers |
$ | 13.28 | .80 | |||||
Pipefitters (Including HVAC Pipe Work) |
$ | 12.21 | 3.20 | |||||
Plasterer |
$ | 13.44 | .53 | |||||
Plumbers |
$ | 12.13 | 2.04 |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 28 of 29 | |
FT DETRICK, MD |
Rates | Fringes | |||||||
Power equipment operators: | ||||||||
Backhoes |
$ | 11.31 | 2.33 | |||||
Bulldozers |
$ | 13.00 | 1.21 | |||||
Graders |
$ | 11.00 | .32 | |||||
Loaders |
$ | 15.25 | ||||||
Rollers |
$ | 12.00 | 1.68 | |||||
Roofers |
$ | 13.96 | 2.41 | |||||
Sheet Metal Worker (Including HVAC Duct Work) |
$ | 14.82 | 2.85 | |||||
Sprinkler Fitters |
$ | 12.90 | 1.15 | |||||
Truck Driver, Dump |
$ | 10.00 | 1.40 | |||||
WELDERS Receive rate prescribed for craft performing
operation to which welding is incidental.
|
||||||||
Unlisted classifications needed for work not included
within the scope of the classifications listed may be
added after award only as provided in the labor standards
contract clauses (29CFR 5.5 (a) (1) (ii)). |
||||||||
In the listing above, the SU designation means that
rates listed under the identifier do not reflect
collectively bargained wage and fringe benefit rates.
Other designations indicate unions whose rates have been
determined to be prevailing. |
(1) | Has there been an initial Decision in the matter? This can be: | |
* | an existing published wage determination | |
* | a survey underlying a wage determination | |
* | a Wage and Hour Division letter setting forth a position on a wage determination matter | |
* | a conformance (additional classification and rate) ruling |
EXHIBIT D | W9I2DR-09-C-0026 | |
FAR REGULATIONS | ||
USAMRIID REPLACEMENT | Page 29 of 29 | |
FT DETRICK, MD |
1800 West Loop South | ||
Houston, TX 77027 | ||
T: 713 860 1500 | ||
D: 713 860 8129 | ||
F: 713 860 8128 | ||
www.ies-co.com |
Manhattan Torcon A Joint Venture |
||||
By: | /s/ Ted M. Baker | |||
Ted M. Baker | ||||
Executive Vice President |
Media Contacts:
|
Edjuan Bailey, | |
713/860-1500 | ||
Edjuan.bailey@ies-co.com | ||
Laura M. Pennino, Pennino and Partners for IES | ||
281/286-9398, | ||
lp@penninoandpartners.com |